- Sept. 17, 2019
1 of 13
Montlake Project Monthly Construction Update
John Welch Director of Construction, Graham Contracting, LTD
Montlake Project Monthly Construction Update Sept. 17, 2019 John - - PowerPoint PPT Presentation
Montlake Project Monthly Construction Update Sept. 17, 2019 John Welch Director of Construction, Graham Contracting, LTD 1 of 13 Agenda Agenda Project summary Progress to date Whats to come How to stay informed
1 of 13
John Welch Director of Construction, Graham Contracting, LTD
Saw cutting barrier on 24th Avenue overpass. 2 of 13
Rendering of the Montlake area at completion. Montlake area today. 3 of 13
Current rendering of pedestrian land bridge (7/2019). Rendering of pedestrian land bridge in response to RFP Plan (11/2018). WSDOT RFP concept of pedestrian land bridge (2018). 4 of 13
Westbound Montlake off-ramp, looking west. Installation of retaining wall north of Montlake Boulevard westbound off-ramp. Finished retaining wall north of SR 520 westbound off- ramp. 5 of 13 Installation of the noise panels. Trees flagged for removal. Equipment staging at the former MOHAI site.
6 of 13 Removal of the SR 520 Trail railing. Drainage installation. Asphalt placement. Asphalt compacting. New SR 520 Trail connection.
westbound SR 520
Arboretum ramp closure Graham will close westbound SR 520 the weekend of Oct. 5-6. During the closure, crews will set up temporary barrier, as well as pave and stripe the road. Following the weekend closure, westbound travelers will drive on a new SR 520 roadway between 24th Avenue East and Montlake Boulevard. Graham will shift all eastbound traffic over Lake Washington to the existing westbound bridge on Oct. 28, at the conclusion of the weekend work. Work will require a closure of both directions of SR 520 to switch traffic. In the weeks following the traffic shift to the westbound bridge, the eastbound Arboretum on-ramp will permanently close.
WSDOT will drill near the Montlake Market and 76 gas station during the daytime to evaluate the extent of soil contamination for future clean up.
Major upcoming activities
7 of 13 *The existing eastbound on-ramp will remain open until the temporary eastbound on-ramp is constructed and open to traffic in late November. *
Montlake area looking west.
8 of 13
different levels and kinds of noise.
stricter rules for noise levels and the types of equipment allowed.
levels throughout the project area.
Construction Noise Variance, which allows higher decibel levels than normally allowed by city ordinance for noise between 10 p.m. and 7 a.m.
days a week throughout construction.
(impact) work: – 7 a.m. to 10 p.m. weekdays – 9 a.m. to 10 p.m. weekends and holidays Independent noise monitors will be present for night work to ensure compliance with specified noise levels.
9 of 13
Our 24-hour hotline is the best way to report noise complaints and have concerns addressed in the moment.
10 of 13
11 of 13
www.wsdot.wa.gov/projects/sr520/montlake
upcoming construction: www.sr520construction.com
sr520bridge@wsdot.wa.gov
– Monday and Wednesday from noon to 6 p.m. – Tuesday and Thursday from 8 a.m. to noon – Third Saturday of the month from 9 a.m. to noon
12 of 13
Before you leave:
updates
stay in touch
13 of 13