Cost of Compliance with the 2014 Massachusetts MS4 Permit

Massachusetts Department of Environmental Protection Michael Giroux, Cameron Peterson, Eric Correia

slide-2
SLIDE 2

The Massachusetts Department of Environmental Protection

slide-3
SLIDE 3

Findings and Recommendations Cost Analysis Goals and Objectives Background Information

Roadmap

slide-4
SLIDE 4

Background

 The Six Minimum Control Measures The Central Massachusetts Regional Stormwater Coalition (Coalition)  Subject Towns: Southbridge, Holden, Millbury

slide-5
SLIDE 5

Worcester Polytechnic Institute

The Six Minimum Control Measures

WCPC DEP 2014

5

  • 1. Public Education and Outreach
  • 2. Public Involvement and

Participation

  • 3. Illicit Discharge Detection and

Elimination (IDDE)

  • 4. Construction Site Stormwater

Runoff Control

  • 5. Post Construction Site Runoff

Control

  • 6. Pollution Prevention and Good

Housekeeping

slide-6
SLIDE 6

Worcester Polytechnic Institute

Central Mass Regional Stormwater Coalition

WCPC DEP 2014

6

 13 Original Towns in Fiscal Year 2012  17 More Joined in Fiscal Year 2013

slide-7
SLIDE 7

Worcester Polytechnic Institute

Subject Towns

WCPC DEP 2014

7

Population 17,636 Town Budget $52,774,844 Area 36.2 mi2 Percent Impervious 7.04%

Holden

slide-8
SLIDE 8

Worcester Polytechnic Institute

Subject Towns

WCPC DEP 2014

8

Population 16,799 Town Budget $56,739,257 Area 20.9 mi2 Percent Impervious 8.69%

Southbridge

slide-9
SLIDE 9

Worcester Polytechnic Institute

Subject Towns

WCPC DEP 2014

9

Population 13,305 Town Budget $9,018,827 Area 16.3 mi2 Percent Impervious 13.09%

Millbury

slide-10
SLIDE 10

Project Goal and Objectives

 Project Goal  Objectives

slide-11
SLIDE 11

Worcester Polytechnic Institute

Project Goal

Provide the towns of Southbridge, Holden, and Millbury a comprehensive cost analysis of implementing the 2014 MS4 draft permit

WCPC DEP 2014

11

slide-12
SLIDE 12

Worcester Polytechnic Institute

Objectives

  • Objective 1: Become Educated
  • WCPC DEP 2014

12

slide-13
SLIDE 13

Worcester Polytechnic Institute

Objectives

Objective 1: Become Educated

  • Objective 2: Assess Compliance
  • WCPC DEP 2014

13

slide-14
SLIDE 14

Worcester Polytechnic Institute

Objectives

Objective 1: Become Educated Objective 2: Assess Compliance

  • Objective 3: Current Total Expenditures
  • WCPC DEP 2014

14

slide-15
SLIDE 15

Worcester Polytechnic Institute

Objectives

Objective 1: Become Educated Objective 2: Assess Compliance Objective 3: Current Total Expenditures

  • Objective 4: Identify Necessary Changes
  • WCPC DEP 2014

15

slide-16
SLIDE 16

Worcester Polytechnic Institute

Objectives

Objective 1: Become Educated Objective 2: Assess Compliance Objective 3: Current Total Expenditures Objective 4: Identify Necessary Changes

  • Objective 5: Create a Detailed Cost Analysis
  • WCPC DEP 2014

16

slide-17
SLIDE 17

Worcester Polytechnic Institute

Objectives

Objective 1: Become Educated Objective 2: Assess Compliance Objective 3: Current Total Expenditures Objective 4: Identify Necessary Changes Objective 5: Create a Detailed Cost Analysis

  • Objective 6: Create an Informational Video

WCPC DEP 2014

17

slide-18
SLIDE 18

Cost Analysis

 Current Cost of Compliance  Example Cost Sheet: Holden  Anticipated Future Costs for Complying with the 2014 MS4 Draft Permit

slide-19
SLIDE 19

Worcester Polytechnic Institute

Current Cost of Compliance

WCPC DEP 2014

19

Control Measure Holden Millbury Southbridge Public Education $1,000 $566 $10,952 Public Participation $0 $3,242 $0 IDDE $3,520 $4,678 $2,452 Construction $0 $350 $0 Post Construction $1,760 $0 $0 Good Housekeeping $180,246 $576,124 $255,200 Total $186,526 $584,960 $268,604

Impervious Area

7.04% 13.09% 8.69%

slide-20
SLIDE 20

Worcester Polytechnic Institute

Example Future Cost Chart: Holden

WCPC DEP 2014

20

Control Measure Annual Cost One-Time Cost Intermittent Cost Public Education $9,908 $0 $0 Public Participation $0 $0 $0 IDDE $7,872 $314,494 $50,440 Construction $0 $770 $0 Post- Construction $5,280 $1,496 $7,436 Good Housekeeping $220,562 $6,292 $0 Miscellaneous $15,168 $2,376 $0 Total $258,790 $325,428 $57,876

slide-21
SLIDE 21

Worcester Polytechnic Institute

Example Future Cost Chart: Holden

WCPC DEP 2014

21

Control Measure Annual Cost One-Time Cost Intermittent Cost Public Education $9,908 $0 $0 Public Participation $0 $0 $0 IDDE $7,872 $314,494 $50,440 Construction $0 $770 $0 Post- Construction $5,280 $1,496 $7,436 Good Housekeeping $220,562 $6,292 $0 Miscellaneous $15,168 $2,376 $0 Total $258,790 $325,428 $57,876

slide-22
SLIDE 22

Worcester Polytechnic Institute

Example Future Cost Chart: Holden

WCPC DEP 2014

22

Control Measure Annual Cost One-Time Cost Intermittent Cost Public Education $9,908 $0 $0 Public Participation $0 $0 $0 IDDE $7,872 $314,494 $50,440 Construction $0 $770 $0 Post- Construction $5,280 $1,496 $7,436 Good Housekeeping $220,562 $6,292 $0 Miscellaneous $15,168 $2,376 $0 Total $258,790 $325,428 $57,876

slide-23
SLIDE 23

Worcester Polytechnic Institute

Anticipated Future Costs for Complying with the 2014 MS4 Draft Permit

WCPC DEP 2014

23

Holden Southbridge Millbury Impervious Area 7.04% 8.69% 13.09% Number of Outfalls 144 206 267 Current Cost $186,526 $268,604 $584,960 Predicted Annual Cost $258,790 $343,008 $735,629 Percent Increase 39% 28% 26%

slide-24
SLIDE 24

Findings and Recommendations

 Funding Techniques  Centralized Management  Innovative Funding  Regionalization

slide-25
SLIDE 25

Worcester Polytechnic Institute

Finding & Recommendation 1

Finding

  • Funding Techniques

─ CIC Grant ─ Alternatives ─ Millbury’s Technique

Recommendation

  • Seek Alternative Funding

─ 604(b), Source Water Protection, etc.

25

WCPC DEP 2014

slide-26
SLIDE 26

Worcester Polytechnic Institute

Finding & Recommendation 2

Finding

  • Easier With

Stormwater Coordinator

─ Scattered Information

Recommendation

  • Designated Person

─ DCR

26

WCPC DEP 2014

slide-27
SLIDE 27

Worcester Polytechnic Institute

Finding & Recommendation 3

Finding

  • Innovative

Management

─ Millbury’s Piping ─ Art Contest

Recommendation

  • Be Creative

27

WCPC DEP 2014

slide-28
SLIDE 28

Worcester Polytechnic Institute

Finding & Recommendation 4

Finding

  • Regionalization Is

Beneficial

─ More Efficient ─ High Cost/Benefit Ratio ─ Savings with Coalition

Recommendation

  • Form Coalitions
  • Work With

Neighbors

28

WCPC DEP 2014

slide-29
SLIDE 29

Worcester Polytechnic Institute

Citations

http://www.epa.gov/region1/npdes/stormwater/ma/ ic/MA_Imperv2010_Holden.pdf http://www.epa.gov/region1/npdes/stormwater/ma/ ic/MA_Imperv2010_Millbury.pdf http://www.epa.gov/region1/npdes/stormwater/ma/ ic/MA_Imperv2010_Millbury.pdf https://dlsgateway.dor.state.ma.us/DLSReports/DLS ReportViewer.aspx?ReportName=At_A_Glance&Repo rtTitle=At+A+Glance - http://srjengineering.com/services_npdes_08.html

WCPC DEP 2014

29

slide-30
SLIDE 30

Questions?