Joint Wastewater Master Plan Stage 1 Background and Data - - PowerPoint PPT Presentation
Joint Wastewater Master Plan Stage 1 Background and Data - - PowerPoint PPT Presentation
Joint Wastewater Master Plan Stage 1 Background and Data Assessment Joint Shared Services Committee September 14, 2017 Presentation Overview System Issues and Purpose Progress Next steps overview Opportunities 2 Purpose
2
Presentation Overview
Purpose Progress System
- verview
Issues and Opportunities Next steps
3
Purpose
Regulations, Technology, and best practices
Review JAMES Plant infrastructure suitability for Abbotsford, Mission and Industry in the next 25 years
Plant
- dours
Resource Recovery Biosolids
- ptions
Develop a capital growth program for next 25 years
4
OCP Alignment
OCP Master Plan Financial Plans DCC
5
Progress
Master Plan Stage 1 Stage 2 Stage 3 Stage 4
BACKGROUND REVIEW AND DATA ASSESSMENT ANALYSIS AND EVALUATION
June 2018 Fall/Winter 2017 Spring 2018 April 2017
6
System Overview
7
System Overview
- JAMES Plant treats sewage from
Abbotsford, Mission, and Sumas Washington
- Secondary treatment
- Discharge to Fraser River
- Serves 240,000 population
equivalent
8
Service Area
DISTRICT OF MISSION CITY OF ABBOTSFORD
9
Abby Flow Mission Flow
JAMES WWTP (Flow)
Influent Primary Treatment Secondary Treatment Disinfection
Schematic
Fraser River
N
10
Treatment Process
Solids Treatment
- Pasteurization
- Anaerobic Digestion
Dewatering Land Application Inflow to Plant
- Abbotsford
- Mission
- Sumas, WA
Preliminary Treatment (Headworks Screening) Primary Treatment Secondary Treatment (Biological) Disinfection
Fraser River
Solids Source control to prevent upsets
Centrate Treatment
11
Inflow Components
Inflow to Plant
- Abbotsford
- Mission
- Sumas, WA
Residential, Commercial, Institutional Industrial Dry Industries Wet Processors (Extra Strength)
High load
12
Source Control
To protect the sewage collection system, the treatment facilities, the biosolids quality, the receiving environment, and the health and safety of the public and sewer workers
- Importance of pH
- Industrial monitoring
- Strength/pH
13
Upgrades Trigger (Typical)
Solids Treatment
- Pasteurization
- Anaerobic Digestion
Dewatering Land Application Inflow to Plant
- Abbotsford
- Mission
- Sumas, WA
Preliminary Treatment (Headworks Screening) Primary Treatment Secondary Treatment (Biological) Disinfection
Fraser River
Solids
Flow Flow Flow Load Flow Load Load
Centrate Treatment
14
Issues and Opportunities
Extra Strength (High Load) Industries Projection Seismic Capacity Odour Biosolids Biogas
15
BOD Load
Milk processor Total Plant BOD Load (kg/yr)
Extra Strength BOD Load (kg/yr)
Approximately 25 Extra Strength (high load) users Six of them are contributing to the higher load (80-85% of total)
Extra Strength BOD Load (kg/yr)
Extra Strength Industrial Load
Extra Strength (High Load) Industrial BOD growth could drive need for earlier plant expansion. Options
- Impose Pre-treatment for new industries to certain limits
- Impose limits for existing industries (phased in)
Such measures may impact industry investment in community.
Scenarios BOD (kg/d) Eq Pop 1 2016 Level 7,400 106,000 2 1.7% growth per year 11,000 158,000
17
Guiding Principles
JAMES Plant meets Provincial and Federal regulations Regulations Provincial
Municipal Wastewater Regulations (MWR) Organic Matters Recycling Regulation (OMRR)
Federal
Federal Wastewater Systems Effluent Regulation (WSER)
Wastewater
(Secondary Treatment)
Biosolids
(Class A)
Redundancy (Reliability)
18
Assumptions
Abbotsford Residential & ICI Growth @1.6% annually
Mission Residential and ICI Growth @ 2% Sumas, WA growth at 2.8% (per agreement) Extra Strength (High load) Industries Climate Change Phosphorus effluent limit not applicable
19 Abbotsford Farmers Market Mission Farmers Market Canada Day
Public Events Website Presence
- UMC (April 26)
- JSSC (May 18)
- Abbotsford Council Workshop (May 25)
- Mission Council Workshop (July 10)
- Stage 1:
- UMC (August 30)
- JSSC (September 14)
Council
Engagement
20
Next Steps
Stage 1 Stage 2 Stage 3 Stage 4
BACKGROUND REVIEW AND DATA ASSESSMENT ANALYSIS AND EVALUATION
June 2018 Fall/Winter 2017 Spring 2018
Master Plan
April 2017
21