Joint Wastewater Master Plan

Stage 1 – Background and Data Assessment

Joint Shared Services Committee September 14, 2017

slide-2
SLIDE 2

2

Presentation Overview

Purpose Progress System

  • verview

Issues and Opportunities Next steps

slide-3
SLIDE 3

3

Purpose

Regulations, Technology, and best practices

Review JAMES Plant infrastructure suitability for Abbotsford, Mission and Industry in the next 25 years

Plant

  • dours

Resource Recovery Biosolids

  • ptions

Develop a capital growth program for next 25 years

slide-4
SLIDE 4

4

OCP Alignment

OCP Master Plan Financial Plans DCC

slide-5
SLIDE 5

5

Progress

Master Plan Stage 1 Stage 2 Stage 3 Stage 4

BACKGROUND REVIEW AND DATA ASSESSMENT ANALYSIS AND EVALUATION

June 2018 Fall/Winter 2017 Spring 2018 April 2017

slide-6
SLIDE 6

6

System Overview

slide-7
SLIDE 7

7

System Overview

  • JAMES Plant treats sewage from

Abbotsford, Mission, and Sumas Washington

  • Secondary treatment
  • Discharge to Fraser River
  • Serves 240,000 population

equivalent

slide-8
SLIDE 8

8

Service Area

DISTRICT OF MISSION CITY OF ABBOTSFORD

slide-9
SLIDE 9

9

Abby Flow Mission Flow

JAMES WWTP (Flow)

Influent Primary Treatment Secondary Treatment Disinfection

Schematic

Fraser River

N

slide-10
SLIDE 10

10

Treatment Process

Solids Treatment

  • Pasteurization
  • Anaerobic Digestion

Dewatering Land Application Inflow to Plant

  • Abbotsford
  • Mission
  • Sumas, WA

Preliminary Treatment (Headworks Screening) Primary Treatment Secondary Treatment (Biological) Disinfection

Fraser River

Solids Source control to prevent upsets

Centrate Treatment

slide-11
SLIDE 11

11

Inflow Components

Inflow to Plant

  • Abbotsford
  • Mission
  • Sumas, WA

Residential, Commercial, Institutional Industrial Dry Industries Wet Processors (Extra Strength)

High load

slide-12
SLIDE 12

12

Source Control

To protect the sewage collection system, the treatment facilities, the biosolids quality, the receiving environment, and the health and safety of the public and sewer workers

  • Importance of pH
  • Industrial monitoring
  • Strength/pH
slide-13
SLIDE 13

13

Upgrades Trigger (Typical)

Solids Treatment

  • Pasteurization
  • Anaerobic Digestion

Dewatering Land Application Inflow to Plant

  • Abbotsford
  • Mission
  • Sumas, WA

Preliminary Treatment (Headworks Screening) Primary Treatment Secondary Treatment (Biological) Disinfection

Fraser River

Solids

Flow Flow Flow Load Flow Load Load

Centrate Treatment

slide-14
SLIDE 14

14

Issues and Opportunities

Extra Strength (High Load) Industries Projection Seismic Capacity Odour Biosolids Biogas

slide-15
SLIDE 15

15

BOD Load

Milk processor Total Plant BOD Load (kg/yr)

Extra Strength BOD Load (kg/yr)

Approximately 25 Extra Strength (high load) users Six of them are contributing to the higher load (80-85% of total)

Extra Strength BOD Load (kg/yr)

slide-16
SLIDE 16

Extra Strength Industrial Load

Extra Strength (High Load) Industrial BOD growth could drive need for earlier plant expansion. Options

  • Impose Pre-treatment for new industries to certain limits
  • Impose limits for existing industries (phased in)

Such measures may impact industry investment in community.

Scenarios BOD (kg/d) Eq Pop 1 2016 Level 7,400 106,000 2 1.7% growth per year 11,000 158,000

slide-17
SLIDE 17

17

Guiding Principles

JAMES Plant meets Provincial and Federal regulations Regulations Provincial

Municipal Wastewater Regulations (MWR) Organic Matters Recycling Regulation (OMRR)

Federal

Federal Wastewater Systems Effluent Regulation (WSER)

Wastewater

(Secondary Treatment)

Biosolids

(Class A)

Redundancy (Reliability)

slide-18
SLIDE 18

18

Assumptions

Abbotsford Residential & ICI Growth @1.6% annually

Mission Residential and ICI Growth @ 2% Sumas, WA growth at 2.8% (per agreement) Extra Strength (High load) Industries Climate Change Phosphorus effluent limit not applicable

slide-19
SLIDE 19

19 Abbotsford Farmers Market Mission Farmers Market Canada Day

Public Events Website Presence

  • UMC (April 26)
  • JSSC (May 18)
  • Abbotsford Council Workshop (May 25)
  • Mission Council Workshop (July 10)
  • Stage 1:
  • UMC (August 30)
  • JSSC (September 14)

Council

Engagement

slide-20
SLIDE 20

20

Next Steps

Stage 1 Stage 2 Stage 3 Stage 4

BACKGROUND REVIEW AND DATA ASSESSMENT ANALYSIS AND EVALUATION

June 2018 Fall/Winter 2017 Spring 2018

Master Plan

April 2017

slide-21
SLIDE 21

21