SLIDE 1
M ALCOLM D RILLING C OMPANY I NC . D OWNTOWN S AN F RANCISCO - - PowerPoint PPT Presentation
M ALCOLM D RILLING C OMPANY I NC . D OWNTOWN S AN F RANCISCO - - PowerPoint PPT Presentation
M ALCOLM D RILLING C OMPANY I NC . D OWNTOWN S AN F RANCISCO Transbay Construction 140ft 181 Fremont 125 ft Site preparation Pre Drill to remove existing timber piles Replace Class 1 contaminated soil with engineering fill. 56
SLIDE 2
SLIDE 3
SLIDE 4
SLIDE 5
SLIDE 6
Transbay Construction
SLIDE 7
125 ft 140ft
181 Fremont
SLIDE 8
Site preparation
- Pre Drill to remove
existing timber piles
- Replace Class 1
contaminated soil with engineering fill.
SLIDE 9
9.2’ 3.3’’
- 56 Each, 95’ deep cutter soil
mix concrete panel
- Each has one two or three
wide 90’ flange beams
- Drilling sequence is very
critical due to Primary / Secondary panels
- Tracking large amount of
data
SLIDE 10
- 80ft long sampling
beam
- Dip into the freshly
installed concrete panel and collect sample at various elevation
- Sample then cast into
cylinders and break at 3/7/14/28 days
- Test for both strength
and permeability
SLIDE 11
Continuous water spraying to suppress ill odor Splash protection
SLIDE 12
Reference Frame, set to precise location to allow accurate placement
- f the Wide Flanges
Checking Plumbness
SLIDE 13
Wide Flange - Cutting the site in half. Consistently storing 10 – 15 beams on site.
SLIDE 14
Spoil Pool – Stored on site for 24 hours before it solidifies and ready to be off hauled.
SLIDE 15
SLIDE 16
SLIDE 17
SLIDE 18
SLIDE 19
SLIDE 20
SLIDE 21
SLIDE 22
SLIDE 23
Test Pile – 72” diameter, 263.5’ deep, 28’ into rock The actual test - 22 hours continuous monitoring with max load of 9200 kips
SLIDE 24
Report of the test shows satisfactory results We now move on to production ! Not so fast… More preparations!
SLIDE 25
100ft 120 – 130 ft 20+ ft
SLIDE 26
To do the work we need:
- Bauer BG 46 Rotary Drill Rig
- Sumitomo 1500 Crawler Crane
- Leffer 2.5m Casing Oscillator
- Oscillator Power Pack
- 120 LF of 6’ diameter double wall casing
- 270 LF of 5’ diameter rebar cage, 1 per pile
- Air Compressor
- 7 each - 20,000 gal Baker Tanks
- Boom Concrete Pump
- Excavator and Loader
- Concrete Trucks
- Off Haul dump trucks
And we have: 125’ by 140’ … …
SLIDE 27
SLIDE 28
Site Reconfiguration – Disintegrate the scaffold Move all baker tanks to a different location to make access for drilling operation for the remaining piles.
SLIDE 29
SLIDE 30
SLIDE 31
SLIDE 32
Pile installation procedure:
- Set up over a pile and drill the top 5-10’
- Start twisting casing using oscillator and charge the hole with polymer slurry
- Continue drilling while adding more casing
(20’ section each time until 100+’ of casing BGS)
- Continue drilling down to top of rock
(rock verified by Geotechnical engineer on site)
- Drill 20’ of rock socket
- Do a complete water exchange to remove all suspended solid
- Pick / splice / set rebar cages
(260+’ cage came in four 60+’ pieces)
- Pour concrete
- Conduct Crosshole Sonic Log on each pile upon completion
SLIDE 33
SLIDE 34
SLIDE 35
Fresh slurry going into the hole Dirty slurry coming out
- f the hole
SLIDE 36
SLIDE 37
These are for 1 pile Me, measuring cages
SLIDE 38
SLIDE 39
Color coding the verticals to make sure they can splice properly.
SLIDE 40
SLIDE 41
SLIDE 42
SLIDE 43
SLIDE 44
SLIDE 45
SLIDE 46
SLIDE 47
SLIDE 48
SLIDE 49
SLIDE 50
Remember this guy? That’s our test pile ! Its about 15 mins since you saw it the last time, for us at that time was a year!
SLIDE 51
- Put in lot of effort in pre planning will help you succeed in a
complex job like this
- Team work is very important. Good communicated between
the members of the team will help the job go smooth
- Track every detail, adjust accordingly
- Experience is very important, but for job like this, hardly
anyone will have the experience. Hence, being knowledgeable and able to react quickly to problems is essential.
SLIDE 52