F&O Maintenance MC/MM Update (Minor Construction/Major Maintenance) Jim Meikle, Director of Maintenance School Board Monitoring Item October 17, 2019 Presentation Overview Program Profile Good News Summary of Projects


  1. F&O Maintenance MC/MM Update (Minor Construction/Major Maintenance) Jim Meikle, Director of Maintenance School Board Monitoring Item October 17, 2019

  2. Presentation Overview ➢ Program Profile ➢ Good News ➢ Summary of Projects ➢ Project Types ➢ Work in Progress ➢ Moving Forward ➢ What We Learned ➢ Bright Spots 2

  3. Program Profile F&O STAFF FINANCE • Financial Analyst, Capital Funds Director Maintenance Assistant Director Maintenance SCHOOL STAFF MC/MM Program Manager • Principal representatives from Environmental Specialist High, Middle and Elementary Energy Manager Security Coordinator COMMUNITY OUTREACH Safety Officer • Facilities Advisory Council Liaison CONSULTANT ADVICE/INPUT: Subject experts as required 3 3

  4. Good News • Considering many competing budget pressures, MC/MM budget levels maintained at previous year’s level and well supported infrastructure bonds keep rolling • Fulfilled all of our relocatable needs from existing owned stock – no new purchases. Ownership strategy has now exceeded $4 MILLION in cost avoidance • Four buildings off grid with no activities or large work scheduled – Cooling setbacks equals Energy Savings 4

  5. Summary of Projects Four-Year MC/MM Status of Projects Number of Projects Percent Number FY Projects * Completed ** Completed ** ongoing*** 2019 124 110 88.71 18 Ongoing Projects Summary 2018 161 140 86.96 20 2017 162 129 79.63 28 2016 194 144 74.23 48 * Projects added in due to emergencies ** Projects starting in the fall or later *** Projects span more than one year 5

  6. Examples of Individual Projects • Relocatable classroom moves/installations • Internal room conversions • Painting, cladding, siding and flooring • Medium-sized HVAC, electrical and plumbing projects Student Success • Theater, gymnasium, kitchen, art room and music Through improved room equipment upgrades infrastructure and • Replacement playgrounds, fields, tracks, parking systems upgrades ( Performance lots, blacktop rubber and other synthetic play Objectives: 1-5 ) surfaces 6

  7. Examples of System Wide Project s • Third party gym and bleacher safety inspections • Ongoing theater safety inspections and upgrades in collaboration with Arts Education • Safety/security improvements in collaboration with Risk and Emergency Manager Student • Management Environmental testing for lead in Well-Being water, hazardous materials, and radon • Storm Water Management Through improved and • Adding isolation valves to improve water shut-off enhanced Facilities and and upgrading grease traps Equipment • Switchgear servicing ( Performance Objectives: 6-10 ) 7

  8. Work in Progress 8

  9. Moving Forward – Progress Over Time 2018 2008 • Allocation $2.6 m • Allocation $ 6.5 m • Over 800 requests • Under 200 requests • 80% from site based • Less than 15% from requests requests Operational • 20% from systematic pro- Excellence • More than 85% from active inspection systems Vastly increased inspection/analysis and analysis investment in improved teaching, learning and working environments and customer buy-in ( Performance Objectives: 16-20 ) 9

  10. Moving Forward – Innovative Funding 2018 2008 • Major Infrastructure • No Infrastructure Bond Bond funding stream funding stream in eighth year • No funding mechanism in • Arlington voters between MC/MM and Operational supporting at 70-80% entire school renovations Excellence approval • First in region to consider Vastly increased investment in • Over forty million improved teaching, this approach learning and working dollars of new roofs, environments and customer buy-in HVAC and lighting ( Performance systems completed Objectives: 16-20 ) 10

  11. What We Learned • We will need to adjust budget estimates to include projected updates in fire and storm water codes. • It is never ‘too early’ to engage with the County on our summer plans. • We may have to start planning some projects two summers ahead where equipment has extra long lead times. 11 11

  12. Bright Spots • We ran out of bike racks – demand is great – we have replenished our stock • Gunston – Two year HVAC plan completed • Randolph – Two year HVAC plan completed • Small Synthetic Play fields - a great success offering significantly increased outdoor recess time 12

  13. F&O Maintenance MC/MM Update (Minor Construction/Major Maintenance) Jim Meikle, Director of Maintenance School Board Monitoring Item October 17, 2019

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.