Kirkliston Environmental Improvements August 2011 Project Team - - PowerPoint PPT Presentation

kirkliston environmental improvements
SMART_READER_LITE
LIVE PREVIEW

Kirkliston Environmental Improvements August 2011 Project Team - - PowerPoint PPT Presentation

Kirkliston Environmental Improvements August 2011 Project Team Helen Platts CEC Regeneration Project Manager Liz Dominy Landscape Architect Ironside Farrar Ltd Darren Wraight CEC Local Roads Officer Premier 1 Land Services


slide-1
SLIDE 1

Kirkliston Environmental Improvements

August 2011

slide-2
SLIDE 2

Project Team

Helen Platts – CEC Regeneration Project Manager Liz Dominy – Landscape Architect Ironside Farrar Ltd Darren Wraight – CEC Local Roads Officer Premier 1 Land Services – Contractor

slide-3
SLIDE 3

Background

In February 2007 the City of Edinburgh Council commissioned Ironside Farrar Ltd to develop feasibility stage proposals for public realm improvement works for Kirkliston to improve the streetscape within the town centre and provide key linkages to the surrounding developments. A range of elements were analysed to develop the draft proposals such as: Context within the local plan and proposed developments Existing streetscape conditions Pedestrian safety and circulation A series of consultation exercises were undertaken and a series of proposals were drawn up. Kirkliston Environmental Improvements

slide-4
SLIDE 4

Kirkliston Environmental Improvements

Draft proposals 2007

East West

These proposals were used as a basis for the March 2009 Planning Agreement upon which a £280,000 contribution is to be made by the Developer for the provision of Key Arrival Points to the East and West of Kirkliston. The contribution is available from the 1st anniversary of the Commencement of Development which is the 31st August 2011.

slide-5
SLIDE 5

Kirkliston Environmental Improvements February 2011

  • HP appointed as project manager to progress project
  • Background Research / Information gathering undertaken

March/April 2011

  • Consultant (Ironside Farrar) re-engaged to develop final stage proposals
  • West Neighbourhood Team engaged and project team determined

May – June 2011

  • Term contractor (Premier 1 Land Services) commissioned to undertake works
  • Site visits undertaken, utility information gathered, designs developed

June – August 2011

  • Local community engaged
  • Development consortium contacted re: proposals
  • Other involved parties contacted re: proposals i.e., street lighting, road safety, signals
  • Working towards finalised design

Progress since March 2009

slide-6
SLIDE 6

Kirkliston Environmental Improvements

Final Design Development

slide-7
SLIDE 7

Kirkliston Environmental Improvements

Key points of focus

  • Promotion of Kirkliston Town Centre / Town identity
  • Creation of Key Arrival Points to the East and West
  • Improvement of streetscape at the key arrival points
  • Improvement of pedestrian safety, access and movement in these areas
  • Introduction of high quality materials and ‘personalised palette’ without high

maintenance need

  • Maintenance and upgrade of street furniture
slide-8
SLIDE 8

Kirkliston Environmental Improvements

slide-9
SLIDE 9

Kirkliston Environmental Improvements

slide-10
SLIDE 10

Kirkliston Environmental Improvements

slide-11
SLIDE 11

Kirkliston Environmental Improvements September – December 2011

  • Meetings with involved parties to agree plans and ensure joint working where possible
  • Detailed final plans and costings completed
  • Discussions with CEC Planning / Land owners re: design implications
  • Programme of works developed and agreed with contractor
  • Final proposals published and disseminated to local community

January – March 2012

  • Works on site

April – October 2012

  • Maintenance period

Next Steps

slide-12
SLIDE 12

Any questions?

Kirkliston Environmental Improvements