Maine Public District MPD 2018 Transmission Filing MPD OATT: Open - - PowerPoint PPT Presentation
Maine Public District MPD 2018 Transmission Filing MPD OATT: Open - - PowerPoint PPT Presentation
JUNE 27, 2018 Maine Public District MPD 2018 Transmission Filing MPD OATT: Open Customer Meeting This meeting is scheduled per the MPD OATT Open Access Transmission Tariff Attachment J Section III B1. Between 45 Days and 60 Days after
MPD OATT: Open Customer Meeting
2
This meeting is scheduled per the MPD OATT Open Access Transmission Tariff Attachment J – Section III B1. “Between 45 Days and 60 Days after the Publication Date, Transmission Provider will hold an open meeting to discuss the Annual Update (“Customer Meeting”).”
Open Customer Meeting Agenda
Wednesday, June 27, 2018 (9:30 AM to 10:30 AM)
3
- Emera Maine Services
- 2018 Transmission Rate - Major Change Drivers
- Historic Comparison
- Five Year Outlook
- Other July 1 Rate Changes (D, SC, DSM)
- Discussion / Questions
4
Safe and Reliable Electricity Delivery
- Operations and Controls
- Maintenance and Construction
- Restoration
5
- Emera Maine serves two separate districts:
- Maine Public District (MPD)
- Bangor Hydro District (BHD)
- Each district has different transmission
rates
- The two districts are connected to
separate transmission grids
Two Districts – BHD and MPD
Transmission and Distribution
6
Rates and Cost of Service Formula
7
Capitalized Cost of Grid X W.A.C.C. Operating Expense Annual Revenue Requirement
Service Rate Making
8
Capitalized Cost of Grid X W.A.C.C. Operating Expense Annual Revenue Requirement
- Distribution Rates (MPUC)
- Stranded Cost (MPUC)
- Conservation or DSM (MPUC)
- Transmission (FERC)
Today’s Agenda
9
- Welcome
- Overview of EM Transmission Service
- Major Change Drivers
- Transmission Rate Changes
- Five Year Outlook
- Other Rate Changes
- Discussion / Questions
10
- 2017 Retail Settlement Expired
- Transmission Investment
- Completed projects in 2017
- Cost of 2017 operations
- Transmission Formula Changes
- 2018 Federal Income Tax Rate Change from 35% to 21%
Major Transmission Rate Change Drivers
11
Transmission Rate Bill Impact
Customer Class Sample Usage 2018 Change Residential 500 kWh $ 2.12 Medium (ES) 0.25 mW / 91.25 mWh $ 170.00 Large (EP-T) 1.175 mW / 450 mWh $ 2,573.25 Large (ES-T) 0.600 mW / 300 mWh $ 1,830.00 Trans (ST) 2.0 mW / 800 mWh $ 3,780.00
July 1 Rate Change Monthly Bill Rate Impacts
2018 Active and Planned Work
12
- Completion of protection upgrades and relay work for
6901 Rebuild
- Emergency structure replacements at river crossing in
Madawaska – complete; $1M
- Targeted Rebuild of Line 6913
- Mapleton – 0.8 miles; complete; $814K
- Roadside section – started; $408K
- Right-of-Way section – fall; $538K
- Line 4407 maintenance - continued structure replacements
due to woodpecker damage
- Phase 3 – this fall; $1.2M
6905/6909 Riverbank Erosion
13
Lines 6905/6909 After Stabilization
14
Line 4407 Woodpecker Damage
15
16
Condition Inspections
EXTERNAL SHELL ROT WOODPECKER DAMAGE BROKEN CROSS ARM EXCESSIVE INTERNAL DECAY / HEART ROT
2017 - 2018 Projects
17
Emera Maine - Maine Public District
2017 - 2018 Plant Additions
Project Name Spend Through 2017 2018 Forecast In Service Date In Rate Base Line 6901 Rebuild (2238) $8,898,699 $0 December 2016 2017 Line 6901 Protection Upgrades (125B) $649,728 $97,000 Summer 2018 2018 Line 6901 ReEnergy Tap (388B) $55,808 $0 December 2017 2017 Line 4407 Structure Replacement Phase 1 (750A) $540,457 $0 January 2017 2017 Line 4407 Structure Replacement Phase 2 (784A) $1,862,608 $0 December 2017 2017
2017 - 2018 Projects (continued)
18
Emera Maine - Maine Public District
2017 - 2018 Plant Additions
Project Name Spend Through 2017 2018 Forecast In Service Date In Rate Base Line 4407 Structure Replacement Phase 3 (844B) $0 $1,185,000 December 2018 2018 Line 6910 Rebuild Phase 2 (157B) $5,689,632 $0 December 2016 2017 Line 6910 Rebuild Phase 3 (256B) $4,292,352 $12,840 December 2017 2018
2017 - 2018 Projects (continued)
19
Emera Maine - Maine Public District
2017 - 2018 Plant Additions
Project Name Spend Through 2017 2018 Forecast In Service Date In Rate Base Line 6913 Mapleton (2349) $178,110 $635,407 June 2018 2018 Line 6913 Right-of-Way Rebuild (200C) $0 $537,782 December 2018 2018 Line 6913 Roadside Targeted Rebuild (845B) $0 $407,666 December 2018 2018 Line 6905 / 6909 Structure Replacements (789B) $678,635 $335,136 June 2018 2018
20
System Improvements Proposed or Under Consideration for Years 2019 - 2022
Line 6901 Rebuild – Fort Fairfield Tap (Proposed for 2019)
- 1.2 miles of 69kV in ROW; $500K - $700K
Line 6903 Rebuild – Otter Creek to Limestone (Proposed for 2019)
- 9.8 miles of 69kV roadside construction; $4.9M - $6.9M
Line 6930 Rebuild – Dow Siding to Maysville Siding (Proposed for 2019)
- 3 miles of 69kV in ROW; $1.5 - $2.0M
Line 6930 Rebuild – Maysville Siding to Washburn (Proposed for 2020)
- 8.4 miles of 69kV in ROW over two years; $4.5M - $6.0M
Line 1176 Rebuild – Presque Isle to Easton (Conceptual 2021)
- 11.9 miles of 138kV in ROW; $6.0M - $8.5M
Line 6915 Rebuild – Flo’s Inn to North Presque Isle (Conceptual 2022)
- 11.9 miles of 138kV in ROW; $6.0M - $8.5M
Line 6930 – Washburn to Ashland (Conceptual 2022)
- 3 miles of 69kV in ROW; $1.5 – $2.0M
Line 6950 – Westfield to Mars Hill (Conceptual 2022)
- 3.4 miles of 69kV in ROW; $3.0M - $3.5M
Today’s Agenda
21
- Welcome
- Overview of EM Transmission Service
- Major Change Drivers
- Transmission Rate Changes
- Five Year Outlook
- Other Rate Changes
- Discussion / Questions
Revenue Requirement
22 $0 $1,000,000 $2,000,000 $3,000,000 $4,000,000 $5,000,000 $6,000,000 $7,000,000
2013 2014 2015 2016 2017 2018 Revenue Requirement ($)
2018 MPD Transmission Revenue Requirement
(2017 Discount shown in RED)
$0 $2,000,000 $4,000,000 $6,000,000 $8,000,000 $10,000,000 $12,000,000 $14,000,000
2013 2014 2015 2016 2017 2018 2019 2020 2021 2022 Estimated Revenue Requirement ($)
2018 MPD Retail Transmission Revenue Requirement Investment & Refund
Outlook: Retail Revenue Requirement
23
- 30.00%
- 20.00%
- 10.00%
0.00% 10.00% 20.00% 30.00% 40.00% 50.00% 60.00% 70.00%
2018 2019 2020 2021 2022 Estimated
MPD Projected Year-Over-Year Transmission Rate Changes (Pricing based on Medium Secondary at 250kW and 91,250 kWh
Outlook: Yearly Rate Changes
24 $0.009/kWh $0.020/kWh $0.018/kWh $0.022/kWh $0.015/kWh
Yearly Transmission Cost Increases
25
Projected MPD Transmission Rate Changes Yearly Bill Impacts
Customer Class Sample 2018 2019 2020 2021 2022 Residential 500 kWh
$57 $94 $143 $119 $126
Medium (ES) 0.25 mW / 91.25 mWh
$9,690 $16,019 $24,263 $20,218 $21,401
Large (EP-T) 1.175 mW / 450 mWh
$55,554 $91,841 $139,104 $115,912 $122,697
Large (ES-T) 0.600 mW / 300 mWh
$34,200 $56,539 $85,635 $71,357 $75,534
Trans (ST) 2.0 mW / 800 mWh
$81,120 $134,106 $203,120 $169,254 $179,162
Today’s Agenda
26
- Welcome
- Overview of EM Transmission Service
- Major Change Drivers
- Transmission Rate Changes
- Five Year Outlook
- Other Rate Changes
- Discussion / Questions
27
- 2018 MPD Distribution Rate Adjustment
- An increase from 5.92 cents per kWh -> 6.23 per kWh
- Average residential customer using 500 kWh per month will see an
increase about $1.58 cents on their monthly bill
Distribution Rate Adjustment
28
- Emera Maine collects funds on behalf of Efficiency Maine
- Amount collected based on a yearly assessment amount
- 2018 MPD Conservation Rate Adjustment
- A decrease from 0.365 cents per kWh -> 0.243 per kWh
- Average residential customer using 500 kWh per month will see a
reduction of about 61 cents on their monthly bill
- The Conservation Charge is rolled into the Distribution Rate on the
MPD bill.
Conservation Rate Adjustment
29
- Stranded Costs originally recovered the cost of long term electricity
supply contracts
- It also includes new long term contracts as a result of State policy,
settlements, and other adjustments.
- 2018 MPD Stranded Cost Rate Adjustment
- Decrease in Maine Yankee Refund this year
- Refund reduced from 0.200 cents per kWh -> 0.105 cents per kWh
- Average residential customer using 500 kWh per month will see an
increase of about 48 cents on their monthly bill
- The Stranded Cost Rate is rolled into the Distribution Rate on the
MPD bill.
Stranded Cost Rate Adjustment
30
Total Rate Bill Impact
Customer Class Sample Usage 2018 Change Residential
Impacted by T, D, SC & DSM
500 kWh $ 3.57 Medium (ES) Impacted by T, D, SC & DSM 0.25 mW / 91.25 mWh $ 259.29 Large (EP-T)
Impacted by T, D, SC & DSM
1.175 mW / 450 mWh $ 2,921.28 Large (ES-T)
Impacted by T, D, SC & DSM
0.600 mW / 300 mWh $ 2,058.84 Trans (ST)
Impacted by T, D & SC
2.0 mW / 800mWh $ 4,983.53
July 1 Rate Change Monthly Bill Rate Impacts
31
$0.058 $0.057 $0.056 $0.055 $0.056 $0.058 $0.057 $0.058 $0.059 $0.005 $0.007 $0.007 $0.008 $0.010 $0.008 $0.008 $0.007 $0.007 $0.026 $0.025 $0.013 $0.013 $0.011 $(0.004) $(0.004) $(0.003) $(0.001) $0.002 $0.002 $0.002 $0.002 $0.001 $0.001 $0.002 $0.004 $0.003 $0.094 $0.081 $0.077 $0.076 $0.081 $0.086 $0.084 $0.070 $0.072
$(0.02) $- $0.02 $0.04 $0.06 $0.08 $0.10 $0.12 $0.14 $0.16 $0.18 $0.20 2010 2011 2012 2013 2014 2015 2016 2017 2018 $/kWh
Emera Maine - Maine Public District Rate Components for Basic Residential Service 2010-2018 Calendar Years
(amounts expressed in 2016 real dollars)
Distribution Transmission Stranded Costs Conservation Supply
Today’s Agenda
32
- Welcome
- Optional: Overview of EM Transmission Service
- Major Change Drivers
- Transmission Rate Changes
- Five Year Outlook
- Other Rate Changes
- Discussion / Questions