SLIDE 1
Project Area
2
Lee Hwy & Glebe Road Intersection Improvements Jon Lawler, P.E. - - PowerPoint PPT Presentation
Lee Hwy & Glebe Road Intersection Improvements Jon Lawler, P.E. October 30, 2019 Project Manager Project Area Project Area 2 Existing Conditions VDOT Streets 30-35 mph speed limits Inefficient signal phasing Heavy peak
2
3
4
5
6
7
8
9
10
11
12
13
14
15
Anticipated construction completion in 2022
16
Utility Undergrounding Began in January 2017 and is ongoing Final Design Complete January Advertisement September 5 Bid Opening November 4 Board Approval of Contract December 14 Construction Start Spring
18