May 2015 13 hydro schemes in Yorkshire area currently ongoing - - PowerPoint PPT Presentation

may 2015
SMART_READER_LITE
LIVE PREVIEW

May 2015 13 hydro schemes in Yorkshire area currently ongoing - - PowerPoint PPT Presentation

Sam ONeill Telecoms Manager May 2015 13 hydro schemes in Yorkshire area currently ongoing Changes to Feed In Tariff; further reduction prompting a height of activity Limited amount of suitable assets that are viable: Flow and head


slide-1
SLIDE 1

Sam O’Neill Telecoms Manager May 2015

slide-2
SLIDE 2
  • 13 hydro schemes in Yorkshire area currently ongoing
  • Changes to Feed In Tariff; further reduction prompting a

height of activity

  • Limited amount of suitable assets that are viable:

Flow and head height v Access, connection to grid, heritage etc.

slide-3
SLIDE 3
slide-4
SLIDE 4
  • Developer UK Hydro, Planning and EA licence consented
  • Issues - CRT only own half weir, limited access rights to

2018

  • Construction due to commence Summer 2015
slide-5
SLIDE 5
  • Developer UK Hydro
  • EA application submitted however,

Issue with pollution dilution and depleted reach

  • Looking at other options rather

than Fishponds weir

slide-6
SLIDE 6
  • Developer Yorkshire Hydro
  • EA licence consent
  • Failed planning due to flood risk and visible
  • appearance. Have now reached agreement with

EA on how to overcome the flood risk

slide-7
SLIDE 7
  • Developer UK Hydro
  • Planning and EA consents, awaiting FPP approval
  • 3 turbines generating 450kw
slide-8
SLIDE 8
  • Existing hydro scheme, not on C&RT land
  • Developer wishes to add another screw and canoe slalom

course

  • EA licence variation submitted
slide-9
SLIDE 9
slide-10
SLIDE 10
  • Developer UK Hydro
  • Planning and EA licence consent
  • One Archimedean screw generating100kw
  • Construction due to commence Summer 2015
slide-11
SLIDE 11
  • Developer Barn Energy
  • Kaplan turbine, generating 500kw
  • Mainly on Wakefield Council land, long

access track

  • EA and Planning consented
  • Due to start construction

Summer 2015

slide-12
SLIDE 12
  • 50/50 with Greene King (Ship Inn)
  • Got planning permission awaiting EA

consent, due end of May

  • Small scheme (100kw) but relatively easy

build

  • Due to start construction Autumn 2015
slide-13
SLIDE 13
slide-14
SLIDE 14
  • Started Construction February
  • Due to complete 11th September 2015
  • Generation approx. 280kw
slide-15
SLIDE 15
slide-16
SLIDE 16
  • Following sites are currently at Pre-app stage, planning &

EA:

  • Horbury Junction, River Calder, 100kw
  • Knottingley, River Aire, 500kw
  • Rotherham Weir, River Don, 220kw