TMALL 0141 Presentation v 1.0
Lund-Arlv, Project review during the tender period Agenda - - PDF document
Lund-Arlv, Project review during the tender period Agenda - - PDF document
TMALL 0141 Presentation v 1.0 four tracks Lund-Arlv, Project review during the tender period Agenda 12:30-12:45 Purpose of the meeting and presentation of participants 12:45-13:30 Business proposal 13:30-13:45 Short break 13:45-15:15
2
Agenda 12:30-12:45 Purpose of the meeting and presentation of participants 12:45-13:30 Business proposal 13:30-13:45 Short break 13:45-15:15 Orientation of the project according to AFB.24
Project review during the tender period
3
(LUF Ch 1 § 24) The purchasing unit shall treat all suppliers in an equal an non- discriminating way, as well as executing the procurement in an open and transparent way.
- The same identical presentation is shown to all invited tenderers.
- The only questions that will be answered are:
– Questions for which the answer can be read straight from the tender documents – General questions about the project – General questions about procurement law/LUF
- Questions & answers will be sent out to all invited tenderers.
- This presentation will be published on the project website.
The presentation will not be part of the tender documents.
The Law governing the project review during tender period
4
5
Senior Project Manager
Jens-Peter Eisenschmidt
Project Manager Railwayplan Lund-Flackarp
Jenny Åkerholm
Project Manager Civil works
Marie Minör
Project Manager Railway
Thomas Hallgren
Project Manager Construction
Kristofer Söderberg
Project Manager Performance Management
Patrik Dymling
Procurement Manager
Malin Isaksson
Special support
Engineering - Construction Engineering - Systems Engineering - Environment Land Negotiation Communication HSQ
Project Organisation
6
Where
7
- Expansion from two to four tracks, 11 kilometres
Lund-Flackarp 3 km + Flackarp-Arlöv 8 km
- Rebuilding of three stations in Hjärup, Åkarp and
Arlöv. New station, Klostergården (Lund)
- Total budget approx. Total budget 520 M EUR
Flackarp-Arlöv 400 M EUR Lund-Flackarp 120 M EUR (at 2015 price levels)
What
8
- Higher capacity on the railway
- Reduce noise pollution
- Reduce traffic disturbances and congestions
- Reduce the railway barrier effect
Why
9
Preliminary Time plan
10
- Tender Documents, June 2016
- The railwayplan Flackarp-Arlöv gained legal force, November 2016
- Tenders, March 14th 2017
- Contract signed, May/June 2017
Where are we now?
11
Board decision 2016-04-20
- Design and Build contract
- Procurement procedure: Negotiated procedure, (LUF)
- Collaborative business relationship
- Payment form: current account with incentives
- Incentive 80/20 over och under the target cost
- Added value: 25 %
- Contract period: 2017-2022, Lund- Flackarp 2023
- ECI on the part Lund-Flackarp as an Option with a possibly exit
- Warranty period: 5 år
Contract form Lund-Arlöv
12
Risk (higher cost than target cost) – is split 80/20 between Client and Contractor Target cost =Tender amount Incentives (lower cost than target cost) – is split 80/20 between Client and Contractor Fixed compensation= 9% of the target cost
Risk sharing Lund-Arlöv
13
- The contractor will enter the project at an early
stage
- Collaboration
- The contractor affects the design of the project
early on as much influence as possible in time, cost and content
What is ECI - Early Contractor Involvement?
14
ECI - Contrakt
Phase 1 ABT Phase 2 ABT Phase 1 The planning and development phase
- Necessary planning
- Production Cost
- Detailed time schedule
- Risk Management
- Target cost for phase 2
Early Contractor Involvement - Phases
15
Client’s control of constructability 2017 – Start of design/construction 2019 – 2021 Traffic on temporary tracks 2021 Traffic on new 4-track Flackarp - Arlöv 2023 Traffic on new 4-track Lund - Arlöv
Roadmap
16
Start 1/8 2017
17
2017-2018
18
- Design
- Noise barrier in Arlöv moves west.
- Bridge over Lommavägen i Arlöv, completed Jan 2018
- Bridge E6 over road and temporary tracks, completed April 2018
- Pipes which cross E6 east and west of the railway.
- When the project starts Gränsvägen will be ready between
Lundavägen and section 1/100.
- Temporary bridge Gränsvägen and accending road, completed Jan
2018
- Temporary bridge Vragerupsvägen and accending road, completed
April 2018.
- Tunnel for walking and bicycling at Burlövs station, completed June
2018
Civil works
19
Civil works
Bridge, Lommavägen jan 2018 E6 two bridges and pipes that cross E6 april 2018
- Temp. bridge
Gränsvägen and road jan 2018
- Temp. bridge
Vragerupsvägen and road april 2018 Tunnel, Burlöv station West part juni 2018 Noise barrier moves Level crossing Alnarpsvägen closed jan 2018
20
Design Reconstrution of the western part of Arlöv railway yard 5 switches removed 12 new switches to be installed About 2000m new track About 3000m new catenery Signalling system Bombardier interlocking 95 (Side contractor) One of the most busiest tracks in Sweden Lommabanan closed for about 3 month
BEST
21
July 2018
22
2018-2019
23
New pipes and cables in Bruksvägen Pond near E6 Construction for Alnarpsån under Sockervägen completed Jan 2019 Bridge over Kronetorpsvägen the west part, completed Jan 2019 Excavation work for temporary tracks
Civil works
24
Civil works
West bridge, Kronetorpsvägen jan 2019 Pipes and cables, Bruksvägen. Pond near E6 Construction, Alnarpsån, (creek) Sockervägen jan 2019
25
Temporary tracks Flackarp-Arlöv, about 5000m Reconstruction of the west part of Arlöv railway yard Temporary platforms in Åkarp and Hjärup 4 new switches in Åkarp Bombardier signalling system on temporary track 10 000m track 15 new points 12 000m catenery The option Lund-Flackarp must be called off
BEST
26
July 2019
27
2019-2020
28
Tunnel for walking and bicycling at Burlövs station east part, completed Jan 2020 Station bridge Hjärup, completed June 2020 Excavation work for the new four tracks Option Excavation work for the new four tracks Lund-Flackarp
Civil works
29
Civil works
Tunnel, walking/bicycle, Burlöv station West part juni 2018 East part jan 2020 Station bridge, Hjärup juni 2020
30
Dismantling/demolition of excisting 2-track Flackarp-Arlöv Design Reconstruction of the east part of Arlöv railway yard 4 switches removed 8 new switches to be installed About 1500m new track About 2000m new catenery Bombardier signalling system
BEST
31
October 2019
32
2020-2021
33
- E6 bridge over 4-tracks, complete oct 2020
- Bridge Alnarpsvägen, complete oct 2020
- Bridge Gränsvägen, complete oct 2020
- Bridge Lommavägen in Hjärup, complete oct 2020
- Bridge Vragerupsvägen, complete oct 2020
Option:
- Bridge Ringvägen in Lund, complete oct 2020
- New tunnel for walking and bicycling at Klostergården, complete oct
2020
- New bridge over Höje å, complete oct 2020
- New bridge over road108, complete oct 2020
Civil works
34
Civil works
E6 two bridges and pipes that cross E6 april 2018 Bridge over 4-tracks,
- ct 2020
Bridge Gränsvägen
- Temp. jan 2018
finished oct 2020 Bridge Vragerupsvägen
- Temp. april 2018
finished oct 2020 Bridge Alnarpsvägen,
- ct 2020
Bridge Lommavägen in Hjärup, oct 2020 Tunnel walking/bicycle at Klostergården Sept 2020 (option) Höje å (creek) Sept 2020 (option) Road 108 Sept 2020 (option) Ringvägen, Lund Sept 2020 (option)
35
Tunnel in Åkarp, finished jan 2021 Bridge over Kronetorpsvägen (east side), completed jan 2021
Civil works
36
Civil works
West bridge, Kronetorpsvägen Jan 2019 East bridge jan 2021 Tunnel Åkarp Jan 2021
37
Construction of new 4-track Flackarp-Arlöv Temporary platform in Hjärup, east side New platform in Burlöv, east side New platforms i Åkarp 35 000m track 20 new switches 40 000m catenery Bombardiers signalling system Option: New 2-track Lund-Flackarp west side 6 000m new track 7 new switches 7 000m catenery
BEST
38
July 2021
39
July 2021
40
2021-2022
41
Completion east side of Hjärups station with support structures, completed June 2022 Restoration of land continously. The big work with restoration will take part when the temporary tracks are demolished. Option: Demolition existing bridge Ringvägen Excavation and ground preparation for new tracks east side
Civil works
42
Civil works
Hjärup station, support structures East part, june 2022 Demolition existing bridge Ringvägen
43
Start demolition/dismantling of temporary track Completion and opening of new platform east side in Hjärup Option: Demolition/dismantling of existing 2-track Lund-Flackarp
BEST
44
October 2021
45
July 2022
46
July 2022
47
2022-2023
48
Option New bridge over Ringvägen east part, completed sept 2022 New tunnel for walking and bicycling east side Klostergården, completed sept 2022 New station Klostergården open June 2023
Civil works
49
Civil works
Bridge , Ringvägen East part sept 2022 Tunnel, walking/bicycle, Klostergården, east part sept 2022
50
Option Construction of new 2-track Lund-Flackarp, east side 6 000m track 8 000m catenery Bombardier signalling system New platforms Klostergården Restoration of land used for temporary occupation
BEST
51
July 2023
52
- Commit to a close collaborative relationship!
- Collaboration is the critical factor for success
Collaborative business relationship
53
Co-location
- Better understanding of the project
- Improved teamwork
- Shorten ways of decision
Collaborative business relationship
54
Safe working environment
- Always the highest priority
- A mutual commitment to keep a high standard
- From top to bottom and bottom to top
Collaborative business relationship
55
Risk management
- A joint effort and open sharing of risks
- Maximize opportunities and minimize threats
- Closely tied to form of payment 80/20
- Smart solutions benefit both parties
Collaborative business relationship
56
Building information modeling (BIM)
- All digital deliveries
- Visualize:
- collision control
- track economy
- execution of construction work
- production planning
- planning for safe working enviroment
- Contractor supplies digital workspace
- Workspace and deliveries for all parties