Date: 11 August 2011 Client: Ofgem
Modelling the Impact of Transmission Charging Options Project - - PowerPoint PPT Presentation
Modelling the Impact of Transmission Charging Options Project - - PowerPoint PPT Presentation
Modelling the Impact of Transmission Charging Options Project TransmiT Stakeholder Event 11 th August 2011 Date: 11 August 2011 Client : Ofgem Contents Background Objectives of the study Modelling methodology Key assumptions and
Date: 11 August 2011 Title: Modelling the Impact of Transmission Charging Options 2
Contents
- Background
- Objectives of the study
- Modelling methodology
- Key assumptions and data sources
- Project timelines
- Questions
Date: 11 August 2011 Title: Modelling the Impact of Transmission Charging Options 3
Background
- On 27 May 2011 Ofgem outlined its proposed approach for Project TransmiT
- Ofgem issued tender for analytical support for Project TransmiT on 3 June 2011
- Project kicked off on 23 June 2011
- On 7 July 2011, Ofgem launched a Significant Code Review of electricity transmission
charging
- Redpoint has been working with NGET and Ofgem on constraint forecasting using
PLEXOS since October 2010
Date: 11 August 2011 Title: Modelling the Impact of Transmission Charging Options 4
Objectives
Status Quo Imperfect foresight (agent simulation) Perfect foresight Improved ICRP Socialised 2011-2020 2021-2030
- Impact on consumer bills
- Impact on power sector cost
- Detailed outputs
- wholesale electricity prices
- capacity margins
- generation mix
- costs of constraints
- incremental transmission
cost levels
- amount of renewable
generation (by region)
- total carbon emissions
from generation Three
- ptions
T wo methodologies Timeframes Outputs
Specific – mainly based
- n known projects
General – based on generic projects
Date: 11 August 2011 Title: Modelling the Impact of Transmission Charging Options 5
Policy levers
Wide set of policy levers to be covered by modelling framework Only one definition of each option can be fully modelled within Project TransmiT timelines – required by beginning of September
Date: 11 August 2011 Title: Modelling the Impact of Transmission Charging Options 6
Model components
Cost Data
Transmission charging Generation Plan Unconstrained generation ‘stack’ Constrained ‘stack’/zonal supply/demand Detailed system dispatch
Potential Projects Generation Decision Rules Cost Data
Transmission Plan
Potential Projects Transmission Decision Rules Generation background Transmission background
Full results
Based on NGET’s ELSI model Ofgem’s Explorer Model TEC register NGET’s Transport Model Data from TOs Based on expansion of functionality in NGET’s ELSI model Based on functionality in Redpoint’s Investment Decision Model
PLEXOS TransmiT Decision Model
Date: 11 August 2011 Title: Modelling the Impact of Transmission Charging Options 7
Simulation steps
Run Transport Model TNUoS charges Run unconstrained and constrained stacks Expected generation gross margins Constrained boundaries Generation investment decisions Transmission reinforcement decisions Generation retirement and build decisions Transmission reinforcement decisions Step forward 1 year
Date: 11 August 2011 Title: Modelling the Impact of Transmission Charging Options 8
Agent simulation/non-perfect foresight
Generation plan Transmission plan
Generation Decision Rules Transmission Decision Rules Existing plant Yr1 Yr1 Existing boundary capacities 5 yr forward view Fix Fix Roll forward to next year 1 2 3 5 yr forward view 1 2 3 4 Cross-visibility of Generation and Transmission plans Unseen Unseen
Date: 11 August 2011 Title: Modelling the Impact of Transmission Charging Options 9
Perfect foresight
Iterate to converge
Date: 11 August 2011 Title: Modelling the Impact of Transmission Charging Options 10
Generation Decision Rules – New Build
Expected gross margin Forward looking stack + prices Anticipated low carbon support Capital and fixed O&M costs Expected transmission charges Expected levelised non- fuel costs Planning Under Construction Operational Commit
Compare Trigger 1 Trigger 2
Date: 11 August 2011 Title: Modelling the Impact of Transmission Charging Options 11
Generation Decision Rules – Retirements
Expected gross margin Forward looking stack + prices Fixed O&M costs Expected transmission charges Expected fixed costs Plan closure Close
Compare Trigger 1 Trigger 2
Date: 11 August 2011 Title: Modelling the Impact of Transmission Charging Options 12
Transmission Decision Rules
Expected constraint costs Forward looking constrained stack Capital and fixed O&M costs Expected reinforcement costs Under Construction Operational Commit
Trigger Evaluate different reinforcement
- ptions
- 1. Identify constrained boundaries
- 2. Assume independence or
simple dependencies
- 3. T
est reinforcements on each constrained boundary
Date: 11 August 2011 Title: Modelling the Impact of Transmission Charging Options 13
Key assumptions
- Treatment of renewables
– Aim to equate renewables volumes across options by adjusting (implied) support levels
- Treatment of nuclear
– Assume same nuclear build programme under all options
- Treatment of other EMR policy options
– Assume 450 g/kWh Emissions Performance Standard throughout – Assume Strategic Reserve for capacity mechanism
- Choice of boundaries
– Assuming fixed boundaries throughout modelling time horizon – Unique mapping between TNUoS and system zones
- Status Quo policy decisions
– HVDC bootstraps: awaiting policy decision on charging – Offshore: assuming radial connections – Island connections: new TNUoS zones?
Date: 11 August 2011 Title: Modelling the Impact of Transmission Charging Options 14
Key data sources
Data Main source Fuel and carbon price assumptions Ofgem Explorer scenarios Demand profile and growth Ofgem Explorer scenarios Future interconnection Ofgem Explorer scenarios Existing plant data and costs NGET constraints model Target generation mix NGET Gone Green scenario Renewables resource availability and maximum build rates NGET Gone Green scenario/ARUP Regional wind output profiles NGET Balancing Mechanism bid-offer pricing assumptions NGET constraints model Gas transport charges by zone/region National Grid Gas Generation investment data (capital costs, O&M costs, technical parameters, cost of capital etc) PB Power/Mott MacDonald /Arup studies for DECC Onshore transmission investment data (known projects with capital costs, O&M costs, cost of capital, construction time etc) Transmission Operators Offshore transmission investment data (capital costs, O&M costs, cost of capital, construction time etc) Offshore Transmission Review
Date: 11 August 2011 Title: Modelling the Impact of Transmission Charging Options 15
Overall project plan
Detailed model design Dataset collation Model handover Policy option modelling Model development Proof of concept End-to-end testing Reporting Project kick-off June 2011 July 2011 August 2011 September 2011 October 2011 Stakeholder meetings: Possible further meetings
Date: 11 August 2011 Title: Modelling the Impact of Transmission Charging Options 16