Muon Accelerator Program Monthly Status Review December 14, 2012 - - PowerPoint PPT Presentation

muon accelerator program monthly status review
SMART_READER_LITE
LIVE PREVIEW

Muon Accelerator Program Monthly Status Review December 14, 2012 - - PowerPoint PPT Presentation

Muon Accelerator Program Monthly Status Review December 14, 2012 Outline Introduction MAP Management Update L2 Manager Updates AOB December 14, 2012 MAP Monthly Status Report 2 Introduction Goals for our monthly status


slide-1
SLIDE 1

Muon Accelerator Program Monthly Status Review

December 14, 2012

slide-2
SLIDE 2

Outline

  • Introduction
  • MAP Management Update
  • L2 Manager Updates
  • AOB

December 14, 2012 MAP Monthly Status Report 2

slide-3
SLIDE 3

Introduction

  • Goals for our monthly status meetings

– Provide a chance to systematically check on all of the major activities that are presently underway – Aid in tracking program progress and issues – Identify areas needing further support

  • Hope to maintain a fairly uniform rotation

between all of the L1 research areas for the remainder of each month’s Weekly Meetings

  • Will also want some special updates. For

example:

– MASS Working Group Status Report – High Level Program Updates

December 14, 2012 MAP Monthly Status Report 3

slide-4
SLIDE 4

Some Important Dates

  • Next MICE Collaboration Meeting: February 14-16 @RAL
  • DOE (mini-)Review: March 5-6 @FNAL

– Review to focus on updated management plan – Follow up on issues identified during August review

  • Muon Collider Higgs Factory Workshop: March 21-23

@UCLA

  • Keep an eye on the CSS2013 pre-meeting calendar:

http://www.snowmass2013.org/tiki-index.php?page=premeetings

  • PASI Workshop: April 3-5 @RAL (with contiguous IDS-NF

meeting)

  • Lehman-style review of MICE Construction activities targeted

for April-May timescale

  • IPAC `13: May 12-17, Shanghai, China
  • MAP Collaboration Meeting: May @FNAL (please email any

known conflicts)

December 14, 2012 MAP Monthly Status Report 4

slide-5
SLIDE 5

MAP Management Update I

  • Major efforts currently focus on:

– Updated program management structure at Fermilab

  • Project 29M
  • Updated structure to handle Pass-through funds at Fermilab
  • Implementation of PMO: Project scheduling, accounting and tracking

– Completing FY12 reporting requirements – Detailing FY13 plans – Resource-loaded schedule and detailed budget profiles for MICE construction effort – Updated Program Management Plan

  • Adjustments for managing program as a project
  • Review of programmatic needs
  • Implement dedicated management structure for MICE Construction

Activities

– In consultation with DOE-OHEP – Support integrated international MICE Construction framework (DOE-STFC driven change) – Prepare for more rigorous review cycle in the next year

  • Available for review in January 2013

December 14, 2012 MAP Monthly Status Report 5

slide-6
SLIDE 6

MAP Management Update II

  • Preparations for “Snowmass on the Mississippi”

– MASS WG is implementing a plan to complete a set of studies to evaluate specific staging options – Coordinator assignments are being made for the required white paper

  • Collaborations:

– Several opportunities are presenting themselves for new international MAP involvement

  • Italy
  • China
  • Russia

December 14, 2012 MAP Monthly Status Report 6

slide-7
SLIDE 7

L2 MANAGER STATUS REPORTS: DESIGN & SIMULATION (WBS 2)

December 14, 2012 MAP Monthly Status Report 7

slide-8
SLIDE 8

Milestone Status (Progress) Resource Conflicts, Plan Changes and Issues Late Items Summary of Previous Month Quarterly Plans Upcoming Work (Next Month)

Monthly L2 Status Report -

WBS: Presenter:

  • In progress: Project X – MAP Task Force Report
  • To be started: IDS-NF Proton Driver costing study
  • Observation of Project X evolution to staging and ensuring that

Project X can be upgraded to be proton driver

  • Participated in bi-weekly Target Studies Meeting
  • Participated in Project X siting
  • “Project X Proton Source” for Muon collider Higgs Factory Mini-

Workshop

  • 2nd iteration of Task Force Report
  • Initiate work on siting of proton rings with new Project X layout

followed by possible target through acceleration layout(s)

  • Develop Accumulator and Compressor Rings
  • Develop Compressor Ring extraction line to target for NF
  • IDS-NF Proton Driver description and costing
  • Investigate re-use of Project X pulsed linac for muon

acceleration

  • Task Force Report
  • Task Force team focused on other topics

14 December 2012

02.01 – Proton Driver Keith Gollwitzer

slide-9
SLIDE 9

Milestone Status (Progress) Resource Conflicts, Plan Changes and Issues Late Items Summary of Previous Month Quarterly Plans Upcoming Work (Next Month)

Monthly L2 Status Report -

WBS: Presenter:

Current Outstanding Activities

  • Decay Channel Chicane (Rogers, Neuffer)
  • Capture Taper (Sayed)
  • Update Cooling Channel (Stratikis)
  • Front End Element Alignment (Prior)
  • Optimization Algorithms (Sayed, Ryne, Qiang)
  • Evaluation of Decay Channel Stop Bands (Sayed)
  • IDS120k coil configuration (Weggel)
  • ICOOL, G4Beamline comparison (rogers,Snopak)
  • Establish Chicane Scenario (Rogers, Neuffer)
  • Decay Channel Chicane- Re-optimized Phase rotator
  • Capture Taper – Evaluate 15T peak field option
  • Update Cooling Channel – Evaluate 7 cell option
  • Front End Element Alignment – Front End Progress report
  • Optimization- Parallelized ICOOL, Install MARS at NERSC
  • Decay Channel – Evaluate Coil/Shielding Scenario
  • Capture Taper – Determine optimal peak/end fields
  • Update Cooling Channel
  • Front End Element Alignment Determine Alignment

sensitivities

  • Optimization Algorithms – Optimize Front End Phase rotator

and Cooling channel parameters

14 December 2012

02.02 Harold Kirk

slide-10
SLIDE 10

Milestone Status (Progress) Resource Conflicts, Plan Changes and Issues Late Items Summary of Previous Month Quarterly Plans Upcoming Work (Next Month)

Monthly L2 Status Report -

WBS: Presenter:

  • Guggenheim D&S

– Diktis is progressing with last stage

  • HCC D&S

– No funding

  • FOFO Snake D&S

– Uncertain

  • Final Cooling D&S

– Bob Palmer is progressing

  • STTR Phase II proposal submitted for HCC D&S (MuPlus)
  • SBIR/STTR Phase I proposal submitted for Advanced

Modeling Tools (MuPlus)

  • Construct WBS, milestones, and work packages
  • Guggenheim D&S
  • HCC D&S
  • FOFO Snake D&S
  • Final Cooling D&S
  • 6D Baseline Selection

– Need some preparatory work – (Basically on hold awaiting the other 6D D&S tasks)

  • Guggenheim D&S
  • HCC D&S
  • FOFO Snake D&S
  • Final Cooling D&S
  • HCC D&S
  • FOFO Snake D&S
  • Need funding for HCC D&S

– Awaiting STTR Phase II grant (~ March 2013)

  • Need funding for FOFO Snake D&S (uncertain)

14 December 2012

02.03 Cooling Tom Roberts

slide-11
SLIDE 11

Milestone Status (Progress) Resource Conflicts, Plan Changes and Issues Late Items Summary of Previous Month Quarterly Plans Upcoming Work (Next Month)

Monthly L2 Status Report -

WBS: Presenter:

  • MAD designs for NF Linac & RLAs, transfer line Linac to RLA1
  • Hybrid synchrotron lattice: working on code updates
  • Fill in acceleration chain: not begun
  • MAD designs for NF Linac and RLAs completed, sent to

Daresbury engeering

  • Calculations mostly in place for updated design optimization

code (on-the-fly model swapping: hybrid synchrotron and FFAG designs). Beginnings of code structure in place.

  • Finish off optimization code, begin validation
  • RLA1 to RLA2 transfer line design in response to Daresbury
  • Q2: studies of hybrid synchrotron cell structure with new code
  • Q3: look at FFAGs in acceleration chain
  • Hybrid synchrotron
  • With increased resources: detailed tracking studies for Linac/

RLA chain

14 December 2012

02.04 Acceleration & Decay Rings

  • J. Scott Berg
slide-12
SLIDE 12

Milestone Status (Progress) Resource Conflicts, Plan Changes and Issues Late Items Summary of Previous Month Quarterly Plans Upcoming Work (Next Month)

Monthly L2 Status Report -

WBS: Presenter:

  • Optimizing the Higgs Factory (HF) collider lattice design to

avoid reverse bends and reduce the circumference.

  • Requirements to the Higgs Factory collider lattice formulated.
  • Optimum β* for the expected beam emittance determined.
  • New design of the HF collider lattice developed featuring:
  • a quadruplet Final Focus for the detector background

reduction,

  • tunable β* in the range 1.5cm – 10cm,
  • large momentum compaction factor (~0.1) .
  • Continued optimization of the HF collider lattice design.
  • Start of the beam dynamics simulations in HF with account of

fringe fields and multipole errors once the preliminary magnet design is available.

  • Development of the Higgs Factory collider lattice design.
  • Work on the 3TeV collider lattice suspended until the

background reduction with the quadruplet Final Focus is validated by MDI simulations in the Higgs Factory case

14 December 2012

02.05 Collider Ring Design

  • Y. Alexahin
slide-13
SLIDE 13

Milestone Status (Progress) Resource Conflicts, Plan Changes and Issues Late Items Summary of Previous Month Quarterly Plans Upcoming Work (Next Month)

Monthly L2 Status Report -

WBS: Presenter:

  • Complete planned developments of physics and geometry

modules of MARS15 for adequate modeling of backgrounds in MC detectors: new ROOT-based geometry is up and running; developments and tests of substantially updated electromagnetic shower (EMS) modules with precise modeling down to 1 keV are nearing completion.

  • Higgs Factory (HF) IR lattice is almost ready for use within

MARS for MDI studies.

  • HF IR magnet design is agreed upon.
  • Finishing EMS module developments and tests in MARS.

Benchmarking showed amazing performance.

  • Iterations done on the HF IR lattice and magnet designs.
  • Timing and double-layer rejection studies finished for a 1.5-TeV

MC with latest ILCRoot version and showed these techniques to be very promising.

  • Agreed on a HF detector design (SiD with CMS phase 2

tracker) and machine MDI study priorities (HF, then 3 TeV).

  • Once a consistent design of HF IR quads and dipoles is

finished (in early January?), implement these into MARS along with a final (?) lattice; build the MDI model and prepare the first test runs with a toy detector.

  • Start building a HF detector model under lcsim aiming at its

implementation to MARS in Q2.

  • Q2: Build a complete consistent MARS model of the HF IR,

magnets, detector and preliminary MDI and magnet protection

  • system. Perform first runs to address IR magnet performance

and background loads on sub-detectors. Prepare timing and double-layer rejection techniques for the HF lcsim detector model (if it is built).

  • Q3: Optimization of HF magnet protection system and MDI.

Production MARS runs to feed the detector studies. With this source, launch full detector simulations (if the lcsim model built).

  • MDI priorities changed from a 3 TeV MC to a Higgs Factory.
  • Who will build a first lcsim version of a HF detector? SLAC?

Fermilab (Hans, Ron, Nikolai T. et al) with INFN help?

14 December 2012

02.06 - Machine-Detector Interface

Nikolai Mokhov

slide-14
SLIDE 14

L2 MANAGER STATUS REPORTS: TECHNOLOGY DEVELOPMENT (WBS 3)

December 14, 2012 MAP Monthly Status Report 14

slide-15
SLIDE 15

Milestone Status (Progress) Resource Conflicts, Plan Changes and Issues Late Items Summary of Previous Month Quarterly Plans Upcoming Work (Next Month)

Monthly L2 Status Report -

WBS: Presenter:

  • Modular cavity (collaboration with SLAC)

– RF Design (cavity optimization, Multpacting (MP) simulations with external magnetic field) – Fabrication (cavity body, waveguide, Be & Cu plates), post- processing and testing

  • 201 MHz cavity

– Preparation for testing at MTA using the single cavity vessel, need accessory components: fabrication of RF coupler, tuners and actuators – EP of remaining nine cavities for MICE

  • Modular cavity design review at SLAC
  • Review of the modular cavity drawings at LBNL

– Comments from LBNL sent to SLAC – Drawings of Be plate design sent to UMiss for quotation – Revisit the ¼ waveguide transition design

  • Prototypes of the RF spring grooves for 201 MHz cavity

coupler design

  • Fabrication of six actuators at LBNL
  • Finalize and complete the modular cavity drawings

– Define responsibilities of SLAC and LBNL, and sign off fabrication drawings – Start the cavity fabrication at SLAC machine shop – Development of the cavity testing plan

  • Complete and deliver the 201 MHz cavity coupler drawings to

Fermilab for fabrication

  • Continue the fabrication of actuators at LBNL
  • Complete modular cavity drawings
  • Start fabrication of the modular cavity at SLAC
  • Place PO of beryllium plates by UMiss
  • Development of the modular cavity testing plan
  • Data analysis of previous 805 MHz testing results
  • EP of MICE cavities at LBNL
  • MP simulation studies of the MICE cavity and coupler with

external magnetic fields

  • Fabrication of two 201 MHz RF couplers for the first MICE

cavity in preparation for the testing at MTA

  • Complete the fabrication of actuators at LBNL
  • Support MTA RF testing programs
  • Comments/feedback of the modular cavity drawings from Fermilab
  • RF coupler drawings for the 201 MHz cavity
  • Fabrication of actuators (already discussed with LBNL machine

shop, new hire or new assignment will be in place soon)

  • MICE SS magnets
  • Preparation of the cold-mass for testing at Fermilab
  • MICE/MuCool cryostat design and fabrication at LBNL
  • LBNL hired a new welder for the cryostat work

14 December 2012

03 01: Normal Conducting RF Derun Li

slide-16
SLIDE 16

Milestone Status (Progress) Resource Conflicts, Plan Changes and Issues Late Items Summary of Previous Month Quarterly Plans Upcoming Work (Next Month)

Monthly L2 Status Report -

WBS: Presenter:

  • Research Instruments visit to finalize completion plan for

explosion bonded 500 MHz Cavities

  • Research Instruments visit with review of facilities
  • Work at RI to complete explosion bonded 500 MHz cavities
  • Develop cavity electroforming plan
  • Complete fabrication of 500 MHz cavities at Research

Instruments

  • Asymmetry in beam tube thickness on the two ends of each

500 MHz explosion bonded cavities. RI has retained one of their expert retirees for help on this. A HIPPed cavity has the same issue and will be used to develop required techniques.

14 December 2012

3.2 – Superconducting RF Don Hartill

slide-17
SLIDE 17

Milestone Status (Progress) Resource Conflicts, Plan Changes and Issues Late Items Summary of Previous Month Quarterly Plans Upcoming Work (Next Month)

Monthly L2 Status Report -

WBS: Presenter:

  • Souchlas: MARS simulation of revised W shielding
  • Ding: MARS simulation of shifting proton focal point
  • Sayed: ICOOL simulation of relation between proton beam

time and rapidity of magnet taper

  • Graves: He-W shield cooling calculations
  • Zhan: Ongoing FLUENT simulation of Hg flow in welded pipe
  • Continuation of all projects of previous month
  • Weggel: Begin conceptual design of magnets & shields for

chicane.

  • The basic target system concept is well-defined.
  • Clarify whether we can drop the capture solenoid field from

20 T to 15 T.

  • Optimize target & decay magnetic configuration for best

performance of beam delivered to accelerator (a step towards a global optimization of the entire MC/NF).

  • Extend target system conceptual design up to start of buncher

(including chicane in decay/drift region).

  • Begin technical design of magnet cryostats, shielding modules,

and mercury handling system.

14 December 2012

03.04 Targets and Absorbers Kirk McDonald

slide-18
SLIDE 18

Milestone Status (Progress) Resource Conflicts, Plan Changes and Issues Late Items Summary of Previous Month Quarterly Plans Upcoming Work (Next Month)

Monthly L2 Status Report -

WBS: Presenter:

  • 2212 Conductor improvement – Fermilab/Oxford Supercond.

has reduced carbon and hydrogen impurities by more than 50% in a recent 360m test sample

  • IR Magnets "Optics and magnet requirements of a HF muon

storage ring and IR and an integrated plan for conceptual design studies was coordinated. An abstract -"Preliminary Design of a Higgs Factory mu+mu- Storage Ring" has been prepared and submitted to IPAC2013.

  • Rapid Cycling Magnets - HTS magnet (0.5 T, ≤16 Hz) & test

system design complete

  • 2212 Conductor - React and test improved 2212 conductor and

determine properties

  • IR- Magnets - Preliminary IR magnet cross-sections and 2D field

maps will be begun for subsequent use in a MARS model of HF IR.

  • Rapid Cycling Magnets – Design, review, and fab of cryogenic

parts; complete procurement of remaining cryogenic components;

  • 2212 Conductor – continued test of conductor properties;

begin procurement of conductor for next larger scale test; continue development of cable and coil design.

  • IR-Magnets – continued development of IR magnet cross-

sections and iteration with AD on requirements, heat loads, etc.

  • Rapid Cycling Magnets – continue fabrication of parts,

assembly of components, etc.; preparations for test in E4R – move power supplies, review status of cryo-system, planning for move, installation, and vacuum/pressure testing. Begin preparation of engineering note for safety review.

  • Conductor development needs funding for realistic scale test

and development

14 December 2012

3.4 – Magnets

  • J. Tompkins
slide-19
SLIDE 19

Milestone Status (Progress) Resource Conflicts, Plan Changes and Issues Late Items Summary of Previous Month Quarterly Plans Upcoming Work (Next Month)

Monthly L2 Status Report -

WBS: Presenter:

  • New hardware: 201-MHz single cavity module

– tuner control (bench test) [Q1] – Done (P. Hanlet)

  • Infrastructure – on track

– beam-line upgrade mechanical installation done (J. Volk), elect., instr., doc.; circulator/switch re-commissioning; vacuum system for 2nd 805-station in hall [Q2]

  • Experimental program

– 805-MHz all season cavity E(B) performance – on track [Q2]

  • Data analysis: HPRF beam test, vacuum RF in B – on track [Q2]
  • Review of 805-MHz modular cavity design, integration at MTA
  • Replacement DAQ PC installed
  • Started retesting of 805-MHz circulator
  • Cryo-plant maintenance
  • MTA tour (1st year IIT physics students, Northwestern group)
  • 805-MHz all-season cavity operation (25 MV/m at B=0)
  • Parts, test plan design for dielectric-loaded HPRF (K. Yonehara)
  • 805-MHz RF conditioning/control program update
  • Circulator testing and repair
  • 201-MHz RF controls upgrade plan
  • Finalize beam-line drawings and commissioning plan
  • Build fixture for cavity button microscopy
  • Plan for retraining solenoid magnet
  • All-season cavity operation in B-field
  • Past data: publish box cavity (magnetic insulation), Be-Cu

buttons (pillbox), beam test (HPRF)

  • Current program: continue operation of 805-MHz “all-season”

pillbox cavity – install in solenoid, study gradient vs magnetic field – additional instrumentation (acoustic, light)

  • Next test: build fixturing and start assembly of 201-MHz Single-

Cavity Module (MICE RFCC-Lite) in Lab-6; low-level RF testing

  • For later: help finalize integration plan for SLAC/LBNL modular

cavity package

  • Infrastructure

– Controls upgrades for 805- and 201-MHz RF; circulator – Final beam-line documentation, shakedown, commissioning to upstream beam absorbers – Processing of laser scan data for hall model

  • Q1 OK so far, some items may slip beyond Q2

– all-season cavity program, single-cavity module installation, circulator re-commissioning

  • Limited access to tech resources from FNAL-AD due to shutdown

work (impact on RF program, beam-line preparations)

  • Scheduling of infrastructure work in parallel with exp’tal program will

be challenging as usual

14 December 2012

3.5 – MuCool Test Area Yagmur Torun

slide-20
SLIDE 20

L2 MANAGER STATUS REPORTS: SYSTEMS TESTS (WBS 4)

December 14, 2012 MAP Monthly Status Report 20

slide-21
SLIDE 21

Milestone Status (Progress) Resource Conflicts, Plan Changes and Issues Late Items Summary of Previous Month Quarterly Plans Upcoming Work (Next Month)

Monthly L2 Status Report -

WBS: Presenter:

  • First MICE-US resource-loaded schedule which has been

matched with the planned activities by the MICE-UK effort

  • Updated budget estimate to complete MICE construction work
  • Spectrometer Solenoid Magnet Controls review completed
  • Review of coil winding effort at Qi Huan completed
  • NSF grant proposal submitted

– UC Riverside, IIT, UMississippi, UChicago, UNH, U Iowa

  • Spectrometer Solenoid 1 Controls Review modifications begun

– External internet established, new pressure gauge instrumented, heater currents read, cryomech readout fixed, alarm handler implemented

  • SS1 – HTS leads replaced, PS modifications underway
  • SS2 – cold mass/shield assembly installed in vacuum vessel
  • Coupling coil repair/modifications complete – gauges, sensors, leaking tube
  • Local magnetic shield design – tweak geometry and thickness
  • Magnetic Field modeling continues – includes compressors and racks
  • Implement all upgrades to SS1 controls system (software and

hardware) – cooldown and begin power tests again

  • Coupling coil safety sign-off, pressure test tubes, ship to FNAL
  • Beam data run – test of new Online Reconstruction and C&M

Software

  • Extend Magnetic Shielding model to include local shield option
  • Finish cooldown of Focus Coil and start power testing
  • Complete testing SS1
  • Review of full engineering plan for local shielding of cooling

channel magnetic field in MICE Hall (H. Witte)

  • Begin testing of first CC at Fermilab
  • FC controls review
  • Hall

– continue installation of SS support infrastructure and electrical infrastructure for new Step IV rack and compressor locations – Fix major AC refrigerant leak

  • Fix Decay Solenoid compressor (oil leak) – remove/reinstall
  • 14 hour activation run in February

– measure impact on ISIS equipment with MICE target operating with beam bump – hopefully allow us to double the loss limit

  • Collaboration Meeting – mid-February
  • Complete testing FC1
  • Finish PID analysis paper – submit for publication
  • Finish Step I emittance measurement paper – submit for pub
  • Priority changes in Controls – improvements in SS1 controls

highest priority

– Need additional controls personnel

  • EMR now due at RAL April 2013 (rather than Feb)

14 December 2012

04 01

  • L. Coney
slide-22
SLIDE 22

Milestone Status (Progress) Resource Conflicts, Plan Changes and Issues Late Items Summary of Previous Month Quarterly Plans Upcoming Work (Next Month)

Monthly L2 Status Report -

WBS: Presenter:

  • -
  • Email discussion on the 6d cooling demonstration issues
  • Have got feedback from Bob Palmer only so far:
  • 201 vs 805 Mhz: 805 is preferable, since 201 = MICE
  • HW: will “inherit” at least one 805 MHz RF and two ~22 T SC sol.
  • Relatively intense muon beam source: no feedback for now
  • Note on intensity: RAL beam would not deliver many muons in 0.2

mm emittance. A study to see how to make such a beam would be worthwhile.

  • Solicit more feedback
  • Detail muon source options/parameters
  • Seek potential synergies with NuStorm (in the framework of

MASS as well)

  • -
  • -

14 December 2012

04 02 - 6D Cooling Demonstration

Snopok

slide-23
SLIDE 23

AOB

  • Are there any other issues for today’s

discussion

  • Questions?
  • Comments?

December 14, 2012 MAP Monthly Status Report 23