long quadrupole program
play

Long Quadrupole Program Giorgio Ambrosio DOE Review of the LARP - PowerPoint PPT Presentation

BNL - FNAL - LBNL - SLAC Long Quadrupole Program Giorgio Ambrosio DOE Review of the LARP Program SLAC July 9-10, 2011 LQ Task Leaders: Fred Nobrega (FNAL) Coil fabrication Jesse Schmalzle (BNL) Coil fabrication Helene Felice (LBNL)


  1. BNL - FNAL - LBNL - SLAC Long Quadrupole Program Giorgio Ambrosio DOE Review of the LARP Program SLAC July 9-10, 2011 LQ Task Leaders: Fred Nobrega (FNAL) – Coil fabrication Jesse Schmalzle (BNL) – Coil fabrication Helene Felice (LBNL) – Structure Maxim Marchevsky (LBNL) – Instrumentation and QP Guram Chlachidize (FNAL) – Test preparation and test Long Quadrupole – G. Ambrosio 1 LARP DOE Review, 7/9/2012

  2. Outline • Main features • Practice coils — Lessons learned • LQS01a — Results — Lessons learned • LQS01b — Results — Lessons learned • LQS02 — Results — Lessons learned • LQS03 — Plans • Budget and conclusions Long Quadrupole – G. Ambrosio 2 LARP DOE Review, 7/9/2012

  3. LARP Magnet Development Chart 2004-06 2005-10 2008-13 2011-15 Long Quadrupole – G. Ambrosio 3 LARP DOE Review, 7/9/2012

  4. Long Quadrupole † Main Features: • Aperture: 90 mm • magnet length: 3.7 m Target: • Gradient: 200 T/m Goal: • Demonstrate Nb 3 Sn magnet scale up: — Long shell-type coils LQS01 S.S.L. 4.5 K — Long shell-based structure (bladder & keys) Current 13.7 kA Deadline: by the end of 2009 Gradient 240 T/m — Reproducibility, training memory, and Peak Field 12.25 T performance at 1.9K Stored Energy 460 kJ/m † LQ Design Report available online at: https://plone4.fnal.gov/P1/USLARP/MagnetRD/longquad/LQ_DR.pdf Long Quadrupole – G. Ambrosio 4 LARP DOE Review, 7/9/2012

  5. LQ Features • LQS is based on TQS (1m model) with modifications for long magnets • Aluminum shell Structure Modifications: – Added tie-rods for yoke & pad laminations – Added masters – Added alignment features for the structure – Rods closer to coils – Rods made of SS Cross-section of TQ/LQ coil • Coil modifications: – LQ coils = TQ coils with gaps to accommodate different CTE during HT – From 2-in-1 (TQ coils) to single coil fixtures (LQ) – Bridge between lead-end saddle and pole – Mica during heat treatment Long Quadrupole – G. Ambrosio 5 LARP DOE Review, 7/9/2012

  6. Practice Coil – Lessons Learned • Several issues found during Practice Coils fabr. — bowing, longitudinal tension in coil, damage to leads, incomplete impregnation, damage to insulations • All issues and causes have been addressed:  More QC, more detailed travelers  Discrepancy reporting  Fewer discrepancies going forward in production  More robust fabrication technology Long Quadrupole – G. Ambrosio 6 LARP DOE Review, 7/9/2012

  7. LQS01a Quench History • Slow start — First quenches at high SSL at 4.5K : 240 T/m ramp rate (200 A/s) Target: 200 T/m — Slow training at 4.5K • Due to low pre-load on pole turns • Faster training at 3K — Reached 200 T/m 200 A/s • Stopped training — to avoid coil damage and to achieve better performance with optimal pre-stress Test report available online at: https://plone4.fnal.gov/P1/USLARP/MagnetRD/longquad/report/TD-10-001_LQS01_test_summary.pdf Long Quadrupole – G. Ambrosio 7 LARP DOE Review, 7/9/2012

  8. LQS01a - Lessons Learned • Coil oversize not accounted for in structure assembly, caused non optimal prestress  CMM measurements of all coils  Adjustment of coil-structure shims for optimal preload  Procedures for checking at warm proper coils-structure matching LQS01a LQS01b Nominal Oversized Long Quadrupole – G. Ambrosio 8 LARP DOE Review, 7/9/2012

  9. LQS01b Quench History SSL at 4.5K : 240 T/m 227 Target: 200 T/m At 4.5 K: reproducible quenches in coil #8  G = 222 T/m; Iq/Ic = 92 ssl At 1.9 K: variable quench curr. in coil #9  limited stability of conductor Long Quadrupole – G. Ambrosio 9 LARP DOE Review, 7/9/2012

  10. LQS01b Quench History 2 nd Therm. cycle 1 st quench: G = 208 T/m 2 nd quench G = 222T/m with controlled cooldown DT < 100 K Long Quadrupole – G. Ambrosio 10 LARP DOE Review, 7/9/2012

  11. LQS01b Magnetic Measurement LQ does not have alignment features. They are in HQ (1m) and will be in LHQ (~4m).  Field quality of long Nb 3 Sn magnets will be demonstrated by LHQ † G. Velev , et al., “Field Quality Measurements and Analysis of Average harmonics in the TQS and LQS at 45 T/m the LARP Technology Quadrupole Models”, IEEE Trans. On (~ 2.6 kA) at the ref. radius r 0 of 22.5 mm Long Quadrupole – G. Ambrosio 11 LARP DOE Review, 7/9/2012 Applied Supercond. , vol.18, no.2, pp.184-187, June 2008

  12. LQS01b - Lessons Learned • LQS01b reached the best performance of all TQS02 series (1m models with same conductor)! • Demonstrated good training memory  We know how to make long Nb 3 Sn coils without degradation  Segmented shell structure can be used for long Nb 3 Sn magnets with shell-type coils  We have tools (computation & instrumentation) for protecting long Nb 3 Sn magnets Long Quadrupole – G. Ambrosio 12 LARP DOE Review, 7/9/2012

  13. LQS01b To Be Improved • Some “bubbles” on coils • Big voltage spikes at low inner layer current (flux jumps) — Coil-insulation separation • No expected Gradient • Plans: increase at 1.9 K — Strengthen insulation (coil 13)  Smaller filament diam. in — Change/remove inner layer LQS03 coils 54/61  108/127 heaters Long Quadrupole – G. Ambrosio 13 LARP DOE Review, 7/9/2012 Maximum Voltage Spike amplitude at 4.5 K with 50 A/s ramp rate

  14. LQS02 Quench History Limited performance “Reverse ramp-rate dependence” Long Quadrupole – G. Ambrosio 14 LARP DOE Review, 7/9/2012

  15. LQS02 Analysis • Holding quenches, Voltage Tap data, Quench Antenna data, and Spike Recording System data confirmed: • The cause is “ Enhanced Instability ” in one coil — An unknown “issue” causes a decrease of the stability threshold of the conductor in coil 13 OL. — Possible “issues” are: (i) a local damage or a non-uniform splice forcing more current in a few strands; (ii) a damage of some strands decreasing the local RRR and/or causing filaments merging. Long Quadrupole – G. Ambrosio 15 LARP DOE Review, 7/9/2012

  16. LQS02 - Lessons Learned • There are “issues” that we cannot detect during fabrication or assembly, which may limit magnet performance • These “issues” decrease the instability threshold of the conductor  We need to understand the cause of these “issues”  We have demonstrated that over- compression is one, …  We need more stability margin  LQS03 coils have 108/127 RRP with higher stability margin than 54/61  We need to understand coils yield  So far in LQ we tested 7 good coils out of 8  We need to plan for possible reassembly during production Long Quadrupole – G. Ambrosio 16 LARP DOE Review, 7/9/2012

  17. LQS03 • Four new coils with RRP 108/127 • Same target prestress of LQS01b • Slightly improved coil-structure matching wrt to LQS02  Ready for test  Cooldown starts in two weeks • GOALS: — exceed 200 T/m at 4.5 K — exceed 220 T/m at 1.9 K — demonstrate training memory after unrestricted cooldown Long Quadrupole – G. Ambrosio 17 LARP DOE Review, 7/9/2012

  18. Post LQS03 LQS03 meets goals yes no LQ is done! Analysis of cause LQS03b addressing issue Long Quadrupole – G. Ambrosio 18 LARP DOE Review, 7/9/2012

  19. LQ Budget • LQ actual budget profile (in $K) — conductor cost/coil put 2 yrs. in advance of coil fabrication Coils # 5 5 2 5 17 FY06 FY07 FY08 FY09 FY10 FY11 FY12 TOTAL LQ conductor 435 435 174 435 1479 3789 3149 1926 1824 508 LQ all but cond. 130 610 12347 565 1045 3963 3584 1926 1824 508 13826 Long Quadrupole – G. Ambrosio 19 LARP DOE Review, 7/9/2012

  20. Conclusions • The Long Quadrupole is demonstrating Nb 3 Sn scale- up to ~4 m — Target gradient with LQS01a; — Matched the best performance of all short models with LQS01b — Demonstrated good memory with LQS01b 2 nd thermal cycle • We have learned a lot, also by addressing unexpected issues — LQS03 should demonstrate that we are back on track • There some open questions that will be addressed by the rest of the program — LHQ will demonstrate good field quality in long Nb 3 Sn magnets Long Quadrupole – G. Ambrosio 20 LARP DOE Review, 7/9/2012

  21. Backup Slides Long Quadrupole – G. Ambrosio 21 LARP DOE Review, 7/9/2012

  22. LQ Fabrication Process • Cable: — Cabling: LBNL — Qualification tests: BNL, FNAL, LBNL • Coils: — Wind & curing: FNAL — Reaction & impregnation, BNL, FNAL — Instrumentation: BNL, FNAL, LBNL • Structure: — Pre-assembly & magnet assembly: LBNL • Test: — Warm and cold test: FNAL Long Quadrupole – G. Ambrosio 22 LARP DOE Review, 7/9/2012

  23. LQS01b (same coils of LQS01a) • More uniform prestress distribution in the coils By using thinner coil-pad shims • Higher preload based on 1m models (TQS03 a/b/c)  Peak load: 190 MPa +/- 30  No coil-pole separation in LQS01b Long Quadrupole – G. Ambrosio 23 LARP DOE Review, 7/9/2012

  24. LQS01b: 220 T/m Gradient at 4.4K of LQ & all 1m models with RRP 54/61 in 4 quenches LQS01b: 222 T/m 92% ssl based on strand test (95% ssl based on cable test) Long Quadrupole – G. Ambrosio 24 LARP DOE Review, 7/9/2012

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend