North Carolina Turnpike Authority Board of Directors Meeting August - - PowerPoint PPT Presentation
North Carolina Turnpike Authority Board of Directors Meeting August - - PowerPoint PPT Presentation
North Carolina Turnpike Authority Board of Directors Meeting August 2, 2018 4 th Quarter Triangle Expressway Update - Operations & Customer Service Kristen Pearce Back Office System Manager 2 TriEx Operations & Customer Service Update
4th Quarter Triangle Expressway Update - Operations & Customer Service
Kristen Pearce Back Office System Manager
2
Transaction Statistics
TriEx Operations & Customer Service Update
0 M 1 M 2 M 3 M 4 M 5 M Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun FY17 - Q1 FY17 - Q2 FY17 - Q3 FY17 - Q4 FY18 - Q1 FY18 - Q2 FY18 - Q3 FY18 - Q4 2009 Certified Transaction Projection Actual Transactions
FY17 - Q1 FY17 - Q2 FY17 - Q3 FY17 - Q4 FY18 - Q1 FY18 - Q2 FY18 - Q3 FY18 - Q4 Actual Transactions 11,570,102 11,706,855 11,561,253 12,675,376 12,566,202 12,657,190 12,232,513 13,780,931 2009 Certified Traffic and Revenue1 10,440,591 9,788,054 10,918,982 10,748,373 11,300,881 10,762,744 11,486,687 11,486,688 Delta 1,129,511 1,918,801 642,271 1,927,003 1,265,321 1,894,446 745,826 2,294,243 Percent of Actual vs. 2009 Base Case 111% 120% 106% 118% 111% 118% 106% 120%
1Target monthly transaction data based on annualized numbers contained in the 2009 Certified Traffic and Revenue Report developed by CDM Smith3
Toll Transactions by Type
TriEx Operations & Customer Service Update
0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100% M 1 M 2 M 3 M 4 M 5 M Jul-16 Aug-16 Sep-16 Oct-16 Nov-16 Dec-16 Jan-17 Feb-17 Mar-17 Apr-17 May-17 Jun-17 Jul-17 Aug-17 Sep-17 Oct-17 Nov-17 Dec-17 Jan-18 Feb-18 Mar-18 Apr-18 May-18 Jun-18 FY 2017 FY 2018 ETC Transactions Video Transactions ETC %
4
Monthly Transponders Sold
TriEx Operations & Customer Service Update
2,000 4,000 6,000 8,000 10,000 12,000 Jul-16 Aug-16 Sep-16 Oct-16 Nov-16 Dec-16 Jan-17 Feb-17 Mar-17 Apr-17 May-17 Jun-17 Jul-17 Aug-17 Sep-17 Oct-17 Nov-17 Dec-17 Jan-18 Feb-18 Mar-18 Apr-18 May-18 Jun-18 FY 2017 FY 2018 Sticker Hard Case Exterior
Total Transponders Sold: 397,704
5
4th Quarter Triangle Expressway Update – Finance
David Roy Director of Finance
6
TriEx Finance Update
Revenue Statistics
$0 M $1 M $2 M $3 M $4 M $5 M Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun FY17 - Q1 FY17 - Q2 FY17 - Q3 FY17 - Q4 FY18 - Q1 FY18 - Q2 FY18 - Q3 FY18 - Q4 2009 Certified Revenue Projection Actual Revenue
FY17 - Q1 FY17 - Q2 FY17 - Q3 FY17 - Q4 FY18 - Q1 FY18 - Q2 FY18 - Q3 FY18 - Q4 Actual Revenue1 $ 10,210,606 $ 10,802,362 $ 11,371,706 $ 11,625,254 $ 11,938,800 $ 11,810,005 $ 12,206,584 $ 12,982,210 2009 Certified Traffic and Revenue2 $ 7,913,993 $ 7,419,368 $ 8,468,479 $ 8,336,160 $ 8,735,177 $ 8,319,217 $ 9,332,303 $ 9,332,303 Delta ($) $ 2,296,613 $ 3,382,994 $ 2,903,227 $ 3,289,094 $ 3,203,623 $ 3,490,788 $ 2,874,281 $ 3,649,907 Percent of Actual vs. 2009 Base Case 129% 146% 134% 139% 137% 142% 131% 139%
1Actual revenue is reported on a cash basis 2Target monthly revenue data based on annualized numbers contained in the 2009 Certified Traffic and Revenue Report developed by CDM Smith7
Q1 = $10.2 M Q1 = $8.7 M Q1 = $11.9 M Q2 = $10.8 M Q2 = $8.3 M Q2 = $11.8 M Q3 = $11.4 M Q3 = $9.3 M Q3 = $12.2 M Q4 = $11.6 M Q4 = $9.3 M Q4 = $13.0 M
$0 M $5 M $10 M $15 M $20 M $25 M $30 M $35 M $40 M $45 M $50 M FY17 Actual (Total = $44.0M) FY18 Projections (Total = $35.7M) FY18 Actual (Total = $48.9M)
Revenue Statistics
TriEx Finance Update
- Revenue figures are inclusive of all toll revenue and fees, but exclude transponder revenues (YTD = $418,102.98)
- Actual revenues reported on a cash basis
YTD revenues 37.0% higher than financing base case projections YTD revenues up 11.2% year-over-year
FY 18 – 4th Quarter
8
Q1 = $3.6 M Q1 = $4.5 M Q1 = $3.5 M Q2 = $3.9 M Q2 = $4.5 M Q2 = $4.7 M Q3 = $3.9 M Q3 = $4.6 M Q3 = $4.4 M Q4 = $4.9 M Q4 = $4.6 M Q4 = $5.5 M
$0 M $5 M $10 M $15 M $20 M FY17 Actual (Total = $16.3M) FY18 Projections (Total = $18.2M) FY18 Actual (Total = $18.0M)
TriEx Finance Update
Operating Expenditures
- Actual operating expenditures reported on a cash basis
YTD expenditures 1.2% lower than projected budget
FY 18 – 4th Quarter
9
4th Quarter Triangle Expressway Update – Maintenance Report
Dennis Jernigan, P.E. Director of Highway Operations
10
TriEx Maintenance Report
Mainline Traffic Statistics
FY17 Q4 AWT = 48,900 FY18 Q4 AWT = 53,000
8% Increase
FY17 Q4 AWT = 19,200 FY18 Q4 AWT = 20,300
5% Increase
FY17 Q4 AWT = 19,000 FY18 Q4 AWT = 22,100
11% Increase
FY17 Q4 AWT = 36,600 FY18 Q4 AWT = 40,000
9% Increase
Q4: April - June AWT: Average Weekday Traffic
11
TriEx Maintenance Report
98.1 98.9 98.5 99.2 98.7 100.0 97.9 97.8 96.8 98.1 83.2 87.6 87.7 97.3 89.0 90.4 92.5 92.2 91.3 91.6 85.2 82.4 83.8 88.3* 84.4 90.9 91.1 91.3 94.0* 91.7 Unpaved Shoulders and Ditches Road Surface Drainage Structures Roadside Traffic Control Devices Overall Q1 FY 2018 Q2 FY 2018 Q3 FY 2018 Q4 FY 2018 Rolling Rating
Roadway Maintenance Statistics
* Excludes Pavement Striping/Marking, Characters and Symbols, and Pavement Markers characteristics..
12
Monroe Construction Update
Christopher Sweat, P.E. Summit Engineers
13
Monroe Expressway Overview
Monroe Construction Update
- 20-mile long expressway
- 4 to 6 lanes wide (expandable to median)
- 37 bridges
- 21 box culverts
- 8 interchanges
- Open Road Tolling
14
Important Dates
Monroe Construction Update
- Phased ITS Integration
May 2018 thru September 2018
- Substantial Completion
November 27, 2018
- Final Completion
May 28, 2019
15
Monroe Construction Update
16
Monroe Bypass Constructors, LLC
Monroe Bypass Constructors is a Joint Venture comprised of three companies: United Infrastructure Group, Inc. Anderson Columbia Company, Inc. Boggs Paving, Inc.
Monroe Construction Update
17
Toll Zone Progress
Monroe Construction Update
- AET-8 has been accepted.
- AET-7 has been accepted. Factory Acceptance Testing
(FAT) will be Aug. 6-10.
- AET-6 has been accepted.
- AET-5 has been accepted.
- AET-4 has been accepted.
- AET-3 should be accepted next week.
- AET-2 accepted by Sept. 1.
18
Monroe Construction Update
19
Marshville Area (3B)
Monroe Construction Update
20
Expressway Bridge over CSX RR and US 74WB (3B)
Monroe Construction Update
21
Expressway Bridge over CSX RR and US 74WB (3B)
Monroe Construction Update
22
Toll Site #8 (3B)
Monroe Construction Update
23
Toll Site #8 (3B)
Monroe Construction Update
24
Forest Hill School Road (3B)
Monroe Construction Update
25
Austin Chaney Rd. Interchange (3A)
Monroe Construction Update
26
Toll Site #7 (2C)
Monroe Construction Update
27
Toll Site #7 (2C)
Monroe Construction Update
28
Olive Branch Rd. and NC 200 (2C)
Monroe Construction Update
29
Toll Site #6 (2C)
Monroe Construction Update
30
Toll Site #6 (2C)
Monroe Construction Update
31
US 601 Interchange (2C)
Monroe Construction Update
32
US 601 Interchange (2C)
Monroe Construction Update
33
Sound Wall 7B2 near Fowler Rd. (2C)
Monroe Construction Update
34
Sound Wall 7B2 near Fowler Rd. (2C)
Monroe Construction Update
Toll Zone 5 and Sound Wall 7A (2B)
35
Monroe Construction Update
Toll Zone 5 and Sound Wall 7A (2B)
36
Monroe Construction Update
37
Rocky River Road Interchange (2B)
Monroe Construction Update
38
Unionville-Indian Trail Interchange (2B)
Monroe Construction Update
39
Toll Site #5 (2B)
Monroe Construction Update
40
Secrest Shortcut Rd. and Sound Wall (2A)
Monroe Construction Update
41
Indian Trail-Fairview Road Interchange (2A)
Monroe Construction Update
42
Stinson Hartis Rd. (2A)
Monroe Construction Update
43
US 74 Interchange (1)
Monroe Construction Update
44
Stallings Rd. (1)
Monroe Construction Update
45
Elevated Section (1)
Monroe Construction Update
46
Elevated Section (1)
Complete 540 Senior Underwriter Selection
David Roy Director of Finance
47
Request for Qualifications
- Select an underwriting team to support the
financing of Phase I of the Complete 540 project
- Similar to the process used for the Monroe
Expressway financing in 2016
- The RFQ was posted on May 29th
Complete 540 Senior Underwriter Selection
48
Evaluation Criteria
Experience of Firm's Primary Personnel 25% Experience with Similar Transactions 20% Plan of Finance Discussion 20% Credit/Marketing Analysis 20% Pricing 15%
Complete 540 Senior Underwriter Selection
49
Selection Process
Proposals Due The Selection Committee met to shortlist Senior Manager firms Interviews for shortlisted firms and selected recommended firm May 29th June 20th June 26th July 11th July 18th Finance Committee met to consider recommended firm
Selection Committee:
− Evan Rodewald, NCDOT Chief Financial Officer − David Roy, NCTA Director of Finance − David Miller, PFM
RFQ Posted Complete 540 Senior Underwriter Selection
50
Next Steps
Selection Committee meets to select recommended Co-Managers Finance Committee meets to consider recommended firms NCTA Board Approval of recommended firms August 2nd August September 19th November 30th NCTA Board approval of recommended Senior Manager firm Complete 540 Senior Underwriter Selection
51
Recommendation
- 20 firms submitted Statements of
Qualification
– 8 firms proposed to serve in the role of Senior Manager
- Shortlisted Firms for Senior Manager:
– Bank of America Merrill Lynch – Citi – J.P. Morgan – Wells Fargo
Complete 540 Senior Underwriter Selection
52
Volvo Trucks/FedEx Platooning
Dennis Jernigan, P.E. Director of Highway Operations
53
AVPG Designation
Volvo Trucks/FedEx Platooning
- Triangle Expressway designated as a USDOT
Autonomous Vehicle Proving Ground in January 2017
- First meeting with Volvo Trucks team in
March 2017
- Collaborated with Volvo team, NCDOT and
NCDMV on platooning legislation that was passed in July 2017
- Volvo submitted a plan for demonstration in
March 2018
- Ordinances issued by NCDOT March 29, 2018
- Demonstration began in early April 2018
54
Details of Demonstration
Volvo Trucks/FedEx Platooning
- Veridea Parkway served as the proving ground and southern
terminus of route
- Davis/Hopson interchange was used as northern terminus of
route
- Salt barn location at Green Level was used to store
tractors/trailers overnight
- Demonstration occurred outside a.m. and p.m. peak periods
- Trucks were spaced 75 to 100 feet apart as they traveled at
62 miles per hour
- All tractors had licensed drivers, each with 15+ years driving
experience Safety Was Paramount In All Demonstrations
55
Photo courtesy of The Associated Press
Volvo Trucks/FedEx Platooning
56
Drivers: Ulysses, Justin, Cindy Technical Team: Franklin, Bob, George
Volvo Trucks/FedEx Platooning
57
Volvo Trucks/FedEx Platooning
58
Media Outlets
Volvo Trucks/FedEx Platooning
59
Volvo Trucks/FedEx Platooning
60
I-485 Project Update
Rodger Rochelle Chief Engineer Carly Olexik NCTA Communications Officer
61
Public Open House Locations
I-485 Project Update
62
I-485 Project Update
63
- 320+ people attended
- Around 50 staff
answered questions
I-485 Project Update
Publicinput.com Website
July 2-31
I-485 Project Update
- 401 Comments
- 184,982 Views from
social media
- 44,675 Direct views
- 283 Participants
- 1,404 Responses
Geofencing
I-485 Project Update
- 119,157 People
Reached
- 4,655 Link Clicks
- 185,478
Impressions
- 286 Comments
Next Steps
I-485 Project Update
- New geofence ad encouraging residents
to provide feedback through the August 10 comment period
- The project team is providing responses to
all comments received
67
Thank You!