kingston city school district khs second century capital
play

Kingston City School District KHS Second Century Capital Plan 2013 - PowerPoint PPT Presentation

Kingston City School District KHS Second Century Capital Plan 2013 Bond Follow Up Design Initiatives 6 Dec. 2012 Monthly Update 2013 Bond Follow Up Design Initiatives 6 Dec. 2012 Board Meeting December 13, 2017 K H S S e c


  1. Kingston City School District KHS Second Century Capital Plan 2013 Bond – Follow Up Design Initiatives 6 Dec. 2012 Monthly Update 2013 Bond – Follow Up Design Initiatives 6 Dec. 2012 Board Meeting – December 13, 2017 K H S S e c o n d C e n t u r y C a p i t a l P l a n 1

  2. Pre-Construction /Design Progress Updates KHS Main Renovations Package – Second Phase: • KSQ and their consultants have finalized the contract documents and program needs for the secondary phase of work on the Main Building Package. 2013 Bond – Follow Up Design Initiatives 6 Dec. 2012 • KSQ has submitted these documents to the NYSED. • The NYSED project review time frame is currently projecting to take approximately 8 to 9 months. • These documents will continue to be reviewed by the project team while under NYSED 2013 Bond – Follow Up Design Initiatives 6 Dec. 2012 review. • Secondary phase of work will commence upon regeneration of funds as mandated by the. • Bid NYSED dates to be established upon NYSED project approval and regeneration of funds. On-Going Project Team Pre-Construction/Design Tasks: • Continuous updating of project costs for current / future work packages along with FFE costs. • Contacting perspective trade specific contractor to ensure contractor awareness and participation for upcoming bid packages. • Continue to monitor the bidding climate and reacting accordingly. • Tracking and updating District phasing requirements and needs. K H S S e c o n d C e n t u r y C a p i t a l P l a n 2

  3. KHS HS Ma Main Re Renovati tions Pa Pack ckage – Seco cond Ph Phase: : • KSQ and their consultants have finalized the contract documents and program needs for the secondary phase of work on the Main Building Package. Construction Progress Updates • Contractors are utilizing the Christmas Break (12/25/17 through 1/1/18) to complete work throughout the High School campus. • General Contractor continuing to work on deficient items at the Field House. 2013 Bond – Follow Up Design Initiatives 6 Dec. 2012 • Contractors working on the Main Mechanical punchlist. • Cafeteria work is finishing in preparation of December 22, 2017 turnover to KCSD. • Final inspections for the elevator and fire alarms 2013 Bond – Follow Up Design Initiatives 6 Dec. 2012 • Kitchen equipment installation is complete – Consultant completing final review of installation on December 18 th . • Cafeteria tile work is nearing completion. • Casework installation ongoing • Furniture delivery on December 18 th . • Department of Heath final inspection December 22 nd . • Salzmann South Addition work is ongoing with installation of concrete, steel and rebar. • Cleanup of MJM demolition continues. • Renovations are taking place in the balance of the unoccupied Salzmann areas. K H S S e c o n d C e n t u r y C a p i t a l P l a n 3

  4. 2013 Bond – Follow Up Design Initiatives 6 Dec. 2012 2013 Bond – Follow Up Design Initiatives 6 Dec. 2012 Storage inside the Cooler and Freezer New Ice Maker and Tray Warmer K H S S e c o n d C e n t u r y C a p i t a l P l a n 4

  5. 2013 Bond – Follow Up Design Initiatives 6 Dec. 2012 2013 Bond – Follow Up Design Initiatives 6 Dec. 2012 New Food Service Serving Counter New Food Service Area K H S S e c o n d C e n t u r y C a p i t a l P l a n 5

  6. 2013 Bond – Follow Up Design Initiatives 6 Dec. 2012 2013 Bond – Follow Up Design Initiatives 6 Dec. 2012 Ware Washer Equipment Installation K H S S e c o n d C e n t u r y C a p i t a l P l a n 6

  7. 2013 Bond – Follow Up Design Initiatives 6 Dec. 2012 2013 Bond – Follow Up Design Initiatives 6 Dec. 2012 New Char-broiler, Griddle and Range Oven K H S S e c o n d C e n t u r y C a p i t a l P l a n 7

  8. 2013 Bond – Follow Up Design Initiatives 6 Dec. 2012 2013 Bond – Follow Up Design Initiatives 6 Dec. 2012 Cafeteria Floor and Wall Tile Installation K H S S e c o n d C e n t u r y C a p i t a l P l a n 8

  9. 2013 Bond – Follow Up Design Initiatives 6 Dec. 2012 2013 Bond – Follow Up Design Initiatives 6 Dec. 2012 Ongoing Cafeteria Tile Installation and Completed Feature Wall K H S S e c o n d C e n t u r y C a p i t a l P l a n 9

  10. 2013 Bond – Follow Up Design Initiatives 6 Dec. 2012 2013 Bond – Follow Up Design Initiatives 6 Dec. 2012 New Food Service Serving Counter K H S S e c o n d C e n t u r y C a p i t a l P l a n 10

  11. 2013 Bond – Follow Up Design Initiatives 6 Dec. 2012 2013 Bond – Follow Up Design Initiatives 6 Dec. 2012 Excavation and Prep for Salmann South Addition K H S S e c o n d C e n t u r y C a p i t a l P l a n 11

  12. 2013 Bond – Follow Up Design Initiatives 6 Dec. 2012 2013 Bond – Follow Up Design Initiatives 6 Dec. 2012 MJM Ongoing Cleanup and Rock Hammering for South Addition K H S S e c o n d C e n t u r y C a p i t a l P l a n 12

  13. 2013 Bond – Follow Up Design Initiatives 6 Dec. 2012 2013 Bond – Follow Up Design Initiatives 6 Dec. 2012 MJM Ongoing Cleanup and Oil Tank Removal K H S S e c o n d C e n t u r y C a p i t a l P l a n 13

  14. 2013 Bond – Follow Up Design Initiatives 6 Dec. 2012 2013 Bond – Follow Up Design Initiatives 6 Dec. 2012 Ongoing MJM Cleanup K H S S e c o n d C e n t u r y C a p i t a l P l a n 14

  15. 2013 Bond – Follow Up Design Initiatives 6 Dec. 2012 2013 Bond – Follow Up Design Initiatives 6 Dec. 2012 Thank You! K H S S e c o n d C e n t u r y C a p i t a l P l a n 15

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend