Joint Rail and Road Project Ringerike Line and E16 Highway 19 - - PowerPoint PPT Presentation
Joint Rail and Road Project Ringerike Line and E16 Highway 19 - - PowerPoint PPT Presentation
Joint Rail and Road Project Ringerike Line and E16 Highway 19 April 2018 Ringerike Line and E16 Highway TK TK-08 08 TK TK-07 07 Ring ngeriksba sbane nen o n og E16 FELLESPROSJEKTET RINGERIKSBANEN OG E16 Ringerike Line and E16
Ring ngeriksba sbane nen o n og E16
FELLESPROSJEKTET RINGERIKSBANEN OG E16
Ringerike Line and E16 Highway
TK TK-07 07 TK TK-08 08
Ring ngeriksba sbane nen o n og E16
- 40 km new double track railway from Sandvika to Hønefoss prepared for a
maximum speed of 250 km/h:
- 15 km four lane highway, prepared for max speed 110 km/h
- Construction of a new railway station at Sundvollen
- Complete rebuild of existing railway station at Hønefoss
- Highway intersections at Elstangen, Styggedalen, Ve and possibly at
Helgelandsmoen
Ringerike Line and E16 Highway
Project summary – railway and highway
13.08.2018
Ring ngeriksba sbane nen o n og E16
- 23 km double track railway tunnel with parallel escape and service
tunnel from Sandvika to Sundvollen
- 3 km double track railway tunnel at Vik
- 770 m double track railway bridge across Kroksund
- 640 m 4-lane highway bridge across Kroksund
- 2 x 3 km 2-lane highway tunnels at Vik
- Bridge crossing of the river and wetlands at Mælingen:
- Alt 1: Two railway bridges (300 m + 900 m) plus three highway
bridges (1 x 300 m + 2 x 900 m) with an embankment in- between
- Alt 2: One railway bridge (1800 m) plus two highway bridges (2
x 1800 m)
Ringerike Line and E16 Highway
Project summary – tunnels and bridges
13.08.2018
Ring ngeriksba sbane nen o n og E16 Ringerike Line and E16 Highway
Preliminary Contract Structure
13.08.2018
TK-01 Jong TK-02 Solihøgda TK-05 Mælingen Jong - Ringi railway tunnel Rustan - Høgås railway tunnel Kroksund - Kjelleberget, highway and railroad tunnels and day zones Kjelleberget - Storelva, highway and railway day zones Hghway and railway bridges across Storelva and Mælingen
arb
RT Tracks, overhead contact line, HV/LV, telecom Signal TK-08 (EPC) TK-01 (EPC) TK-02 (EPC) TK-04 (EPC) TK-05 (EPC) TK-06 (EPC) TK-03 (EPC) TK-07 (EPC) Build substructure rail and road Preparatory / Enabling works Prestemoen - Styggedalen day zones, intersections at Ve and Styggedalen, Hønefoss railway station, tracks and railway technique Styggedalen- Hønefoss Several contracts (construction only) Bane NOR Sundvollen railway tunnel, Sunvollen railway station, Elstangen highway interection, highway and railway bridges across TK-03 Sundvollen TK-04 Vik TK-06 Hønefoss Ringerike Line and E16 Highway System design for railway technique (RT) Design substructure rail and road
Ring ngeriksba sbane nen o n og E16 TK-01, TK-02 and TK-03
Jong to Sundvollen
13.08.2018
Two t tunnel t tube bes; o
- ne do
double ble t tra rack t tunnel w l wit ith a a pa para ralle llel e l escape a and d serv rvic ice t tunnel
Ring ngeriksba sbane nen o n og E16
13.08.2018
Civ ivil w il work rks f for r the ra railw ilway lin line:
- 2 x 2,5 km single track tunnels and 3
km double track tunnel
- 5,5 km parallel escape and service
tunnel
- Connection to existing tunnel at Jong
- Estimated total muck production:
1.200.000 sm3
- Rig areas with access tunnels at Jong,
Reverud and Kattås
TK-01
Jong
Ring ngeriksba sbane nen o n og E16 TK-02
Sollihøgda
13.08.2018
Ring ngeriksba sbane nen o n og E16
13.08.2018
Civ ivil w il work rks f for r the ra railw ilway lin line:
- 13,5km double track tunnel
- 13,5 km parallel escape and service tunnel
- Estimated total muck production: 2.950.000 sm3
- Rig areas with access tunnels Rustan, Avtjerna and Høgås
- Firefighting point at Lorangmyr
TK-02
Sollihøgda
Ring ngeriksba sbane nen o n og E16 TK-03
Sundvollen
13.08.2018
Ring ngeriksba sbane nen o n og E16
13.08.2018
Civ ivil w il work rks f for r the ra railw ilway lin line:
- The railway station with platforms, public room, stairs, elevators etc.
- Fillings in the lake Tyrifjorden: 1.000.000 pam3
- Railway bridge: 770 m total length, 2 tracks
- Tunnel: 3,5 km from Sundvollen towards Sandvika
- Estimated total muck production: 1.000.000 sm3
Civ ivil w il work rks f for r the h hig ighway:
- Highway bridge: 640 m, 4 lanes
- Intersection at Elstangen with bridges and “roundabouts” for local roads
and pedestrians
TK-03
Sundvollen
Ring ngeriksba sbane nen o n og E16 TK-04
Vik
13.08.2018
Ring ngeriksba sbane nen o n og E16
13.08.2018
Civ ivil w il work rks f for r ra railw ilway lin line a and d hig ighway:
- Tunnels (3 x 3,2 km) with low overburden through urban areas partly to
be constructed in rock and partly in soil
- Estimated total muck production: 900.000 sm3
- Methods for excavation: “Drill & blast” + “cut & cover” (optimal solutions
to be considered by the contractor)
- 3 km of rail- and highway in parallel trough high value nature resorts
- Rock from tunnelling to be used for open field substructure works in the
project
- Cuts and embankments
TK-04
Vik
Ring ngeriksba sbane nen o n og E16 TK-05
Mælingen
13.08.2018
Ring ngeriksba sbane nen o n og E16
13.08.2018
- Crossing unique wetlands and high value natural resorts
- Challenging soil conditions with high focus on foundation methods
- Typically 70 - 130 m to solid rock
- Alternative crossings of the river and wetlands at Mælingen:
– Alt. 1) Two double track railway bridges (300 m + 900 m) plus three highway bridges (1 x 300 4-lane + 2 x 900 m 2-lane) with (600 m) embankment in-between, or – Alt. 2) One double track railway bridge plus two 2-lane highway bridges (3 x 1.800 m)
- Alternative with embankment or not to be decided by Governing Authorities
TK-05
Mælingen
Alternative1 Alternative 2 Some river crossing concepts
Ring ngeriksba sbane nen o n og E16 TK-06
Hønefoss
13.08.2018
Ring ngeriksba sbane nen o n og E16
- Complete rebuild of Hønefoss railway station with surrounding areas
- Train parking for 8 x 220 m trains
- New railroad from Prestmoen to Hønefoss station and Ve (3 km)
- Railway technique (excl. signal) at the station and the surrounding areas
- New E16 Highway from Prestmoen to Ve (3 km) including two
intersections
- More than 25 constructions incl. bridges and concrete tunnels of variable
sizes
- 2 million m³ of masses from the tunnelling are expected to be used
- Logistically challenging enterprise with continuous rail and road traffic on
existing lines and roads through the entire construction period
- Large areas are covered by marine deposits including quick clay, of
various depths. Typically 50-100 m to solid rock
TK-06
Hønefoss
13.08.2018
Ring ngeriksba sbane nen o n og E16
- Start Preparatory Works:
2020
- Prequalification Main Contracts:
2019/2020
- Contract award first Main Contracts:
2020/2021
- Construction start first Main Contracts:
2021/2022
Ringerike Line and E16 Highway
Preliminary Key Dates
13.08.2018
Ring ngeriksba sbane nen o n og E16
Ringerike Line and E16 Highway
13.08.2018