LRV Wireless Communication Upgrade Project Capital Committee, Sept. 13, 2018 Current State (Kinkisharyo Wi-Fi and Maintenance Workstation) Back Office Link Operations and Maintenance Facility Operations Performance Reporting Private KI
Current State (Kinkisharyo Wi-Fi and Maintenance Workstation)
- Current Kinkisharyo private yard Wi-Fi transmits vehicle data and passenger counts to Kinkisharyo Maintenance
Workstation.
- Workstation transmits data to Agency for maintenance monitoring and performance reporting.
Link Operations and Maintenance Facility Back Office
Private KI Yard Wi-Fi Agency Network Operations Performance Reporting KI MWS KI LRVs
Milestone: Onboard LRVs
- Run Kinkisharyo and Siemens systems parallel while configuring Siemens LRVs to connect to Enhanced Yard Wi-Fi.
Vehicle Systems Network KI MWS
Back Office
Siemens MDS Siemens APC Siemens PIS Siemens CCTV
Agency Network Operations Performance Reporting Siemens LRVs Enhanced Yard Wi-Fi
Link Operations and Maintenance Facility
KI LRVs
Target State Back Office
Verizon Backbone Network
Siemens MDS Siemens APC Siemens PIS Siemens CCTV
Enhanced Yard Wi-Fi Vehicle Systems Network Agency Network Operations Performance Reporting Siemens LRVs Upgraded KI MWS KI LRVs
Link Operations and Maintenance Facility
- Kinkisharyo and Siemens LRVs are on same Wi-Fi and Vehicle Systems Network.
LRV Wireless Communication Upgrade: Authorized Project Allocation $156K
ALLOCATION $ COMMITMENTS
$156 K Construction
Approved Today’s Action Future Action
Illustrative - Not to Scale
LRV Wireless Communication Upgrade: Increase Authorized Project Allocation $248K
ALLOCATION $ COMMITMENTS
Construction
Approved Today’s Action Future Action
Illustrative - Not to Scale