1
Cabos ´11, Maceio
Medium voltage superconducting cable systems for inner city power supply
- F. Schmidt, M. Stemmle, A. Hobl, F. Merschel, M. Noe
Medium voltage superconducting cable systems for inner city power - - PowerPoint PPT Presentation
Medium voltage superconducting cable systems for inner city power supply F. Schmidt, M. Stemmle, A. Hobl, F. Merschel, M. Noe Cabos 11, Maceio 1 Content Basics of Superconductivity Superconducting Cable System Components
1
Cabos ´11, Maceio
2
Cabos ´11, Maceio
3
Cabos ´11, Maceio
4
Cabos ´11, Maceio Temperature Specific resistance
Superconducting state is reached below critical temperature Tc
5
Cabos ´11, Maceio
1 μV/cm Jc
Practical definition of critical current density with 1 µV/cm criterion
6
Cabos ´11, Maceio
Bi2Sr2Ca2Cu3O10 (Bi-2223)
YBa2Cu3O7 (Y-123)
7
Cabos ´11, Maceio
Hg-Ba-Ca-Cu-O (135 K) TI-Ba-Ca-Cu-O (125 K) Bi-Sr-Ca-Cu-O (110 K) Y-Ba-Cu-O (92 K) La-Ba-Cu-O 1900 1920 1940 1960 1980 2000 2 40 60 80 100 120 140
Hg NbTi Nb3Sn Nb3Ge N2 He
T
c
High Temperature Superconductors (HTS) can be cooled with Liquid Nitrogen (LN2)
8
Cabos ´11, Maceio
9
Cabos ´11, Maceio
Core
Cryostat
Termination
room temperature
10
Cabos ´11, Maceio
Lapped dielectric system using PPLP (Polypropylene laminated paper) is established as the insulation for high voltage superconducting power cables
Insulation is impregnated with LN2 under pressure to avoid the formation of nitrogen bubbles
Low dielectric loss factor tan δ is important for cables at higher voltage levels as all losses have to be removed by the cooling system
11
Cabos ´11, Maceio
Two concentric longitudinal welded and
corrugated stainless steel tubes
Multilayer Superinsulation in between the
tubes
Low loss spacer to avoid contact between
inner and outer tube
Vacuum to avoid convection heat losses (10-5
mbar)
PE-outer sheath (optional)
Helium leak test of all welds and pieces to
ensure long term vacuum tightness
Nexans has delivered more than 100 km of flexible transferlines
12
Cabos ´11, Maceio
Redundant Cooling & Control Bulk LN2 Storage Heat Power SCADA Supply Return
No separate return line required in case of individual cryostats
13
Cabos ´11, Maceio
14
Cabos ´11, Maceio
Power supply within European cities predominantly with cables
Study was done investigating employment of high temperature
15
Cabos ´11, Maceio
16
Cabos ´11, Maceio
Dielectric Former Phase 3 Screen LN2 Inlet Cryostat Phase 2 Phase 1 Cooling System Inlet / Return LN2 Return Phase 3 Phase 1
17
Cabos ´11, Maceio
18
Cabos ´11, Maceio HV bus MV bus HV UGC MV UGC Bus tie (open)
19
Cabos ´11, Maceio HV bus MV bus HV UGC MV UGC Bus tie (open)
20
Cabos ´11, Maceio HV bus MV bus HV UGC MV UGC Bus tie (open)
21
Cabos ´11, Maceio
22
Cabos ´11, Maceio
23
Cabos ´11, Maceio
A D E
40 MVA
J B C F I H G
40 MVA 40 MVA 40 MVA 40 MVA 40 MVA 40 MVA 40 MVA 40 MVA 40 MVA
110 kV OHL 110 kV UGC 10 kV UGC 110 kV busbar 10 kV busbar Bus tie (open) 5,0 km 6,2 km 4,6 km 2,6 km 2,7 km 3,0 km 3,1 km 2,2 km 3,6 km 2,6 km 4,3 km 3,2 km 4,7 km
A D E
40 MVA
J B C F I H G
40 MVA 40 MVA 40 MVA 40 MVA 40 MVA 40 MVA 40 MVA 40 MVA 40 MVA
110 kV OHL 110 kV UGC 10 kV UGC 110 kV busbar 10 kV busbar Bus tie (open)
A D E
40 MVA
J B C F I H G
40 MVA 40 MVA 40 MVA 40 MVA 40 MVA 40 MVA 40 MVA 40 MVA 40 MVA
110 kV OHL 110 kV UGC 10 kV UGC 110 kV busbar 10 kV busbar Bus tie (open) 110 kV OHL 110 kV UGC 10 kV UGC 110 kV busbar 10 kV busbar Bus tie (open) 5,0 km 6,2 km 4,6 km 2,6 km 2,7 km 3,0 km 3,1 km 2,2 km 3,6 km 2,6 km 4,3 km 3,2 km 4,7 km
24
Cabos ´11, Maceio
5,0 km 6,2 km 4,6 km 2,6 km 2,7 km 3,0 km 3,6 km 6,8 km 3,2 km 4,7 km
A D E J B C F I H G
110 kV OHL 110 kV UGC 10 kV UGC 110 kV busbar 10 kV busbar Bus tie (open)
40 MVA 40 MVA 40 MVA 40 MVA 40 MVA 40 MVA 40 MVA 40 MVA 40 MVA 40 MVA
3,0 km 8,4 km 2,7 km 2,6 km 5,0 km 6,2 km 4,6 km 2,6 km 2,7 km 3,0 km 3,6 km 6,8 km 3,2 km 4,7 km
A D E J B C F I H G
110 kV OHL 110 kV UGC 10 kV UGC 110 kV busbar 10 kV busbar Bus tie (open)
40 MVA 40 MVA 40 MVA 40 MVA 40 MVA 40 MVA 40 MVA 40 MVA 40 MVA 40 MVA
A D E J B C F I H G
110 kV OHL 110 kV UGC 10 kV UGC 110 kV busbar 10 kV busbar Bus tie (open) 110 kV OHL 110 kV UGC 10 kV UGC 110 kV busbar 10 kV busbar Bus tie (open)
40 MVA 40 MVA 40 MVA 40 MVA 40 MVA 40 MVA 40 MVA 40 MVA 40 MVA 40 MVA
3,0 km 8,4 km 2,7 km 2,6 km
25
Cabos ´11, Maceio
Dispensable devices for new grid concept
Additionally required devices for new grid concept
26
Cabos ´11, Maceio
Nexans HTS 10/40 NA2XS2Y 1 x 630 RM/35 N2XS(FL)2Y 1 x 300 RM/35
1200 600 175 175 125 125 1050 650 850 125 125 100 100 100 100 145 200 400 700 100 100
27
Cabos ´11, Maceio
28
Cabos ´11, Maceio
Comparison of 3 different options based on NPV method Investment costs and operating costs (maintenance and losses) 40 years 2 % yearly increase 6.5 % interest rate 65 €/MWh
Total NPV in M€ 103.2 87.7 93.7
29
Cabos ´11, Maceio
30
Cabos ´11, Maceio
31
Cabos ´11, Maceio
32
Cabos ´11, Maceio
33
Cabos ´11, Maceio
HTS systems attractive alternatives to conventional systems
Concentric HTS cable systems for MV applications
Enabling new grid concepts for urban area power supply Ampacity project in Germany started (HTS cable and SFCL)