lee hwy glebe road intersection improvements
play

Lee Hwy & Glebe Road Intersection Improvements Jon Lawler, P.E. - PowerPoint PPT Presentation

Lee Hwy & Glebe Road Intersection Improvements Jon Lawler, P.E. October 30, 2019 Project Manager Project Area Project Area 2 Existing Conditions VDOT Streets 30-35 mph speed limits Inefficient signal phasing Heavy peak


  1. Lee Hwy & Glebe Road Intersection Improvements Jon Lawler, P.E. October 30, 2019 Project Manager

  2. Project Area Project Area 2

  3. Existing Conditions • VDOT Streets • 30-35 mph speed limits • Inefficient signal phasing • Heavy peak hour traffic • Overhead utilities • Mediocre pedestrian experience • Poor streetlighting • Minimal trees & landscaping • Land uses: Commercial and retail 3

  4. Existing Traffic Volumes 2018 Traffic Volumes 2015 Traffic Volumes AM Peak Hour Total: 3,152 AM Peak Hour Total: 3,346 PM Peak Hour Total: 3,146 PM Peak Hour Total: 3,412 7% Reduction 4

  5. Project Goals • Re-design as Complete Streets • Improve multi-modal access • Reduce multi-modal travel times • Enhance bus stops • Improve streetlighting • Add landscaping where possible • Underground utilities • Upgrade watermains 5

  6. Typical Glebe Rd Cross ‐ Section 6

  7. Glebe Rd – South of Lee Hwy 7

  8. Glebe Rd – South of Lee Hwy 8

  9. Typical Glebe Rd Cross ‐ Section 9

  10. Glebe Rd – North of Lee Hwy 10

  11. Glebe Rd – North of Lee Hwy 11

  12. Typical Lee Hwy Cross ‐ Section 12

  13. Lee Hwy 13

  14. Lee Hwy 14

  15. Streetlighting • Dominion Energy maintained cobra lights – 17 in total • Reduction from 24 dual carlyles lights • 4 County cobra lights on signal poles • County adopted 2019 Streetlight Management Plan 15

  16. Key Milestones / Next Steps SCHEDULE 2017 2018 2019 2020 Utility Undergrounding Began in January 2017 and is ongoing Final Design Complete January Advertisement We are HERE September 5 Bid Opening November 4 Board Approval of Contract December 14 Construction Start Spring Anticipated construction completion in 2022 16

  17. Utility Undergrounding Next Steps • Service reconnections • Dominion wreckout after reconnections • Comcast completed all work in August 2019 • Verizon splicing complete in Oct 2019 • Verizon wreckout complete in Nov 2019 • Streetscape construction – 2 years • Final streetlight install • Remove remaining poles

  18. Questions https://projects.arlingtonva.us/projects/l ee-highway-glebe-road-intersection- improvements/ Jon Lawler, P.E. Project Manager (703) 228-3724 18

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend