  • 1. Overview of Proposed Project
  • 2. Recent Work
  • 3. Timeline
  • 4. Phasing Options
  • 5. Financial Planning
  • 6. Capital Campaign
  • 7. Student Involvement

Agenda

slide-4
SLIDE 4

History

2003: Field subsurface added to facilitate change to artificial turf 2011: Schematic design for Memorial Field Master Plan authorized 2013: West Bleachers replacement, retaining wall, field surface, sinkhole repaired 2015: Board resolution to support use of downtown campus for athletics 2016: Design process, including community outreach 2017: Final design approved by SCASD Board 2018: Project bidding placed on hold 2019: Project documents released to bid

slide-5
SLIDE 5

Why downtown location?

Location: Lack of other suitable property proximate to new State High Available Parking: Over 1,400 garage and parking lot spaces and additional street parking available

slide-6
SLIDE 6

Proposed Project

  • 1. Home/East Bleachers
  • 2. Locker Rooms
  • 3. Restrooms
  • 4. Press Box
  • 5. Concession Stand
  • 6. Field Access Ramp

*Safety, ADA compliant

slide-7
SLIDE 7

Overhead View

slide-8
SLIDE 8

Field View - Home Stands

slide-9
SLIDE 9

Elevation View

slide-10
SLIDE 10

Stadium Plaza Entrance

slide-11
SLIDE 11

Alternate: Classroom

slide-12
SLIDE 12

Site Plan Overview

slide-13
SLIDE 13

Timeline

Open Bids: February 21, 2019 (note date change) Review Bids: February 26, 2019 (Board Facilities & Grounds Com.) Board Info: March 11, 2019 Award Bids: March 18, 2019 Schedule Option 1: Schedule Option 2: April 2019 - Start April 2019 - Start Fall 2019 - Stop for sports Fall 2020 - Project complete

  • Nov. 2019 - Resume construction

*No field use during construction Fall 2020 - Stop for sports Spring 2021 - Project complete

slide-14
SLIDE 14

Timeline

slide-15
SLIDE 15
slide-16
SLIDE 16

Alternate Schedule

If Schedule Option 2 Accepted: Fall 2019 Options

1. Play at alternate locations in district a. South Track (Field Hockey, B/G Soccer, Non-Varsity Football, Marching Band) b. North Field (Varsity Football, B/G Soccer, Field Hockey) 2. Play Varsity Football at other local stadium(s) a. Note: other teams & Band use South Track & North Field 3. Play all Varsity Football games Away a. Note: other teams & band use South Track & North Field

slide-17
SLIDE 17

Memorial Field Tribute

Originally dedicated in 1946 and rededicated in 1993 to honor all State High Alumni who have fallen in wartime.

Historic Site

slide-18
SLIDE 18

Finances

  • Funded via Capital Financing Plan
  • Est. Construction Costs $10 million
  • Est. Soft Costs $3 million
  • Potential Savings (Alternate Phasing):

$500k - $800k

  • Fundraising to date: $600k commitments
slide-19
SLIDE 19

Capital Campaign

  • Commitments in excess of $600,000 to date
  • Naming Opportunities:

○ Stadium, Bleachers, Press Box, Scoreboard, Classroom, Locker Rooms ○ Additional opportunities coming

  • www.scasdfoundation.org
slide-20
SLIDE 20

Information & Resources

www.SCASD.org/MemorialField

slide-21
SLIDE 21

Next Steps

  • Feb. 23: Open Bids
  • Feb. 26: Board Facility and Grounds Committee

March 11: Bids presented to Board of Directors March 18: Award Bids April 2019: Project Begins

slide-22
SLIDE 22

Questions & Feedback