ML&P Government Hill utility work 2013-16 Marty Smith, P.E. Senior Engineer Order of work Voltage upgrades: 4 kV to 12.47 kV Area west of East Loop Road 10/2013 to 4/2014 Substation 13 relocation 5/2014 to 10/2014


slide-1
SLIDE 1

ML&P Government Hill utility work 2013-16

Marty Smith, P.E. Senior Engineer

slide-2
SLIDE 2

Order of work

  • Voltage upgrades: 4 kV to 12.47 kV

– Area west of East Loop Road – 10/2013 to 4/2014

  • Substation 13 relocation

– 5/2014 to 10/2014

  • Port of Anchorage feeder

– Summer of 2014 or 2015

  • Title 21 undergrounding

– Area west of Anderson Street – Design 2015, construction 2016

2

slide-3
SLIDE 3

Voltage upgrade: 4kV to 12.47kV

Beginning 4th quarter 2013

3

slide-4
SLIDE 4

Substation 13 demolition

4

slide-5
SLIDE 5

Old Sub 13 vs. new unit sub

Old Substation 13

5

slide-6
SLIDE 6

New unit substation

All underground connections

6

slide-7
SLIDE 7

New substation profile

Artist’s rendition using Google Earth at 226 E Bluff Drive

7

slide-8
SLIDE 8

Port of Anchorage feeder

  • Purpose

– to provide the port with a loop-fed distribution system

  • Critical asset to the municipality
  • Increases reliability to port

8

slide-9
SLIDE 9

POA feeder route

9

slide-10
SLIDE 10

Title 21 underground project

10

Overhead line to be underground Overhead line to remain Underground line Project location on vicinity map Power pole

slide-11
SLIDE 11

Title 21 project review criteria

11

slide-12
SLIDE 12

ML&P Title 21 project contacts

  • Jake Moe, P.E.

– 263-5407

  • Marty Smith, P.E.

– 263-5236

  • www.mlandp.com/underground