IRRP Stakeholder Meeting
October 24, 2008
IRRP Stakeholder Meeting October 24, 2008 IRRP Stakeholder Meeting - - PowerPoint PPT Presentation
IRRP Stakeholder Meeting October 24, 2008 IRRP Stakeholder Meeting Agenda Welcome 10:00AM 10:05AM Program Overview 10:05AM 10:30AM 20% RPS 10:30AM 11:45AM Lunch Break 11:45PM 12:15PM Beyond 20% 12:15PM 1:45PM Closing
October 24, 2008
Slide 2
Slide 3
Grant Rosenblum Manager, Renewables Integration IRRP Stakeholder Meeting October 24, 2008
Slide 5
CAISO Corporate Goal CAISO Corporate Goal: Support the integration of renewable resources into the California power grid to fulfill State policy objectives
Maximize Renewable Maximize Renewable Resource Participati Resource Participation
Reliability Reliability Cost Cost Efficiency Efficiency
Grid Operati Grid Operations
Infrastructure Infrastructure Markets Markets Regulatory Activities Regulatory Activities
Slide 6
Slide 7
developments (e.g., once through cooling, long-term RA, greenhouse gas regulations, DR policy)
participants
Slide 8
Markets Operations Regulation Infrastructure
2012 2010
Tehachapi Upgrade Segment 1 Complete
Today
Tehachapi Upgrade Segments 4 - 10 Complete Sunrise Complete Tehachapi Upgrade Segments 11 Complete Tehachapi Upgrade Segments 2& 3 Complete DA/RT Renewables Forecasting MRTU Implemented
2020
33%+ RPS Goal
RAMP Forecasting MRTU Implemented Scarcity Pricing AB32 GHG Reduction Once Through Cooling Rules Overgen Study Existing Fleet Study Resource Mix assessment PDR DDR Interchange Scheduling LTPP TPP/RETI 20% RPS goal Storage Pilot
Clyde Loutan Senior Advisor, Regional Transmission Engineer IRRP Stakeholder Meeting October 24, 2008
Slide 10
Load Following is ing is necessary to m necessary to maintain stable op aintain stable operations erations
700 - 800 MW 500 - 900 MW
Regulation is required to maint red to maintain frequency ain frequency and maintain and maintain interchange schedules interchange schedules
170 - 250 MW 100 - 500 MW
Slide 11
Slide 12
Plexos)
model to determine:
timeframes
the unit commitment process
Slide 13
existing resources
reserve procurement, supplemental energy dispatch and regulation algorithms
the level of limitations identified and in the model and analytical approach
Slide 14
Slide 15
generation
Slide 16
Slide 17
England ISO, and PJM
Slide 18
Wind Ra Wind Ramp mp Forecast Forecast Automatic Automatic Dispatch Dispatch Wind Wind Data Data Display Load Load Forecast Forecast Wind Wind Forecast Forecast Generation Generation Schedule Schedule Interchang Interchange Schedule Schedule Masterfile Masterfile Data Data
Decision Tool
Slide 19
Slide 20
Jim Blatchford
IRRP Stakeholder Meeting October 24, 2008
Slide 22
Slide 23
AWS Truewind Studies
Slide 24
2
Slide 25
Nex Next D t Day ay
Annua Annual MA l MAE % m % mons
< 12% % m % mons
< 14% Annua Annual MA l MAE
Plant E 13.83% 22.2% 55.6% 19.83% Plant H 13.65% 16.7% 58.3% 18.60% Plant F 15.30% 0.0% 16.7% 19.43% Plant I 6.80% 100.0% 100.0% 15.38% Plant A 11.30% 66.7% 83.3% 15.63% Plant O 14.18% 33.3% 50.0% 18.44% Plant J 12.94% 25.0% 66.7% 21.17% Plant K 14.57% 16.7% 50.0% 20.57% Plant L 14.76% 16.7% 50.0% 21.41% Plant G 15.29% 8.3% 16.7% 17.80% Plant D 8.13% 100.0% 100.0% 41.41% Plant B 14.59% 0.0% 50.0% 20.64% Plant C 12.43% 25.0% 50.0% 17.44% Plant M 14.91% 16.7% 58.3% 18.77% Plant N 14.86% 16.7% 33.3% 24.49% Overa Overall ll 13.3 13.32% 2% 28.7 28.7% 54.4 54.4% 18.8 18.85% 5% Fac Facilit ility Nex Next Ope t Operatin rating Hour g Hour
Slide 26
A B C
D
Slide 27
Continue to Improve the Curves w/ Data Quality
Slide 28
Consequences
Patterns
forecast time periods
Slide 29
Jun 19, 2009 May 22, 2009 Apr 17, 2009 Mar 20, 2009 Feb 20, 2009 Jan 23, 2009 Dec 19, 2008 Nov 21, 2008
Udi Helman Principal, Market and Product Development IRRP Stakeholder Meeting October 24, 2008
Slide 31
(Market Initiatives Roadmap, etc.)
needed capabilities (Roadmap, etc.)
capability and market value in ancillary services
power sector market and policy developments (e.g., once through cooling, long-term RA, greenhouse gas regulations)
Slide 32
available to represent binding constraints and elicit needed capabilities to relieve those constraints
Slide 33
to support 20% RPS, but that additional capabilities would enhance integration (and are needed beyond 20%)
Slide 34
Commitment (RUC)
Shortages
(PDR) and Dispatchable Demand Response (DDR)
Slide 35
Slide 36
Beyond 20%
Clyde Loutan Senior Advisor, Regional Transmission Engineer IRRP Stakeholder Meeting October 24, 2008
Slide 38
Slide 39
Plexos and PNNL)
Slide 40
timelines
procurement, supplemental energy dispatch and regulation algorithms
market products
strategies
Beyond 20%
David Le Lead Regional Transmission Engineer IRRP Stakeholder Meeting October 24, 2008
Slide 42
Slide 43
CREZs
for accessing CREZ
transmission planning process
Phase II schedule and work plans currently in development by RETI
Beyond 20%
Udi Helman Principal, Market and Product Development IRRP Stakeholder Meeting October 24, 2008
Slide 45
sectoral?
Procurement Plan
updated on an ongoing basis to inform market needs
Slide 46
Specifications
David Hawkins Lead Renewables Power Engineer IRRP Stakeholder Meeting October 24, 2008
Slide 48
Generation Generation Portfolio Portfolio Storage Storage Demand Demand Response Response
Resources Required for Resources Required for Renewables Integ Renewables Integration ration
Quick St Quick Start Units art Units Fast Ramp Fast Ramping ing Wider Opera Wider Operating ting Range Range (lo (lower P wer Pmin
min)
Regulat Regulation cap ion capability ability Shift Energy Shift Energy from from
ak to on-pea
Mitigate Mitigate Over Over Generation Generation Voltage Voltage Support Support Regulat Regulation cap ion capability ability Price sensi Price sensitive loa tive load Respons Responsive to ive to ISO ISO dispat dispatches ches Frequen Frequency cy Responsive Responsive Respons Responsive to ive to Wind Wind Generation Generation Produ Production ction
“Partners in Success” “Partners in Success”
Wind Genera Wind Generation tion Solar Generation Solar Generation Hydro Generation Hydro Generation
Slide 49
Source: July 2008 DOE Report on 20% Wind by 2030
Slide 50
Slide 51
interchange schedules.
delivery of wind energy from BPA to CAISO on a 10, 15, 20, or 30 minute basis.
Slide 52
Slide 53
Slide 54
Slide 55
dispatch commands
system
Slide 56
Slide 57
production with available transmission capacity
wind parks and detection of wind sheer
stability limits on key transmission paths (i.e. COI)
Renewable Integration
Integration
Slide 58
DOE SCE IRC WREZ
Policy / Regulation R&D Infrastructure Markets / Operations
DOE AWEA PG&E EPRI NERC NREL PARS PIER UWIG VGIS WECC WGA WPTF WREZ CEC PNNL CPUC BPA FERC WREGIS SDG&E
Slide 59