THURSDAY, DECEMBER 20, 2012 EAST LAND BRIDGE
1 Feasibility study by Ben C. Gerwick, Inc.
New Orleans East Land Bridge Study LPV 111 to Chef Menteur, Chef - - PowerPoint PPT Presentation
Feasibility study by Ben C. Gerwick, Inc. New Orleans East Land Bridge Study LPV 111 to Chef Menteur, Chef Menteur to Rigolets Presentation to the SLFPA.E by Dale E. Berner, PhD PE and Jean O. Toilliez, PhD, PE THURSDAY, DECEMBER 20, 2012 1
THURSDAY, DECEMBER 20, 2012 EAST LAND BRIDGE
1 Feasibility study by Ben C. Gerwick, Inc.
THURSDAY, DECEMBER 20, 2012 EAST LAND BRIDGE
2 East Land Bridge feasibility study
THURSDAY, DECEMBER 20, 2012 EAST LAND BRIDGE
3 East Land Bridge feasibility study
› Storm surge › Present day/future condition hazard › Future projects › Large collection of case studies directly connected to the East Land Bridge
THURSDAY, DECEMBER 20, 2012 EAST LAND BRIDGE
4 Existing studies
THURSDAY, DECEMBER 20, 2012 EAST LAND BRIDGE
5
LACPR Technical Report // CPRA
THURSDAY, DECEMBER 20, 2012 EAST LAND BRIDGE
6
LACPR Technical Report
" ! 100.YRP 25 12.5 400.YRP 32 12.5 1000.YRP 36 12.5
THURSDAY, DECEMBER 20, 2012 EAST LAND BRIDGE
7
LACPR Technical Report // FEMA
#$% & %' (!
100.YRP 14.6 17.9 400.YRP 17.8 21.5 1000.YRP 19.4 23.8
THURSDAY, DECEMBER 20, 2012 EAST LAND BRIDGE
8
LACPR Technical Report
THURSDAY, DECEMBER 20, 2012 EAST LAND BRIDGE
9
LACPR Technical Report
THURSDAY, DECEMBER 20, 2012 EAST LAND BRIDGE
10
LACPR Technical Report
THURSDAY, DECEMBER 20, 2012 EAST LAND BRIDGE
11 East Land Bridge feasibility study
THURSDAY, DECEMBER 20, 2012 EAST LAND BRIDGE
12
THURSDAY, DECEMBER 20, 2012 EAST LAND BRIDGE
13
THURSDAY, DECEMBER 20, 2012 EAST LAND BRIDGE
14
&- .#&! .#&! /.#&! .#&! Maximum water level 10 11.6 12.7 15.4 Minimum water level .1.8 .2.0 .2.1 .2.3 "%$% .#&$*! .#&$*! /.#&$*! .#&$*! Bay Waveland, MS 74 77 79 82 Shell Beach, LA 82 88 94 107 "011 "%$* 12 ** &3&% 73145 15 m 6.5 m (21 ft) 12.50 s 73143 20 m 7.3 m (24 ft) 12.50 s 73142 20 m 8.0 m (26 ft) 12.50 s 73141 21 m 8.8 m (29 ft) 12.50 s
THURSDAY, DECEMBER 20, 2012 EAST LAND BRIDGE
15
LACPR Technical Report
THURSDAY, DECEMBER 20, 2012 EAST LAND BRIDGE
16
LACPR Technical Report // IPCC // State guidance (Calif.) // Vermeer and Rahmstorf
4 15#+'%( Low.lying shoreline protection where primary purpose is to slow down erosion/shoreline retreat where failure would be local and limited in severity. 0.47m or 1.55ft (calculated from the mid.range VR, akin to a 50% confidence level) Critical feature (e.g. levee or floodwall) destined to protect public and private properties and where failure would be catastrophic. 0.7m or 2.3ft (upper limit of VR results, akin to a 90% confidence level)
THURSDAY, DECEMBER 20, 2012 EAST LAND BRIDGE
17
THURSDAY, DECEMBER 20, 2012 EAST LAND BRIDGE
18
THURSDAY, DECEMBER 20, 2012 EAST LAND BRIDGE
19 Statistical analyses // Buoy data // NOAA.NGDC
Blum and Roberts
THURSDAY, DECEMBER 20, 2012
20
EAST LAND BRIDGE
THURSDAY, DECEMBER 20, 2012 EAST LAND BRIDGE
21
Coastal degradation
5 7% * Petites Coquilles Visible signs of shoreline erosion
East of Unknown Pass New interior water bodies have replaced elevated vegetative cover. Alligator Bend, interior area Larger water bodies in lieu of vegetative cover.
Comparison of ELB aerial photographs, spanning approximately 30 years (1980.2011). Note that useful comparative visual data covering the West end of the ELB is not
THURSDAY, DECEMBER 20, 2012 EAST LAND BRIDGE
22
Penland et al. Location of shore.normal transects for Lake Borgne. From (Penland et al. 2002) Measured trends in shoreline rates for transects 27.38, as per . Bars indicate historical trends, as recorded between 1850 to 1995. Curves represent more recent trends.
Reference: Penland, S., A. Beall, D. Britsch, and S.J.
!". New Orleans, LA: U.S. Geological
THURSDAY, DECEMBER 20, 2012 EAST LAND BRIDGE
23 › Data provided by USGS reveals that at the ELB, the historical average shoreline movement rate is 5.7ft/year, with accelerating trends recorded in more recent epochs › Between 1930 and 1995, the rate is approximately 9.4ft/year › Slows down to 7.2ft/year when measured between 1960 to 1995: restoration projects › While no data exists for the region of the ELB located at the Lake Pontchartrain side › Assume from satellite imagery that this area is less likely to undergo coastal recess rates as severe as those recorded on Lake Borgne side › Prone to severe retreat
› Alligator Bend has the fastest recorded rate of erosion with over 12ft per year; › Justifies the on.going shoreline protection efforts
THURSDAY, DECEMBER 20, 2012 EAST LAND BRIDGE
24
LACPR // USGS // Design values
5 6 * 1%+'(! [m] [m] Low Average High Chef Menteur, LA 229904 3329253 0.15 (0.49) 0.35 (1.15) 0.6 (1.97) Michoud, LA 217710 3325564 0.35 (1.15) 0.75 (2.46) 1.2 (3.94) 5 1%
1% + '(! 1% / +'(! ELB 3.0 0.15 (0.50) 0.30 (1.0)
THURSDAY, DECEMBER 20, 2012 EAST LAND BRIDGE
25
Anticipating changes and implementing solutions
THURSDAY, DECEMBER 20, 2012 EAST LAND BRIDGE
26
&$ 5 1$ PO.22
Shoreline protection against wave action on marsh Bayou Chevée area NRCS (federal) and LACPR (state) PO.34
Shoreline protection and marsh restoration South.west bend
USACE (federal) and LACPR (state)
THURSDAY, DECEMBER 20, 2012 EAST LAND BRIDGE
27 East Land Bridge feasibility study
THURSDAY, DECEMBER 20, 2012 EAST LAND BRIDGE
28 Risk reduction and shoreline stabilization
Risk framework: USACE ER 1105.2.100 (USACE 2000)
THURSDAY, DECEMBER 20, 2012 EAST LAND BRIDGE
29
Plan Formulation
THURSDAY, DECEMBER 20, 2012 EAST LAND BRIDGE
30
Plan Formulation
THURSDAY, DECEMBER 20, 2012 EAST LAND BRIDGE
31
Measure selection
Limit realm of potential measures to well.defined and recognized framework
Lopez, J., and M. Davis. #$ # %&%' ( !) ! & . New Orleans, LA: Lake Pontchartrain Basin Foundation, April 2011. Lopez, J., N. Snider, C. Dufrechou, M. Hester, and
&*' + &&% ,--.( /012. New Orleans, LA: Lake Pontchartrain Basin Foundation, 2009.
THURSDAY, DECEMBER 20, 2012 EAST LAND BRIDGE
32
90% )* 1* $ 6%**2+ 5
net benefit for flood reduction Potential for regional.scale surge reduction. Promotion of low.energy climate. Increases natural wildlife habitat. May reduce incoming wave energy during storm surge Limit coastline recess and provides benefits for marsh restoration projects. Strengthens ELB's role as flood defense line by maintaining current marsh area. Leverages US90 alignment and provides direct protection against moderate storm surge with limited impact on local system Physical, high. crested line of defense against moderate to severe storm surge Enhanced potency of flood risk reduction system with ability to hydraulically lock LP Positive acceptability factors
define new protection status to large areas; enlargement
wildlife refuge. Remote location and low social impact.
benefits with low disruption to existing landscape.
habitat and promotes favorable environmental conditions.
as building block for replanting and restoration efforts.
material. Reduced footprint Opportunities for including small.scale restoration projects along US 90 alignment.
ecological impact during/after construction.
blocks for replanting/marsh revitalization efforts.
integrated into state park or recreation areas with bike/walk paths, beaches, etc.
revaluation of nearby natural landscape Negative acceptability factors
existing landscape.
direct, measurable reduction in storm surge in densely populated areas.
change in sea.level.
environmental disruption during marsh nourishment phase.
restoration subject to limited quantity and availability.
building material and potential disruption to natural habitat.
be conducted in sensitive areas.
would require upgrades to existing infra.structures that would affect local ecosystem.
issues; inhabited areas may be left unprotected
landscape and local ecosystem.
construction may incur environmental impact; mitigating measures should be enforced.
and/or prolonged pass closures
THURSDAY, DECEMBER 20, 2012 EAST LAND BRIDGE
33
7- :3%$ 4 / Background study Literature/Data collection $10,000
Grid generation, model setup, model calibration, simulations $40,000 ; Salinity Model setup, calibration and simulations $10,000
Calculation of Lagrangian currents $5,000 Temperature Model setup, simulations $10,000
Determination of dominant bio.chemical processes and corresponding parameters, model setup and simulations $10,000 < Nutrient supply Determination of dominant bio.chemical processes and corresponding parameters, model setup and simulations $10,000 1=9:7:5'%( $95,000
Determination of bottom sediment properties and sediment intake, model setup and simulations $10,000 > Other water quality parameters Additional modeling efforts for specific parameters $5k to 10k :7:5'%( $115,000 ?$$+@+-@%A+B/
Post.feasibility study: establish performance of gates
Determine the fate of water quality during closures spanning from one week to a month Estimate the time needed for the local ecosystem to recover from the closure and restore itself to pre.closure conditions after the lake is re.connected to Lake Borgne Performance of non. traditional/composite gate structures aimed at minimizing hydrologic disruption
THURSDAY, DECEMBER 20, 2012 EAST LAND BRIDGE
34
Performance criteria
) &- %%% #% 1 1 2 Levee
Selected for next screening round Armored berm
Selected for next screening round Augmented berm
This measure was eliminated from further consideration because of potential cost and acceptability issues. The measure would necessarily interfere
Bend) Barrier Island
This measure does not properly address storm surge reduction and is incomplete: the concept spans outside the realm of authority of the SLFPA.E. Elevated highway
This measure leaves out a large area of ELB vulnerable to shoreline erosion and marshland loss. Alignment does not line up with interests of stakeholders. Objective 1 To reduce flood risk at the LPB by placing a physical flood barrier against storm surge. Objective 2 To preserve the integrity and encourage efforts to expand and strengthen the shoreline at the ELB.
THURSDAY, DECEMBER 20, 2012 EAST LAND BRIDGE
35
› Armored berm
› Shoreline/foreshore protection alone is limited › Small.scale protection measures can only limit dame sustained from minor events.
› Very potent flood risk reduction measure
› No direct answer to shoreline stabilization › Cost and real estate constraints
› Trade.off conceded
› Higher level of flood protection at the expense of a more focused foreshore and shoreline stabilization project (FSSP). › Trade.off is modulated favorably by the presence of on.going foreshore stabilization (Alligator Bend Marsh Restoration and Shoreline Protection) › CLEAR assessment strongly indicates that these efforts should have tangible impact on the marshland. Consequently, the armored berm option is given a lower priority.
Plan formulation: conclusion
&+
High.crested levee Feasibility study and conceptual design of high.crested levee protection at ELB.
FSSP evaluation and monitoring program Track success through quantifiable metrics such as a regrowth index, organic top.layer measurements; aerial photo and on.site collection campaign.
Complement/augment existing FSSP with ad.hoc measures wherever required. Conditioned to efficacy of high.crested levee in limiting storm surge, augment and/or complement existing FSSP at critical areas where shoreline stabilization is critical and participates in improving the efficacy of the flood control system.
THURSDAY, DECEMBER 20, 2012 EAST LAND BRIDGE
36 East Land Bridge feasibility study
THURSDAY, DECEMBER 20, 2012 EAST LAND BRIDGE
37
ADCIRC/SWAN modeling
and marshland within the project area and their impact on hurricane storm surge hazard;
Chef Menteur and Rigolets passes
structure on the time and spatial redistribution of storm surge near the ELB. Define case studies
THURSDAY, DECEMBER 20, 2012 EAST LAND BRIDGE
38
4 1
' %( #15#! '%+ %% ( "** '( ! $$C
! Overtopping barrier.weir considered for testing in the LACPR (shown for reference; see Section 2.2.6) 12.5 100.YRP level 18 2.6 6 22 400.YRP level 21.5 2.6 8 26 Non.overtopping barrier considered for testing in the LACPR (shown for reference; see Section 2.2.6) 100.YRP level 25 400.YRP level 32
Numerical investigation: preliminary design parameters to be tested for efficacy
Project alignment for tentative levee concept (orange line). The proposed path follows a simpler alignment than a similar alignment considered in the LACPR Technical Report. Establishment of crest elevation for levees based on storm surge elevation assessment from LACPR Technical Report. Future conditions for surge elevations are those reported for the Or.leans area, and correspond to Future Case 2, featuring a more conservative SLR projection. Case studies to integrate a high.crested levee, with a crest elevation of 22 ft.NAVD88
THURSDAY, DECEMBER 20, 2012 EAST LAND BRIDGE
39 ADCIRC/SWAN modeling
THURSDAY, DECEMBER 20, 2012 EAST LAND BRIDGE
40 ADCIRC/SWAN modeling
ADCIRC/SWAN modeling
THURSDAY, DECEMBER 20, 2012 EAST LAND BRIDGE
41 › BASE CASE › FWOA.ELB.intact
› Future without Action (FWOA) scenario › ELB remains intact and vegetated.
› Basis for comparison with most scenarios
› SCENARIO 1
› FWOA.ELB.degraded
› where the ELB has been allowed to erode and disappear.
› Estimate the role of the ELB topography and vegetation in suppressing storm surge in Lake Pontchartrain.
› SCENARIO 2
› Levee.Gate.Closed.ELB.intact
› Proposed levee across the ELB with no openings at the Chef Menteur and Rigolets passes. › Hydraulically isolates Lake Pontchartrain from Lake Borne and the Gulf of Mexico.
› Approximate the redistribution of storm surge at nearby locations
› SCENARIO 3
› Levee.Gate.Open.ELB.intact aka "Open.pass.intact"
› Openings at the Chef Menteur and Rigolets passes.
› Estimate the change in surge response within Pontchartrain and at nearby locations including the Mississippi coast.
› SCENARIO 4
› Levee.Gate.Open.ELB.degraded aka "Open.pass.degraded"
› Open gates and anticipates a degraded ELB
› Measure the impact of coastline degradation on the storm surge time/space distribution in Lake Pontchartrain and vicinity.
ADCIRC/SWAN modeling
THURSDAY, DECEMBER 20, 2012 EAST LAND BRIDGE
42
SCENARIO 1 vs. BASE CASE
Coastline recess rate Adopt “road maintained” scenario so that the highways are assumed to be maintained at current elevation (through mitigating measures) Anticipated profile evaluation Evaluate impact of degradation on efficacy
without flood control system Smart shift of ELB terrain along delineated area: focused assessment
THURSDAY, DECEMBER 20, 2012 EAST LAND BRIDGE
43
SCENARIO 1 vs. BASE CASE
THURSDAY, DECEMBER 20, 2012 EAST LAND BRIDGE
44
SCENARIO 2 vs. BASE CASE
THURSDAY, DECEMBER 20, 2012 EAST LAND BRIDGE
45
SCENARIO 3 vs. BASE CASE
THURSDAY, DECEMBER 20, 2012 EAST LAND BRIDGE
46
SCENARIO 4 vs. SCENARIO 3
THURSDAY, DECEMBER 20, 2012 EAST LAND BRIDGE
47
ADCIRC/SWAN modeling
THURSDAY, DECEMBER 20, 2012 EAST LAND BRIDGE
48
ADCIRC/SWAN modeling
THURSDAY, DECEMBER 20, 2012 EAST LAND BRIDGE
49
ADCIRC/SWAN modeling
THURSDAY, DECEMBER 20, 2012 EAST LAND BRIDGE
50 East Land Bridge feasibility study
THURSDAY, DECEMBER 20, 2012 EAST LAND BRIDGE
51 Recommendations
THURSDAY, DECEMBER 20, 2012 EAST LAND BRIDGE
52
STEP 1
Timeline for adaptive construction sequence, starting with the construction of a base design. Base design Bring protection to the 100.year level within a 20.year horizon. A final upgrade, scheduled to be completed 30 to 50 years from present day, is aimed at bringing the level of protection to the 400.year level by means of a hard structure (I, L or T.wall or batter.pile). 100.YRP levee 400.YRP levee Detailed assessment of settlement needed 2.3 ft. settlement over 50 years anticipated for rock wall by Geoengineering
THURSDAY, DECEMBER 20, 2012 EAST LAND BRIDGE
53
THURSDAY, DECEMBER 20, 2012 EAST LAND BRIDGE
54 STEP 1
THURSDAY, DECEMBER 20, 2012 EAST LAND BRIDGE
55 ACU or heavy riprap Heavy overtopping and complete submergence Conservative design, robust structure capable of withstanding the most critical situations
THURSDAY, DECEMBER 20, 2012 EAST LAND BRIDGE
56 Recommendations
THURSDAY, DECEMBER 20, 2012 EAST LAND BRIDGE
57 STEP 2
THURSDAY, DECEMBER 20, 2012 EAST LAND BRIDGE
58
STEP 3
THURSDAY, DECEMBER 20, 2012 EAST LAND BRIDGE
59
STEP 3
THURSDAY, DECEMBER 20, 2012 EAST LAND BRIDGE
60
Conclusion
THURSDAY, DECEMBER 20, 2012 EAST LAND BRIDGE
61
Conclusion
THURSDAY, DECEMBER 20, 2012 EAST LAND BRIDGE
62