Meeting 4
Commando Park, Cochrane Final Schematic Design
October 23, 2013
Meeting 4 Commando Park, Cochrane Final Schematic Design October - - PowerPoint PPT Presentation
Meeting 4 Commando Park, Cochrane Final Schematic Design October 23, 2013 Agenda 1. Review of Schematic Design 2. Sections 3. Order of Magnitude Budget 4. Discussion A Cultural Landscape of the Cree, Ojibway and Algonquin First Nations
October 23, 2013
A Cultural Landscape of the Cree, Ojibway and Algonquin First Nations
Cultural Significance
Colonial Land Subdivision and the Train
Existing Urban Fabric
Grid of Roads Terminate at the Lake
Potential Places
Other “views” to be Preserved
Suggestions from the Landscape. Where the Town ends & the Lake begins
Fifth Street Park Entrance
Fronts onto 5th Street. Opens onto Commando Lake.
Schematic Design
Look Out
22-Oct-13
Page 1 of 3
Item No Description Element Low High 1 Pavilion - Total ROM cost to construct Pavillion at north end of park: 3,500 sf @ $225 psf Tent Structure Hard Landscaping $1,500,000 $2,000,000 2 Mirador @ Railway Station and 11th * Foundations *Retaining Walls * Floor * Site Accoutrements
Landscaping - Benches $100,000 $200,000 3 Mirador @ 4th and 7th * Foundations *Retaining Walls * Floor * Site Accoutrements
Landscaping - Benches $150,000 $250,000 4 Waters Edge Feature @ Beach * Foundations *Retaining Walls * Floor * Site Accoutrements
Landscaping - Benches * Dock $200,000 $300,000 5 Waters Edge Feature @ 4th Street * Foundations *Retaining Walls * Floor * Site Accoutrements
Landscaping - Benches * Dock $175,000 $275,000 22-Oct-13
Page 2 of 3 12/3/9081
Cochrane Commando Park
12/3/9081
Cochrane Commando Park
6 Waters Edge Feature @ East * Foundations *Retaining Walls * Floor * Site Accoutrements
Landscaping - Benches * Dock $200,000 $300,000 7 Suspension Bridge - Cost to construct suspensions bridge located at south end of Lake by 'Yellow Bars' * Lake remediation * Foundations * Bridge $750,000 $1,000,000 8 Bandshell Revitalization - Cost includes all elements to update bandshell area * Seating * Lighting * Hard Landscaping * Landscaping $100,000 $200,000 9 Fountain on north west corner * Plumbing and Controls * Foundation *Hard Landscaping $150,000 $250,000 10 Boat Launch * Revitalize Existing Boat Launch * Concrete Ramp and Foundation 75000 $135,000.00 11 Splash Pad at existing beach house * Plumbing and Controls * Foundation *Hard Landscaping $150,000 $500,000 12 Revitalization of the Beach Building * Revitalize Existing Beach Building - match theme of Miradors and Pavilion $100,000 $150,000 13 Zip Lines * Landscaping * Removable Structure * Foundations $185,000 $250,000 14 Top soil and Sodding - Allowance * Restoration along entire length of pathway $160,000 $200,000 15 Planting and Landscaping * Provisions for basic landscaping and ground coverings * Create Landscape Elements indicated on plan $200,000 $300,000 22-Oct-13
Page 3 of 3
16 Gravel Walkways * 3m wide and 3km long crushed stone walkways around park perimeter and through penninsula. $120,000 $200,000 Cochrane Commando Park
12/3/9081
17 Asphalt Walkways * Fee for asphalt walkways, in addition to requirements of item 16 for gravel walkways. Provides a hard multi use trail surface. $150,000 $225,000 18 Site Drainage * Steel Culverts installed along pathway to divert surface runoff towards lake and prevent ponding in landscaped areas * Drainage swales and ditching $50,000 $100,000 19 Electrical Panel's * located around site to control lighting circuits and
bandshell, summer festival, winter festival, etc. $75,000 $100,000 20 Electrical Conduits in Duct Bank * Cost of electrical duct bank as well as conduit provided for lighting and underground to pole mounted hydro services. $750,000 $1,000,000 21 Electrical Light Fixtures * Pole mounted and post lighting along the pathway $350,000 $500,000 22 Sound System * Sound system around the park complete with speakers, PA system and amplification and Base station in new pavilion. $40,000 $60,000 $8,578,138.00 23 Contractor's General Conditions & Fees 15% 1,286,720.70 $ $9,864,858.70 24 Construction Contigency Allowance 7% $690,540.11 $10,555,398.81 25 HST 13% $1,372,201.85 CONSTRUCTION BUDGET $11,927,600.65 26 Permit and Fees @ 15% * $1,789,140.10
TOTAL CAPITAL PROJECT BUDGET $13,716,740.75
What type of park do we consider Commando Park to be? Is it a passive park? Is it a recreational park? Is it an activity park, perhaps a novelty park?
Can Commando Park be all the things that we want it to be while preserving its cultural significance/cultural landscape? Is it a transformative park transforming with the seasons? Is it transformative due to the multiple and varied existing places that are meaningful, quaint and in need of some help – sometimes?