SR 520 Program Public Meeting: Montlake Market property May 23, - PowerPoint PPT Presentation

SR 520 Program Public Meeting: Montlake Market property May 23, 2019 Dave Becher Penny Mabie SR 520 Program Director of Construction Meeting facilitator David Goldberg SR 520 Program Ombudsman 1 Meeting welcome, agenda WSDOT


  1. SR 520 Program Public Meeting: Montlake Market property May 23, 2019 Dave Becher Penny Mabie SR 520 Program Director of Construction Meeting facilitator David Goldberg SR 520 Program Ombudsman 1

  2. Meeting welcome, agenda • WSDOT Presentation • Q&A session • Public feedback • Closing remarks • Meeting adjourns – 7 p.m. Conceptual rendering of a public outlook at west end of a new Montlake lid, looking west. 2

  3. SR 520: Montlake Project and the “Rest of the West” 3

  4. SR 520 Montlake Project and the Montlake Market • WSDOT’s need for market and gas station property • Legislature’s 2018 directive to WSDOT • Soliciting community feedback 4

  5. WSDOT’s Montlake Market survey • Jan. 30 - Feb. 14 online survey • 1,729 responses • Strong support for market, but diverse opinions on cost • Many opposed to WSDOT using property for entire duration of SR 520 reconstruction • High interest in how property is used after Montlake Project construction • Survey report link: https://www.wsdot.wa.gov/sites/default/files/2019/03/22/SR520-Report- MontlakeMarket-Survey-web.pdf 5

  6. Discussions with the Community and Legislature • WSDOT discussed Montlake Market with legislators:  Potential to avoid disturbance of building  Estimated $20 million cost to preserve market operations  Property’s contamination • Legislators could not support added project costs, but wanted to address community’s interests 6

  7. Legislature’s new directive • New proviso in 2019-2021 transportation budget • Directs WSDOT to:  Offer lease to Montlake Market until Jan. 1, 2020  Identify area on or near market property for temporary market or food service to operate during construction  Sell market property after Montlake Project complete … 5 to 6 years sooner than previously planned 7

  8. What does the Legislature’s new directive mean? • WSDOT needs gas station and market property • Close and remove gas station • Clean up soil and groundwater contamination • Close and remove Montlake Market building • Sell property after Montlake Project • Work to provide an area for a is completed – about six years temporary market / food service sooner than previously planned during construction 8

  9. Next steps • May - June 2019:  WSDOT and property owner reached sale agreement  Negotiate temporary lease with gas station  Negotiate Montlake Market lease to Jan. 1, 2020 • Summer 2019:  Close gas station  Additional soils and groundwater testing 9

  10. Next steps, cont’d • Summer-fall 2019:  Confirm cleanup plan  Begin gas station cleanup  Offer current Market operators opportunity to operate temporary market or food service  If current operators decline, solicit offers from other potential market or food-service vendors 10

  11. Next steps, cont’d • Jan. 1, 2020:  Montlake Market lease ends • Early 2020:  Provide area for temporary market / food service  Relocate cell tower Cleanup of a former gas-station site  Remove Market building  Clean up market area • 2023 (currently anticipated):  WSDOT completes Montlake Project, sells remainder of property 11

  12. Montlake Project engagement • Summer 2019: • June 6, 2019:  Montlake Project monthly  Montlake Project design and public meetings begin preconstruction open house  Montlake Project drop-in 5:30–7:30 p.m. o information center opens St. Demetrios o 12

  13. Your questions (20 min.) Your feedback Graham Contracting’s conceptual rendering (20 min.) of a new Montlake lid and reconstructed SR 520, looking west. Closing remarks 13

  14. Thank you! Email us at: SR520Bridge@wsdot.wa.gov SR 520 Construction Corner https://sr520Construction.com Graham Contracting’s conceptual rending of a pedestrian and bicycle land bridge over SR 520, in Montlake. Tonight’s presentation will be online at: https://www.flickr.com/photos/wsdot/sets/72157703288866895/ Presentation also linked from the SR 520 Program website: www.wsdot.wa.gov/projects/sr520bridge 14

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.