James A. Gifford Causeway Widening Cost Savings Opportunities April - PowerPoint PPT Presentation

7. a) 2. Attachment James A. Gifford Causeway Widening Cost Savings Opportunities April 3, 2019 7. a) 2. Attachment EA - Project Sequencing Short Term Improvements Emergency culvert repairs relining of 3 existing CSP culverts


  1. 7. a) 2. Attachment James A. Gifford Causeway Widening Cost Savings Opportunities April 3, 2019

  2. 7. a) 2. Attachment EA - Project Sequencing Short Term Improvements Emergency culvert repairs – relining of 3 existing • CSP culverts Priority 1: Causeway Slope Stabilization and • Platform Widening - 2m sidewalk & lighting of Causeway - north side - creation of 3 m wide shoulder - south side - 4-5 m extension of rock fill for future 4-lanes - south side Long Term Improvements Priority 2: Bridgenorth intersection improvements • Priority 3A: Ennismore intersection improvements • Priority 3B: Future 4-laning of causeway, including • bridge widening

  3. 7. a) 2. Attachment EA – Short Term Improvement Widen on 2 Sides Original Bid - $6.75 M

  4. 7. a) 2. Attachment Tender T-13-2018 – Value Engineered Widen on 1 side Revised Bid - $5.2 M Net Savings = $1.54 M

  5. 7. a) 2. Attachment EA - Long Term Improvement

  6. 7. a) 2. Attachment Table #1 – Approved Project Sequencing Short Term Improvement 1 Widening & Stabilization Rock fill & stabilize shoreline 2019-2020 $5.8 M 2 Maintenance repairs Pavement Rehab. Exist. 2-lanes 2021 $2.7 M 3 Road enhancements sidewalk, st. lights, storm sewer 2021 $1.0 M 4 Chemong Bridge rehabilitation 2022 $0.8 M $10.3 M Long Term Improvement 5 Roundabout Bridgenorth 2029 $1.1 M 6 Roundabout Ennismore 2029 $1.1 M 7 4-Lane construction 2 new lanes; rehab ex. 2-lanes 2039 $7.0 M 8 Chemong Bridge Twin 2039 $15 M $24.2 M

  7. 7. a) 2. Attachment Table #1 – Approved Project Sequencing Cost No. Description Timing ($M) Widening & 2019- 1 Stabilization 2020 $5.8 Maintenance 6 2 Repairs 2021 $2.7 Sidewalk, Street 3 lights, storm 2021 $1.0 1 7 system 2 Bridge 4 Rehabilitation 2022 $0.8 3 Roundabout – 5 Bridgenorth 2029 $1.1 8 4 Roundabout – 6 Ennismore 2029 $1.1 5 7 4-lane constr. 2039 $7.0 8 Twin Bridge 2039 $15.0

  8. 7. a) 2. Attachment Table #1 – Approved Project Sequencing Projection of Costs $20M $15M $10M $5M

  9. 7. a) 2. Attachment Table #2 – Alternative Project Sequencing Short Term Improvement 2 Pavement Rehab. Pavement Rehab. Exist. 2-lanes 2019 $2.7 M 4 Chemong Bridge rehabilitation 2022 $0.8 M $3.4 M Long Term Improvement 5 Roundabout Bridgenorth 2029 $1.1 M 6 Roundabout Ennismore 2029 $1.1 M 1 Widening & Stabilization Rock fill & stabilize shoreline 2039 $5.8 M 1 Inflation on Rock Fill Estimated deferral cost to 2039 2039 $4.0 M 7 4-Lane construction 2 new lanes; rehab ex. 2-lanes 2039 $7.0 M 3 Road enhancements sidewalk, st. lights, storm sewer 2039 $1.0 M 8 Chemong Bridge Twin 2039 $15 M $35.0 M

  10. 7. a) 2. Attachment Table #2 – Alternative Project Sequencing Projection of Costs $20M $15M $10M $5M

  11. 7. a) 2. Attachment Projection of Costs Summary Table #1 - Approved EA Project Sequencing 5 years 10 years 20 years Total $34.5 M $10.3 M $2.2 M $22.0 M Table #2 - Alternative Project Sequencing 5 years 10 years 20 years Total $38.5 M $3.5 M $2.2 M $32.8 M

  12. Risk 7. a) 2. Attachment Approved Project Sequencing Public Safety and Liability - roadway remains in a safe and passable condition - inspection and monitoring; regular and routine patrols - respond immediately to repairs or maintenance existing infrastructure Timing of Infrastructure Improvements - Rock fill widening and stabilization - 2019/2020 - Pavement & maintenance repairs; road enhancements – 2021 - Chemong Bridge rehabilitation - 2022 Procurement and Contractual Issues - No issues Regulatory Approvals - DFO approvals pending

  13. Risk 7. a) 2. Attachment Alternative Project Sequencing Infrastructure Improvements - Rock fill widening and stabilization – deferred to 2039 - Pavement & maintenance repairs – 2019 - Road enhancements – deferred to 2039 - Chemong Bridge rehabilitation - 2022 Procurement and Contractual Issues - Inflationary cost impacts due to deferral of widening and stabilization - Expenses already incurred under current contract - Renegotiation of major contract - If unsuccessful, potential revoking of contract - Potential for litigation against the County. Regulatory Approvals - DFO approvals may be not required to complete maintenance and enhancements. - DFO approvals would eventually be needed for any in-water work (2039).

  14. 7. a) 2. Attachment Recommendation Be it resolved that County Council receives the James A Gifford Causeway Widening Cost Savings Opportunities report; and That County Council endorse proceeding with the Causeway Improvement Plan as being the lowest cost solution and as previously approved by Council in the 10 year capital forecast.

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.