massachusetts lobstermen s association 3 14 2018
play

Massachusetts Lobstermens Association 3/14/2018 March 2018 1 - PowerPoint PPT Presentation

Massachusetts Lobstermens Association 3/14/2018 March 2018 1 Where are we in the process? Federal Permitting State Permitting December 2017 Draft COP submitted ENF (MEPA) & EFSB Ongoing updates to Applications COP until


  1. Massachusetts Lobstermen’s Association 3/14/2018 March 2018 1

  2. Where are we in the process? Federal Permitting State Permitting December 2017 Draft COP submitted ENF (MEPA) & EFSB • Ongoing updates to Applications COP until deemed sufficient • Available for review before finalizing • January/February 2018 MEPA hearing and scoping for Environmental Impact Report (DEIR). • MEPA Certificate released April 2018 EIS Scoping Hearings EFSB Hearing DEIR Submitted Public input opportunities (purple) May - August DEIR Review and FEIR production EFSB ongoing review August/September DEIS Released by BOEM March 2018 2

  3. Vineyard Wind: Local stakeholder and community focused since 2009 – First offshore wind developer to enter into a community partnership: Vineyard Power Coop – Non-profit serving 10% of Martha’s Vineyard’s customers – Letters of Support from all towns of Martha’s Vineyard and Nantucket, and Mashpee Wampanoag – First US offshore wind developer to engage a fisheries’ representative – Local staff with extensive U.S. offshore wind experience – Based in New Bedford – Offices in Vineyard Haven and Boston March 2018 3

  4. Turbine Site Identified by Multi-Year Stakeholder Process – BOEM – Federal Process – 2010 BOEM Task Force – Local government representatives – Multiple stakeholder meetings – Habitat and fisheries working groups – 2011: Request for Interest – 2012: Environmental Assessment & Call for Information – 2014: Lease Sale Notices – 2015: Auction and Lease issuance – 2015 – Present: Task Force & Working Groups on-going guidance and consultation – Massachusetts Policy – Energy Diversity Act of 2016 – Utilities procure total of 1600MW of offshore wind March 2018 4

  5. Proje ct Context and Background – Vineyard Wind Lease area OCS-A 0501 – ~261 square miles – Northern tip of Lease Area is ~35 miles offshore from Cape Cod, and ~14 miles south of Martha’s Vineyard and Nantucket – Study and analysis began as soon as lease acquired in 2015 – Building on earlier consultations by project and Vineyard Power – Offshore geological surveys in 2016 and 2017 Additional surveys planned for spring and summer 2018 March 2018 5

  6. Outreach Alliance to Protect Nantucket Sound Martha’s Vineyard Fishermen Preservation Trust; New England Fishery Management Council – – – Association to Preserve Cape Cod; Massachusetts Audubon Society; Northeast Fisheries Sciences Center; – – – Cape and Islands Self-Reliance; Massachusetts Clean Energy Center; Northeast Fishery Management Council; – – – Cape and Vineyard Electrical Cooperative; Massachusetts Fisheries Institute; Northeast Fishery Sector Managers X, XI, XIII, VII, – – – VIII; – Cape Cod Fishermen’s Alliance; – Massachusetts Fisheries Working Group; – Port of New Bedford; – Cape Light Compact; – Massachusetts Fishermen’s Partnership and Support Services; Recreational Fishing Alliance; – – Climate Action Business Association; Massachusetts Habitat Working Group; Rhode Island Fishermen’s Advisory Board; – – – Coalition for Social Justice; Massachusetts Lobstermen’s Association; Rhode Island Habitat Advisory Board; – – Conservation Law Foundation; – Nantucket Rotary Club; Scallop Industry Advisors Meeting; – – Coonamessett Farm Foundation; – National Academies of Sciences, Offshore Renewable Sierra Club; – – Eastern Fisheries; Energy Development and Fisheries Conference; – Stoveboat - Saving Seafood; – Environment Massachusetts; – National Wildlife Federation; – – The Nature Conservancy; – Environmental Business Council of New England; – Natural Resources Defense Council; – Town Dock; – Environmental League of Massachusetts; – New Bedford Harbor Development Commission; – University of Massachusetts (various campuses); and – Hercules SLR; – New England Aquarium; – Woods Hole Oceanographic Institute. New England Energy and Commerce Association; – Long Island Commercial Fishing Association; – March 2018 6

  7. Nearest suitable existing substations are in Barnstable – Minimizes amount of cable installed – No changes to existing transmission system will be required – Connection location enhances grid reliability by providing power at edge of grid system ~ 37 miles Federal waters March 2018 7

  8. Construction and Operations Plan Project Envelope Layout and Project Size Foundation WTGs • ~800MW project • 800MW of monopiles or 400MW of piles • 8 – 10MW WTG • Up to 106 WTG positions and up to 400MW of jackets • Rotor size of 164-180 m (538-591 ft) • Continuous construction from 2021 to • Pile driving hammer • Hub height of 109-121 m (358-397 ft) 2024 or 2 ~400MW stages with up to 5 • Scour protection on all positions • Installation with a jack-up vessel or years in-between construction periods • Installation with a jack-up vessel or vessel on dynamic positioning (DP) vessel on dynamic positioning (DP) with feeder barges with feeder barges Inter-array cables Export Cables Electrical Service Platform (ESP) • 66kV cables • Up to three 220kV export cables • Four light-weight ESPs or two • Example layout identified, not finalized • Two corridors identified with variants conventional ESPs • Maximum total cable lengths indicated • Max total cable lengths indicated • Each ESP installed on one monopile or • Installation techniques include jet plow, • Installation techniques include jet plow, a single jacket foundation mechanical plow & mechanical mechanical plow & mechanical • Scour protection on all positions trenching. trenching. Dredging in some locations • Installation using foundation and • Installation with a vessel on dynamic to achieve burial depth turbine installation vessels or positioning (DP) • Installation with a vessel on dynamic specialized crane vessel • Pre-lay grapnel run positioning (DP) and some use of an anchored vessel • Use of mattresses or rock protection on areas of minimal cable burial • Pre-lay grapnel run

  9. G:\Projects2\MA\MA\4903\MXD\COP\Wind_Development_Area_20171204.mxd 70°50'0"W 70°40'0"W 70°30'0"W 70°20'0"W 70°10'0"W 0 1 4580000 4580000 41°20'0"N 41°20'0"N 30 4570000 4570000 1 0 20 4560000 4560000 30 41°10'0"N 41°10'0"N Project Layout ) ! ( ( ! ( ! 1 ) " " ) ! ( 0 m ! ( ! ( n 5 2 ! ( 8 0 0 ! ( 1 ( ! 9 ! ( . A ! ( ! ( 4550000 ! ( 4550000 - 1 nm ( ! ( ! S ( ! ! ( ! ( ! ( ( ! C ! ( ! ( ( ! ( ! ! ( O ! ( ! ( .918 nm ( ! ( ! ( ( ! ! ( " ) " ) ( ! ( ! ( ! a ! ( ! ( ( ! 40 ! ( e ! ( ! ( ( ! . ! ( 7 r ! ( ! ( ( ! A 5 ( ! ! ( 6 ! ( ( ! ! ( ( ! ( ! n ! ( e m ( ! ( ! ( ! 20 ( ! 1 nm ! ( ! ( ( ! s 1 ! ( ! ( n a ! ( ! ( m ! ( ( ! ( ! ! ( ! ( e ! ( 41°0'0"N ! ( 4540000 ! ( 4540000 ! ( L ! ( ( ! ( ! ! ( ! ( ( ! 41°0'0"N ! ( d ! ( ( ! ( ! ( ! ( ! n ! ( ! ( ( ! ! ( i ( ! W ( ! ( ! ! ( ! ( ( ! ! ( ( ! d ( ! ( ! r ( ! 20 a ! ( ! ( y ! ( ! ( e n ( ! i V ( ! 4530000 4530000 50 40°50'0"N 40°50'0"N LEGEND Basemap: NOAA 12300-05-2008 4520000 4520000 Vineyard Wind Lease Area by OCS Block Number Wind Development Area for COP Review Bathymetric Contours 10m Interval WTG ( ! Electrical Service Platforms ) " *Please note, WTG and Offshore Substation yellow 4510000 4510000 and green markers have been enlarged in this figure for visibility ° 0 2.5 5 Kilometers Scale 1:360,000 1 inch = 9 kilometers 0 2 4 Nautical Miles 60 Map Coordinate System: NAD 1983 UTM Zone 19N 70°50'0"W 70°40'0"W 70°30'0"W 70°20'0"W 70°10'0"W Service Layer Credits:

  10. Foundations Monopiles Jackets March 2018 10

  11. Scour Protection Scour – Stone placed around foundation – Sized between 4-12 inches – 3-6 feet high Scour protection radius 22-26m (72-85ft) – Protects the foundation from the removal of sediments near the base. – Dimensions – 138ft - 170ft diameter March 2018 11

  12. Proposed Offshore Cable Corridors – 2 possible corridors: Western & Eastern (only 1 will be used) – Multiple options through Muskeget Channel – August/September 2017 surveys, more in 2018 – Routing – Considerations include water depth, bathymetry, SSU areas, etc. – Federal and state waters (Land Under the Ocean) – Avoidance of mapped eelgrass habitat and core habitat for whales – Minimization of impacts to hard/complex bottom areas – Installation via jet-plow, plow, or mechanical trenching – Target burial depth = 5 to 8 feet (1.5 to 2.5 m) – 6-foot-wide swath affected by trenching – Where sand waves are present, dredging will be used to achieve target burial depth – Extensive outreach with local and regional fishermen and their representatives March 2018 12

  13. Site Data Extensive data is available on the site that has been collected by Vineyard Wind and others

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend