7. a) 2. Attachment James A. Gifford Causeway Widening Cost Savings Opportunities April 3, 2019 7. a) 2. Attachment EA - Project Sequencing Short Term Improvements Emergency culvert repairs relining of 3 existing CSP culverts


slide-1
SLIDE 1

James A. Gifford Causeway Widening Cost Savings Opportunities

April 3, 2019

  • 7. a) 2. Attachment
slide-2
SLIDE 2

EA - Project Sequencing

  • Emergency culvert repairs – relining of 3 existing

CSP culverts

  • Priority 1: Causeway Slope Stabilization and

Platform Widening

  • 2m sidewalk & lighting of Causeway - north side
  • creation of 3 m wide shoulder - south side
  • 4-5 m extension of rock fill for future 4-lanes -

south side

  • Priority 2: Bridgenorth intersection improvements
  • Priority 3A: Ennismore intersection improvements
  • Priority 3B: Future 4-laning of causeway, including

bridge widening

Short Term Improvements Long Term Improvements

  • 7. a) 2. Attachment
slide-3
SLIDE 3

EA – Short Term Improvement Widen on 2 Sides Original Bid - $6.75 M

  • 7. a) 2. Attachment
slide-4
SLIDE 4

Revised Bid - $5.2 M Net Savings = $1.54 M Tender T-13-2018 – Value Engineered Widen on 1 side

  • 7. a) 2. Attachment
slide-5
SLIDE 5

EA - Long Term Improvement

  • 7. a) 2. Attachment
slide-6
SLIDE 6

Table #1 – Approved Project Sequencing

Short Term Improvement 1 Widening & Stabilization Rock fill & stabilize shoreline 2019-2020 $5.8 M 2 Maintenance repairs Pavement Rehab. Exist. 2-lanes 2021 $2.7 M 3 Road enhancements sidewalk, st. lights, storm sewer 2021 $1.0 M 4 Chemong Bridge rehabilitation 2022 $0.8 M Long Term Improvement 5 Roundabout Bridgenorth 2029 $1.1 M 6 Roundabout Ennismore 2029 $1.1 M 7 4-Lane construction 2 new lanes; rehab ex. 2-lanes 2039 $7.0 M 8 Chemong Bridge Twin 2039 $15 M $10.3 M $24.2 M

  • 7. a) 2. Attachment
slide-7
SLIDE 7

4 1 6 5 2 3 7 8 No. Description Timing Cost ($M) 1 Widening & Stabilization 2019- 2020 $5.8 2 Maintenance Repairs 2021 $2.7 3 Sidewalk, Street lights, storm system 2021 $1.0 4 Bridge Rehabilitation 2022 $0.8 5 Roundabout – Bridgenorth 2029 $1.1 6 Roundabout – Ennismore 2029 $1.1 7 4-lane constr. 2039 $7.0 8 Twin Bridge 2039 $15.0

Table #1 – Approved Project Sequencing

  • 7. a) 2. Attachment
slide-8
SLIDE 8

$5M $10M $15M $20M

Projection of Costs

Table #1 – Approved Project Sequencing

  • 7. a) 2. Attachment
slide-9
SLIDE 9

Short Term Improvement 2 Pavement Rehab. Pavement Rehab. Exist. 2-lanes 2019 $2.7 M 4 Chemong Bridge rehabilitation 2022 $0.8 M Long Term Improvement 5 Roundabout Bridgenorth 2029 $1.1 M 6 Roundabout Ennismore 2029 $1.1 M 1 Widening & Stabilization Rock fill & stabilize shoreline 2039 $5.8 M 1 Inflation on Rock Fill Estimated deferral cost to 2039 2039 $4.0 M 7 4-Lane construction 2 new lanes; rehab ex. 2-lanes 2039 $7.0 M 3 Road enhancements sidewalk, st. lights, storm sewer 2039 $1.0 M 8 Chemong Bridge Twin 2039 $15 M $3.4 M $35.0 M

Table #2 – Alternative Project Sequencing

  • 7. a) 2. Attachment
slide-10
SLIDE 10

$5M $10M $15M $20M

Projection of Costs

Table #2 – Alternative Project Sequencing

  • 7. a) 2. Attachment
slide-11
SLIDE 11

5 years 10 years 20 years $3.5 M $2.2 M $32.8 M Total $38.5 M 5 years 10 years 20 years $10.3 M $2.2 M $22.0 M Total $34.5 M

Projection of Costs

Summary

Table #1 - Approved EA Project Sequencing Table #2 - Alternative Project Sequencing

  • 7. a) 2. Attachment
slide-12
SLIDE 12

Risk

Public Safety and Liability

  • roadway remains in a safe and passable condition
  • inspection and monitoring; regular and routine patrols
  • respond immediately to repairs or maintenance existing infrastructure

Timing of Infrastructure Improvements Approved Project Sequencing

  • Rock fill widening and stabilization - 2019/2020
  • Pavement & maintenance repairs; road enhancements – 2021
  • Chemong Bridge rehabilitation - 2022

Procurement and Contractual Issues

  • No issues

Regulatory Approvals

  • DFO approvals pending
  • 7. a) 2. Attachment
slide-13
SLIDE 13

Risk

Infrastructure Improvements Alternative Project Sequencing

  • Rock fill widening and stabilization – deferred to 2039
  • Pavement & maintenance repairs – 2019
  • Road enhancements – deferred to 2039
  • Chemong Bridge rehabilitation - 2022

Procurement and Contractual Issues

  • Inflationary cost impacts due to deferral of widening and stabilization
  • Expenses already incurred under current contract
  • Renegotiation of major contract
  • If unsuccessful, potential revoking of contract
  • Potential for litigation against the County.

Regulatory Approvals

  • DFO approvals may be not required to complete maintenance and

enhancements.

  • DFO approvals would eventually be needed for any in-water work (2039).
  • 7. a) 2. Attachment
slide-14
SLIDE 14

Recommendation

Be it resolved that County Council receives the James A Gifford Causeway Widening Cost Savings Opportunities report; and That County Council endorse proceeding with the Causeway Improvement Plan as being the lowest cost solution and as previously approved by Council in the 10 year capital forecast.