Middle School Prototype Nita Mensia-Joseph, COO * October 10, 2017 Presented to School Board Customization Overview Starting SF 134,875 SF Reduction of SF: Stage storage and dressing room (~2000) Relocation of projector room and stairwell
2
Customization Overview
Starting SF Reduction of SF: Stage storage and dressing room Relocation of projector room and stairwell 134,875 SF (~2000) (~350) Increase in SF 600 capacity auditorium / flipping auditorium with Courtyard infill Add 1 Health Classroom Replaced a classroom with science and added science prep area and orchestra Increase stairwell and corridor width Increase the size of the cafeteria ~395 ~780 ~2100 ~1200 ~2000 Net Increase ~4,125 SF Total ~139,000 SF
3
Customized Prototype - 1st Floor
4
Customized Prototype - 2nd Floor
5
Customization - Electives Wing
Filled in courtyard, deleted stage storage and dressing rooms, rotated auditorium to position stage adjacent to music classrooms Added two foreign language rooms,
- rchestra, and office
Revised layout of tech lab and flex space Increased capacity to 600, relocated projector room into auditorium
6
Customization - Gym
Storage room size was increased for future use as a classroom A ~780 SF health classroom was added adjacent to the gym. The three health classrooms could also function as additional flex space.
7
Customization - Academic Wings
Increased stairwell and corridor widths throughout the entire building Added a Science Lab and Science Lab Prep to each academic wing on both the first and second floors
8
Customization - Cafeteria
Added an additional serving line to bring the total kitchen serving lines to four Increased cafeteria seating capacity to ~450
Budget Analysis
9
Aspect Not Customized Escalated 10/16 - 10/17 June 2017 Award for 134,875 SF (800 capacity gym 400 capacity auditorium) Customized October 2017 estimate for ~139,000 SF (800 capacity gym 600 capacity auditorium) Escalated to Oct 2018 October 2018 contract (Sept. 2020 delivery) ~139,000 SF (800 capacity gym 600 capacity auditorium) Construction (~$230 / SF*) $31,017,500 (~$238 / SF**) $33,084,500 (~$249 / SF***) $34,738,725 Abatement $834,615 $834,615 $834,615 Demolition $834,615 $834,615 $834,615 Soft Costs (incl. CM w/MBP) $5,541,490 $6,379,185
- incl. CM w/MBP 45m $847,184
$6,379,185
- incl. CM w/MBP 45m $847,184
Contingency (5%) $1,550,875 $1,654,225 $1,750,458 Sunk $3,246,788 $3,246,788 $3,246,788 Total $43,025,883 $46,033,928 $47,784,386 PSF ~$319 ~$331 ~$344
Proposed Elevations
10
Progressive Traditional Transitional