may 2015
play

May 2015 13 hydro schemes in Yorkshire area currently ongoing - PowerPoint PPT Presentation

Sam ONeill Telecoms Manager May 2015 13 hydro schemes in Yorkshire area currently ongoing Changes to Feed In Tariff; further reduction prompting a height of activity Limited amount of suitable assets that are viable: Flow and head


  1. Sam O’Neill Telecoms Manager May 2015

  2. • 13 hydro schemes in Yorkshire area currently ongoing • Changes to Feed In Tariff; further reduction prompting a height of activity • Limited amount of suitable assets that are viable: Flow and head height v Access, connection to grid, heritage etc.

  3. • Developer UK Hydro, Planning and EA licence consented • Issues - CRT only own half weir, limited access rights to 2018 • Construction due to commence Summer 2015

  4. • Developer UK Hydro • EA application submitted however, Issue with pollution dilution and depleted reach • Looking at other options rather than Fishponds weir

  5. • Developer Yorkshire Hydro • EA licence consent • Failed planning due to flood risk and visible appearance. Have now reached agreement with EA on how to overcome the flood risk

  6. • Developer UK Hydro • Planning and EA consents, awaiting FPP approval • 3 turbines generating 450kw

  7. • Existing hydro scheme, not on C&RT land • Developer wishes to add another screw and canoe slalom course • EA licence variation submitted

  8. • Developer UK Hydro • Planning and EA licence consent • One Archimedean screw generating100kw • Construction due to commence Summer 2015

  9. • Developer Barn Energy • Kaplan turbine, generating 500kw • Mainly on Wakefield Council land, long access track • EA and Planning consented • Due to start construction Summer 2015

  10. • 50/50 with Greene King (Ship Inn) • Got planning permission awaiting EA consent, due end of May • Small scheme (100kw) but relatively easy build • Due to start construction Autumn 2015

  11. • Started Construction February • Due to complete 11 th September 2015 • Generation approx. 280kw

  12. • Following sites are currently at Pre-app stage, planning & EA: • Horbury Junction, River Calder, 100kw • Knottingley, River Aire, 500kw • Rotherham Weir, River Don, 220kw

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend