  2. Project Extent CROTONA PARK NORTH Freeman St BRONX RIVER Freeman St Station # 2 and 5 2

  3. Crash Data 2005-2010 Background Freeman St: Southern Bvld – Bristow St. Louis Nine Blvd: Crotona Park E – Freeman St • Pedestrian injuries: 16 • Bicyclist injuries: 2 • Motor vehicle occupant injuries: 60 CB 3 and WHEDCO requested improvements to the corridor 3

  4. Southern Blvd at Freeman St Existing Conditions Intersection under elevated train View South Passengers wait in the NORTH street for bus Narrow sidewalk at Freeman St Station foot of stairs to 2/5 Freeman St subway

  5. Southern Blvd at Freeman St Proposal New sidewalk protects people waiting for the bus NORTH ADA accessible Shortens crosswalk

  6. Southern Blvd at Louis Nine Blvd Existing Conditions Pedestrians vulnerable to fast turning vehicles at wide intersection 130 feet View South Long skewed crossing NORTH 6

  7. Southern Blvd at Louis Nine Blvd Proposal NORTH Angled parking maintained Shorter 2-part crossing 40 feet 36 feet

  8. Louis Nine Blvd and Intervale Ave Existing Conditions Louis Nine Blvd 70 feet NORTH Pedestrians vulnerable to free-right-turning vehicles Wide multi-legged intersection 8

  9. Louis Nine Blvd and Intervale Ave Proposal Separates right-turn onto Intervale Ave from thru movement to Louis Nine Blvd Safer 2-part crossing, slows vehicle turns Grocery Expand existing Greenstreet NORTH

  10. Triangle Corridors Existing Conditions NEW BUILDING 60 foot wide roadbed NEW BUILDING Low traffic volumes Freeman St 10 NEW NORTH BUILDING

  11. Triangle Corridors Daytime Proposal Loading zone Grocery deliveries require parallel parking Angled Parking Added NORTH Maintain angled parking where possible

  12. Other Project Corridors Percentage of vehicles speeding Existing Conditions 32% Wide corridor + Low traffic volumes = High speeds 52% NORTH Southern Blvd Two lanes in each direction 12

  13. Other Project Corridors Proposal 13

  14. Example of Typical Corridor Treatment 14 Laconia Ave, BRONX

  15. Freeman Street at Bristow Street Proposal Painted Neckdown Example NORTH “Painted” neckdown shortens crosswalks

  16. Plan Summary Improvements for Louis Nine/Intervale/Freeman: 1. Reduce travel lanes from four to three lanes, one in each direction with left-turn lanes as needed 2. Construct green pedestrian islands at Louis Nine Boulevard and Southern Boulevard 3. Extend pedestrian area and increase green space at Louis Nine Boulevard and Intervale Avenue 4. Extend curb at Southern Boulevard and Freeman Street 5. Add painted neckdown at Bristow Street and Freeman Street and at Wilkins Ave and Crotona Park East 6. Refurbish all crosswalk markings on corridors 16

  17. Thank www.nyc.gov/dot You 17 17

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.