Market Performance and Planning Forum (examples) March 23, 2011 - - PowerPoint PPT Presentation

market performance and planning
SMART_READER_LITE
LIVE PREVIEW

Market Performance and Planning Forum (examples) March 23, 2011 - - PowerPoint PPT Presentation

Market Performance and Planning Forum (examples) March 23, 2011 How Would Flexible Ramping Constraint Affect LMP? Partially loading 2 generators where 1 alone would seem to be sufficient. Two generators in the market to fill a 100MW


slide-1
SLIDE 1

Market Performance and Planning Forum (examples)

March 23, 2011

slide-2
SLIDE 2

How Would Flexible Ramping Constraint Affect LMP?

Slide 2

  • Partially loading 2 generators where 1 alone would seem to be

sufficient.

  • Two generators in the market to fill a 100MW load.
  • Assume each generator has a range of 40-105 and one has a cost of

$30 while the other has a cost of $35

  • Without any flexible ramping constraints the solution would be for the

$30 generator to fill the 100MWs by itself.

  • With the flexible ramping constraint that each would be dispatched;

presumably the $35 unit would be dispatched to 40 while the cheaper

  • ne would be dispatched to 60.
  • Are the LMPs of each generator correct?
slide-3
SLIDE 3

Example 1

  • Flexi-Ramp constraint enforced in RTPD.
  • Forecast Load: 100MW
  • Forecast uncertainty (Flexible ramp req.): +50MW
  • Resources Available
  • Unit 1: Pmin=40MW, Pmax=105MW, Energy Bid=$30
  • Unit 2: Pmin=40MW, Pmax=105MW, Energy Bid=$35
  • The following two constraints are enforced:

– ENgen-ENload = 0 (Power balance constraint Ignoring losses) – FRonlinegen-up >= FRreq-up (Flexi-ramp constraint)

Page 3

slide-4
SLIDE 4

Example 1 (cont.)

  • Without Flexi-ramp Constraint:

– Unit 1: Committed and loaded to 100MW at price of $30 – Unit 2: Remains Un-committed

  • With Flexi-ramp Constraint enforced in RTPD:

– Unit 1: Committed and loaded to 60MW at price of $30

  • Contributing 45MW of online capacity to Flexi-ramp

constraint – Unit 2: Committed at Pmin= 40MW

  • Contributing 5MW of online capacity to Flexi-ramp constraint
  • Note the energy prices in RTPD are not binding. Only

RTD prices are binding.

Page 4

slide-5
SLIDE 5

Example 1 (cont.)

  • In RTD binding interval no flexi-ramp constraint is

enforced.

  • Assuming actual load in RTD is 100MW

– Unit 1: Dispatched to 60MW at a marginal price of $30 – Unit 2: Dispatched to 40MW at a marginal price of $30

  • Assuming actual load in RTD is 150MW

– Unit 1: Dispatched to 105MW at a marginal price of $35 – Unit 2: Dispatched to 45MW at marginal price of $35

Page 5

slide-6
SLIDE 6

Example 2

Page 6

  • Flexi-Ramp constraint enforced in RTPD.
  • Forecast Load: 100MW
  • Forecast uncertainty (Flexible ramp req.): +100 MW
  • Resources Available
  • Unit 1: Pmin=40MW, Pmax=105MW, Energy Bid=$30
  • Unit 2: Pmin=40MW, Pmax=105MW, Energy Bid=$35
  • The following two constraints are enforced:

– ENgen-ENload = 0 (Power balance constraint Ignoring losses) – FRonlinegen-up >= FRreq-up (Flexi-ramp constraint)

slide-7
SLIDE 7

Example 2 (cont.)

Slide 7

  • Without Flexi-ramp Constraint:

– Unit 1: Committed and loaded to 100MW at price of $30 – Unit 2: Remains Un-committed

  • With Flexi-ramp Constraint enforced in RTPD:

– Unit 1: Committed and loaded to 60MW at price of $30

  • Contributing 45MW of online capacity to Flexi-ramp

constraint – Unit 2: Committed at Pmin= 40MW

  • Contributing 55MW of online capacity to Flexi-ramp

constraint

  • Note the energy prices in RTPD are not binding. Only

RTD prices are binding.

slide-8
SLIDE 8

Example 2 (cont.)

Slide 8

  • In RTD binding interval no flexi-ramp constraint is

enforced.

  • Assuming actual load in RTD is 100MW

– Unit 1: Dispatched to 60MW at a marginal price of $30 – Unit 2: Dispatched to 40MW at a marginal price of $30

  • Assuming actual load in RTD is 200MW

– Unit 1: Dispatched to 105MW at a marginal price of $35 – Unit 2: Dispatched to 95MW at marginal price of $35