By
Niwat Thanpitinan
Wednesday 4 April 2012
Niwat Thanpitinan Wednesday 4 April 2012 About the Speaker : Niwat - - PowerPoint PPT Presentation
By Niwat Thanpitinan Wednesday 4 April 2012 About the Speaker : Niwat Thanpitinan - Suankularb College - Chulalongkorn University - Assumption University Design & Supervision 5 years Real Estate Development 4 years MRTA
By
Niwat Thanpitinan
Wednesday 4 April 2012
About the Speaker :
Niwat Thanpitinan
Design & Supervision
5 years
Real Estate Development
4 years
MRTA Initial Blue Line
5 years
Bridge Projects in London
1 year
Suvarnabhumi Airport Terminal
2 years
Luxurious Hotels in Dubai
4 years
Monorail Project in Mumbai
2 years
Project and Corporate Advisor
Present
27 Engineering Co., Ltd (General Contractor) Blunagaracha Co., Ltd (New Developer in Phuket to
supervise Gold Coast Ships, the boat designer/builder from Australia)
Seven Tides Limited (Dubai, UAE) Secco Engineering Qatar LLC (New Doha International
Airport)
Scomi International PTE LTD (Malaysia)
Palm Jumeirah, Dubai, UAE
Jumeirah Lakes Towers – Cluster Z
Ibn Battuta Gate Hotel – Roof Top
Ibn Battuta Gate Hotel - Interior
Ibn Battuta Gate Hotel – Night View
Monorail Project in Mumbai - Project Participants
Monorail Project in Mumbai - Rolling Stock Trial Run Day
Be Ready for Serious Competition
What?
One Vision, One Identity, One Community
Why?
ASEAN Free Trade Area (AFTA) ASEAN Economic Community (AEC)
When?
2015
ASEAN Economic Community: AEC
ในการประชุมผู้นําอาเซียน หรือ สมาคมประชาชาติแห่งเอเชียตะวันออกเฉียงใต้ เมื่อเดือน
ตุลาคม 2546 ได้มีการร่วมลงนามในปฏิญญาว่าด้วยความร่วมมืออาเซียน ที่เรียกว่า ข้อตกลง บาหลี 2 (Bali Concord II) เห็นชอบให้อาเซียนรวมตัวกันเป็นชุมชนหรือประชาคม เดียวกันภายในปี 2563
ต่อมาในการประชุมสุดยอดอาเซียนครั้งที่ 12 ที่เมืองเซบู ประเทศฟิลิปปินส์ เมื่อเดือนมกราคม
2550 ที่ประชุมผู้นําอาเซียนได้ตกลงร่นระยะเวลาการจัดตั้งประชาคมอาเซียนจากกําหนดเดิม ในปี 2563 เป็นให้แล้วเสร็จภายในปี 2558
ประชาคมอาเซียนที่จะจัดตั้งขึ้น ประกอบด้วยสามเสาหลัก คือ ประชาคมการเมืองและความ
มั่นคงอาเซียน (ASEAN Security Community: ASC) ประชาคมเศรษฐกิจ อาเซียน (ASEAN Economic Community: AEC) และประชาคมสังคมและ วัฒนธรรมอาเซียน (ASEAN Socio-Cultural Community: ASCC)
A contract is an agreement
entered into by two parties or more with the intention of creating a legal obligation, which may have elements in writing. Contracts can be made orally.
Two Main Parties Scope of Works Duration Value Payment Conditions Claim Procedures Variations Penalty Termination
“FIDIC” means the Fédération Internationale des
Ingénieurs-Conseils (the international federation of consulting engineers)
By Financial Transaction Lump Sum Contract Unit Rate Contract Cost Plus Fee Contract By Working Process Detailed Design Contract Design-and-Build Contract (Turnkey or EPC) Fast-track Contract Public Private Partnership (PPP)
By Others Services, Roles and Responsibilities (Feasibility
Study, Design Consultant, CM, CSC, PMC, QS, Contractor, Subcontractor, Concessionaire, etc)
Function or Project Types (Infrastructure,
Residential, Office, Commercial, Industrial, Institutional, Governmental Building)
Construction Activities (Piling, Structure,
Architecture, MEP, Interior, Landscape)
Fair Clear Amendable Enforceable Resolvable
Contract from Different Perspectives
Consultant Strict Enforcement Contractor Acceptable Fulfillment Owner Private - Optimum Achievement Government – Trouble-free Completion
verb (used with object) 1. to demand by or as by virtue
estate by inheritance.
2. to assert and demand the recognition of (a right,
title, possession, etc.); assert one's right to: to claim payment for services.
3. to assert or maintain as a fact: She claimed that he
was telling the truth.
4. to require as due or fitting: to claim respect.
Delay in Site Handover Delay in Approval from Owner/Designer/Consultant Delay in Hiring Other Interfacing Parties Discrepancies in Drawings and Other Contract Documents Obstruction by Other Interfacing Parties Stop Work from the Engineer Inclement Weather
Incorrect Non-Compliant Irrelevant
Change or Variation Order (VO)
Employer’s Change -
Addition
-
Omission
Contractor’s Change -
Mainly for improving work efficiency and speed.
-
Cost should be reduced too.
Quantity/Magnitude Quality (Specification) Sequence of Work Method of Construction
Monthly Progress Milestone Key Date Interim Payment Schedule (MRTA Initial Blue Line)
Inexcusable Delay
(T-No, M-No)
Excusable Delay
(T-Yes, M-No)
Compensable Delay
(T-Yes, M-Yes)
Concurrent Delay (T-Yes/No, M-Yes/No)
Based on CPM only Beware of Float Record of Master Schedule
Arbitration Bond Claim Disputes Engineer Force Majeure General Conditions Handover Indemnity Jurisdiction Key Dates Liquidated Damages Maintenance
Negotiation (discuss in order to reach an agreement) Mediation (intervene in a dispute to bring about
agreement)
Adjudication (give a formal decision on a dispute) Arbitration (hearing and settling of a dispute by an
impartial referee chosen by both sides)
Litigation (bring or contest a law suit / engage in legal
action)
Importance of Written Records
Correspondence Minutes of Meeting Reports (Inception, Progress, Topical, Final) Transmittals or Submittals Forms (RFI, RFC, etc) Emails
These permanent records will be useful in case of any disputes.
1. The Sub-Contract Agreement with all relevant Annexes a. Drawings (issued for Construction – Latest Rev.) b. Specifications c. Scope of Work d. Bill of Quantities 2. The Main Contract Terms and Conditions
f. Pricing and Contract Data 3. Correspondence (Letters, Faxes and Transmittal Notes) 4. Minutes of Meeting (Jointly Signed) 5. E-mails (Shall not be considered Contractual unless ……..)
Contract Manager
Preventive
Contract Administrator
Responsive
Short Form Contract (Thai) FIDIC Contract (English) Joint Venture Agreement (Consortium Agreement) Amicable Settlement Agreement Power of Attorney Addendum
Thank You & Good Bye
Contact Details
Tel : +6681 7517505 Email :
niwatomic@gmail.com
Facebook : Niwat
Thanpitinan