meeting
play

Meeting October 6, 2016 1 WILLOW RUN AIRPORT MASTER PLAN UPDATE - PowerPoint PPT Presentation

WILLOW RUN AIRPORT MASTER PLAN UPDATE Citizens Advisory Committee Meeting October 6, 2016 1 WILLOW RUN AIRPORT MASTER PLAN UPDATE Agenda Current Project Status Aviation Projections Recap FAA forecast approval Summary of


  1. WILLOW RUN AIRPORT MASTER PLAN UPDATE Citizens Advisory Committee Meeting October 6, 2016 1

  2. WILLOW RUN AIRPORT MASTER PLAN UPDATE Agenda  Current Project Status  Aviation Projections Recap  FAA forecast approval  Summary of Facility Needs  Presentation of runway length needs  Review of Alternatives  Recommended runway length alternative  Next Project Steps  Capital improvement plan & project implementation schedule  Questions 2

  3. WILLOW RUN AIRPORT MASTER PLAN UPDATE Current Project Status 3

  4. WILLOW RUN AIRPORT MASTER PLAN UPDATE Current Project Status  Inventory – complete  Forecasts of aviation demand  Original forecasts submitted November 2015  Forecasts approved August 29, 2016 – complete  Review of facility requirements – complete  Finalize alternatives – in process  Review of environmental considerations – in process  Preparation of CIP & project implementation – in process 4

  5. WILLOW RUN AIRPORT MASTER PLAN UPDATE Aviation Projections Recap 5

  6. WILLOW RUN AIRPORT MASTER PLAN UPDATE Aviation Projections Recap Total Operations Based Aircraft 237 250 226 4 217 208 4 (in Thousands) 3 200 44 172.5 192 3 180 42 200 3 40 3 38 Based Aircraft 147.4 160 37 35 140 127.4 150 82 79 120 107.1 75 72 69 67 Total Operations 100 80.8 78.0 75.2 100 72.7 70.6 68.1 80 67.1 60 107 50 102 98 94 40 90 87 20 - 0 1990 1995 2000 2005 2010 2014 2020 2025 2030 2035 2040 2015 2020 2025 2030 2035 2040 Year Year Single Engine Jet Multi-Engine Helicopter 2014-2040 CAGR: 0.82% 6

  7. WILLOW RUN AIRPORT MASTER PLAN UPDATE Critical Aircraft  Existing critical aircraft DC-9-30  DC-9-30  727-200  MD-80  Potential critical aircraft 727-200  CRJ-200  737 (-400,-500,-600,-700,-800)  757-200  767-300 MD-80 7

  8. WILLOW RUN AIRPORT MASTER PLAN UPDATE Summary of Facility Needs 8

  9. Infrastructure Needs  Existing infrastructure in poor condition  Airfield pavements  Landside pavements  Utilities 9

  10. Runway Length Needs  Runway length  Additional runway length needed for some aircraft types and haul lengths Max Allowable Percent of Max Haul Length Takeoff Takeoff Available with Aircraft Type Weight (LB) Weight Allowed Full Payload (NM) Current Runway Length = 7,543 feet DC9-30 103,000 95% 600 MD83 150,000 94% 1,200 B737-800 157,000 90% 800 B727-200 180,000 91% 1,000 B757-200 234,000 92% 1,300 Maximum range available from current runway length B767-300 367,000 89% 1,700 Notes: Runway Length Required on Hot Day, YIP Elev = 716 Current runway length (7,543 feet) Source: Manufacturer Airport Planning Manuals Hot day runway length requirements Full payload 10 Red dots identify top 18 destinations over 1,000 nm that were flown non-stop from YIP in 2014 (Source: 2015 FAA Traffic Flow Management System Counts data)

  11. Runway Length Needs  Runway length 2015 Haul Length Available 2015 Operations  446 Operations Total with Full Payload to/from Destination conducted in 2015 that Aircraft Type Operations from Ex Rwy Length (NM) Over Haul Length Limit were over the efficient DC9-15 1,284 750 0 haul length limit DC9-30 652 600 156  Does not currently meet B727-200 495 1,000 183 FAA funding criteria for MD83 272 1,200 70 runway extension (500 28 B737-400 171 750 operations required) B737-800 36 800 5 B737-300 30 1,250 2  Recommend YIP B737-200 16 600 2 continue to plan for A320 14 1,800 0 additional 2,000 feet of B737-700 13 1,400 0 runway length in the B737-900 4 600 0 future B757-200 0 1,300 0 B767-300 0 1,700 0 11 Total Large Jet Operations 2,987 446

  12. Existing infrastructure in poor condition Facility Improve approach Airfield hot spots minimums Runway to be Ecorse Road designated as 10/28 Needs Crosswind runway recommended for Beck Road American Center smaller aircraft for Mobility Property Possible plan for add’l runway length on either 5R/23L or 9/27 Future Yankee Air Museum Site Parallel runway not needed for capacity, could be maintained for traffic separation ARFF station improvements or replacement recommended Improvements to snow removal Tyler Road Extension equipment storage facilities recommended Improve approach Provide flexible minimums aeronautical development areas Future parallel taxiway to Runway 5R/23L is on the FAA 12 approved ALP I-94

  13. WILLOW RUN AIRPORT MASTER PLAN UPDATE Review of Alternatives 13

  14. WILLOW RUN AIRPORT MASTER PLAN UPDATE Alternative Cost Estimates  Important notes to consider:  Order of magnitude cost estimates  Cost estimates prepared without preliminary engineering  Current dollars  Based upon unit costs for similar projects 14

  15. WILLOW RUN AIRPORT MASTER PLAN UPDATE Outline for Review of Alternatives  Infrastructure / Utilities  Landside Pavements  Buildings and Hangars  Airside Infrastructure 15

  16. WILLOW RUN AIRPORT MASTER PLAN UPDATE Alternatives – Infrastructure / Utilities 16

  17. WILLOW RUN AIRPORT MASTER PLAN UPDATE Utilities Cost Summary Item Total Cost Storm Sewer Ph1 $5,000,000 Water Main $6,760,000 Sanitary Sewer $4,030,000 Electrical Utilities $3,740,000 Fiber Optic Utilities $5,510,000 SUBTOTAL Ph1 $25,040,000 Storm Sewer Ph2 26,000,000 GRAND TOTAL 51,040,000 17

  18. WILLOW RUN AIRPORT MASTER PLAN UPDATE Alternatives – Landside Pavements 18

  19. Landside Pavement Needs Total cost for all landside pavement reconstructions: $7,520,000 Source: Windshield survey conducted by Mead & Hunt (January 26, 2016) using approximation of PASER rating system 19

  20. WILLOW RUN AIRPORT MASTER PLAN UPDATE Alternatives – Buildings & Hangars 20

  21. Hangar 1 / Administrative Offices Alt Item Cost Alt 2 (site 2) Rehabilitate Hangar 1 Relocate Hangar 1 1a $22,000,000 (10 year useful life) Rehabilitate Hangar 1 1b $56,000,000 (30 year useful life) Alt 1a & 1b Relocate Hangar 1 (6 of 8 bays) $38,500,000 Rehabilitate Hangar 1 2 Construct new admin office $1,000,000 Transfer Hangar 1 to private entity & Alt 3 & Alt 4 3 $250,000 construct modular admin office Construct modular Demolish Hangar 1 & construct 4 $4,250,000 admin office modular admin office PREFERRED Alt 2 (site 1) Relocate Hangar 1 Approximate annual revenue generated from Hangar 1: $835,000 (Note: includes leases, rents, landing fees, and fuel sales associated with Hangar 1 activity) 21

  22. ARFF Facility Response Time (in minutes) Total Item Cost Rwy Rwy 5R/23L 9/27 ARFF Alt 1 Refurbish (3,300 sq ft) & $ 2,500,000 2:38 2:54 expand existing ARFF bldg PREFERRED ARFF Alt 2 New ARFF building & associated landside $ 4,300,000 1:39 2:45 pavements (requires parallel taxiway) ARFF Alt 3 New ARFF building & $ 4,000,000 2:22 2:42 associated landside pavements 22

  23. WILLOW RUN AIRPORT MASTER PLAN UPDATE SRE/Maintenance Facility Item Total Cost SRE/Maint Alt 1 Refurbish (13,600 SF @ $100/SF) & expand $ 2,200,000 SRE/Maint Alt 1 (3,000 SF @ $250 SF) $2,200,000 Bldg 2620 23

  24. WILLOW RUN AIRPORT MASTER PLAN UPDATE Alternatives – Airside Pavements 24

  25. Runway 9/27 Item Total Cost Reconstruct Runway 9/27 $32,400,000 (7,292 x 150') PREFERRED Item Total Cost Shorten & Reconstruct Rwy 9/27 $16,100,000 (5,000' x 100‘) Item Total Cost Close and Remove Rwy 9/27 $ 2,100,000 (7,292 x 150') 25

  26. Runway 5L/23R PREFERRED Item Total Cost Item Total Cost Item Total Cost Reconstruct Shorten & Reconstruct Close and Remove Runway 5L/23R $26,500,000 Rwy 5L/23R $ 5,500,000 Rwy 5L/23R $ 1,700,000 (5,996' x 150') (3,500' x 75') (5,996 x 150') 26

  27. WILLOW RUN AIRPORT MASTER PLAN UPDATE Parallel Taxiway to Runway 5/23 Item Total Cost Item Total Cost Item Total Cost Convert Runway 5L/23R to East Side Parallel Taxiway West Side Parallel Taxiway Parallel Taxiway $27,100,000 $22,700,000 $19,700,000 (85,000 sq. yds.) (74,000 sq. yds.) (102,000 sq. yds.) PREFERRED 27

  28. Taxiway System Improvements Item Total Cost Reconstruct Twy B $9,900,000 (Rwy 9/27 to Rwy 5R/23L) Twy B Reconstruct Twy B $4,300,000 (Rwy 5R/23L to Kalitta) Reconstruct Taxiway E $7,200,000 Twy E Remove Twy D $500,000 Remove Twy C $400,000 Remove Taxiway H and E2 $1,800,000 completely Total $24,100,000 Kalitta Facility 28

  29. Taxiway System Improvements Summary Item Alt 1 Alt 1A (remove (no removal abandon of abandon pavement) pavement) Reconstruct Twy B $9,900,000 $9,900,000 (Rwy 9/27 to Rwy 5R/23L) Reconstruct Twy B $4,300,000 $4,300,000 (Rwy 5R/23L to Kalitta) Reconstruct Twy E $7,200,000 $7,200,000 Remove Twy D $500,000 *$80,000 Remove Twy C $400,000 *85,000 Remove Twy H & E2 $1,800,000 *85,000 Construct East Side $22,700,000 $22,700,000 Parallel Twy Total $46,800,000 $44,350,000 * Note: Includes removal of small section of pavement at intersections with active taxiways to delineate closed surfaces 29

  30. West Apron Improvements PREFERRED Item Total Cost Item Total Cost Item Total Cost Reconstruct Reconstruct Reconstruct West West Apron (incl $28,100,000 West Apron $ 3,300,000 Apron at 75% size $22,400,000 30 Eagle flight) (Eagle flight) & reduced strength

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend