LRV Wireless Communication Upgrade Project Capital Committee, Sept. 13, 2018 Current State (Kinkisharyo Wi-Fi and Maintenance Workstation) Back Office Link Operations and Maintenance Facility Operations Performance Reporting Private KI


slide-1
SLIDE 1

Capital Committee, Sept. 13, 2018

LRV Wireless Communication Upgrade Project

slide-2
SLIDE 2

Current State (Kinkisharyo Wi-Fi and Maintenance Workstation)

  • Current Kinkisharyo private yard Wi-Fi transmits vehicle data and passenger counts to Kinkisharyo Maintenance

Workstation.

  • Workstation transmits data to Agency for maintenance monitoring and performance reporting.

Link Operations and Maintenance Facility Back Office

Private KI Yard Wi-Fi Agency Network Operations Performance Reporting KI MWS KI LRVs

slide-3
SLIDE 3

Milestone: Onboard LRVs

  • Run Kinkisharyo and Siemens systems parallel while configuring Siemens LRVs to connect to Enhanced Yard Wi-Fi.

Vehicle Systems Network KI MWS

Back Office

Siemens MDS Siemens APC Siemens PIS Siemens CCTV

Agency Network Operations Performance Reporting Siemens LRVs Enhanced Yard Wi-Fi

Link Operations and Maintenance Facility

KI LRVs

slide-4
SLIDE 4

Target State Back Office

Verizon Backbone Network

Siemens MDS Siemens APC Siemens PIS Siemens CCTV

Enhanced Yard Wi-Fi Vehicle Systems Network Agency Network Operations Performance Reporting Siemens LRVs Upgraded KI MWS KI LRVs

Link Operations and Maintenance Facility

  • Kinkisharyo and Siemens LRVs are on same Wi-Fi and Vehicle Systems Network.
slide-5
SLIDE 5

LRV Wireless Communication Upgrade: Authorized Project Allocation $156K

ALLOCATION $ COMMITMENTS

$156 K Construction

Approved Today’s Action Future Action

Illustrative - Not to Scale

slide-6
SLIDE 6

LRV Wireless Communication Upgrade: Increase Authorized Project Allocation $248K

ALLOCATION $ COMMITMENTS

Construction

Approved Today’s Action Future Action

Illustrative - Not to Scale

Construction $404 K