IRRP Stakeholder Meeting on Renewable Integration Requirements
Jim Blatchford
- Sr. Policy Issues Rep.
IRRP Stakeholder Meeting on Renewable Integration Requirements Jim - - PowerPoint PPT Presentation
IRRP Stakeholder Meeting on Renewable Integration Requirements Jim Blatchford Sr. Policy Issues Rep. Facilitator IRRP Stakeholder Meeting (Teleconference) October 20, 2009 Overview / Call Objective Provide status of ongoing efforts to
Slide 2
Slide 3
Slide 5
Slide 6
Slide 7
Slide 8
Slide 9
April 21 - Concentrated Solar
50 100 150 200 250 300 350 0:00 0:42 1:24 2:06 2:48 3:30 4:12 4:54 5:36 6:18 7:00 7:42 8:24 9:06 9:48 10:30 11:12 11:54 12:36 13:18 14:00 14:42 15:24 16:06 16:48 17:30 18:12 18:54 19:36 20:18 21:00 21:42 22:24 23:06 23:48
Megawatts
Slide 10
April 12 - Wind + Solar
0.0 200.0 400.0 600.0 800.0 1,000.0 1,200.0 1,400.0 1,600.0 0:00 0:43 1:26 2:09 2:52 3:35 4:18 5:01 5:44 6:27 7:10 7:53 8:36 9:19 10:02 10:45 11:28 12:11 12:54 13:37 14:20 15:03 15:46 16:29 17:12 17:55 18:38 19:21 20:04 20:47 21:30 22:13 22:56 23:39
Megawatts
WIND SOLAR WIND + SOLAR
Slide 11
Slide 12
Slide 13
Slide 14
Slide 15
Load, MW t Hour Ahead Load Schedule Hour Ahead Load Schedule t+1
Slide 16
including the 20-minute ramps between hours.
process is provided 2 hours before the beginning of an
number generator based on the statistical characteristics of the load forecast error (derived from 2006/2007 data)
w ha w w a hr w hr ha
CAP G avg G ⋅ − ℜ =
, 1 20 1 ,
ε
s ha s s a hr s hr ha
CAP G avg G ⋅ − ℜ =
, 1 20 1 ,
ε
ha L a hr hr ha
L avg L
, 1 20 1 ,
ε − ℜ =
Slide 17
MW t Operating Hour
Hour Ahead Schedule Day Ahead Schedule Hour Ahead Adjustment Load Following Generation Requirement Regulation Hour Ahead Schedule And Load Following
Slide 18
simulated using a random number generator based on the statistical characteristics of the actual real-time and actual hour- ahead load and wind forecast error
Normal Distribution (TND)
is used to produce forecast errors.
PDF() 1 εmax εmin
1.1 Minimum
Maximum 349.4
97.8 Autocorrelation 0.6
Table 3 Estimated Hour-Ahead Wind Generation Forecast Characteristics (in Fraction of Capacity)
Seasons Winter Spring Summer Fall Average 0.00012
0.0006 Minimum
Maximum 0.3092 0.3084 0.3074 0.3966
0.0723 0.0899 0.0796 0.0792 Autocorrelation 0.6106 0.7061 0.6519 0.5939
Table 1 Real-time Load Forecast Characteristics Table 2 Hour-Ahead Load Forecast Characteristics of the Yr. 2006 (in MW)
Seasons Winter Spring Summer Fall Average
Min
Max 1842.06 1930.54 2446.12 2080.98
637.37 601.34 900.13 687.52 Autocorrel ation 0.70 0.73 0.89 0.83
min( ( , , , , ))
e
f a b c d σ
Slide 19
radiation Rg by the extraterrestrial global irradiation R: k = Rg/R
radiation.
the standard deviation of the solar forecast errors will vary. Thus, the standard distribution of the solar forecast errors can be described as a function of a parameter ξ, .
k σ
1 Fig.9. Clearness index v.s. standard deviation of solar forecast errors.
Clearness Index and Std. Dev. Of solar forecast
Slide 20
Daily pattern of the solar radiation of clearness index. Fig.8. Distribution of solar forecast error in very cloudy day and a very sunny day. Forecast Error
Slide 21
‐Pmax ε Pmax ε
Sunny Day Cloudy Day Probability Sunny Day Probability Cloudy Day Forecast Error Forecast Error
Slide 22
t MW
Economic Dispatch (Load Following) Actual Load Hourly Schedule 5-Minute Schedule
Slide 23
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 2200 2400 2600 2800 3000 3200 3400 3600 Load Following, Summer, Year 2010 vs.2006 Max Load Following Capacity, Inc, MW 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 −3600 −3400 −3200 −3000 −2800 −2600 −2400 −2200 Hours Ending Max Load Following Capacity, Dec, MW
The maximum upward capacity requirement of 3,500 MW
The maximum increase of 800 MW occurs during HE3 (3,500 – 2,700) The maximum downward capacity requirement of 3,450 MW occurs during HE24 The maximum downward capacity increase of 500 MW (3,050 -2,450) occurred in HE22
Slide 24
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 50 100 150 200 250 Load Following, Summer, Year 2010 vs.2006 Max Load Following Ramp Rate, Inc, MW/min 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 −180 −160 −140 −120 −100 −80 −60 −40 Hours Ending Max Load Following Ramp Rate, Dec, MW/min
Slide 25
5 10 15 20 25 30 20 40 60 80 100 120 Max Ramp Rates, Inc/Up, MW/min Load Following, Summer, Year 2010 vs. 2006, Hour 8, 9, 10 5 10 15 20 25 30 −200 −150 −100 −50 Duration (min) Max Ramp Rates, Dec/Down, MW/min 2006 Non Wind 2006 Wind 2010 Non Wind 2010 Wind
Slide 26
t MW
Economic Dispatch (Load Following) Actual Load Hourly Schedule 5-Minute Schedule Regulation
Slide 27
applications using 15-minute intervals for RTUC and 5-minute interval for RTED
dispatch interval 5 minutes before the actual beginning of the interval.
beginning of the interval.
after its beginning).
rtf L a rtf
L avg L
, min 5 5 min 5 ,
) ( ε − ℜ =
] 8 [ ] 5 , [
min 5 ,
− = +
−
t G t t G
w a w rtf
] 8 [ ] 5 , [
min 5 ,
− = +
−
t G t t G
s a s rtf
Slide 28
Load, MW t 5 Minute Dispatch Interval Real Time Load Schedule 5 Minute Ramps Actual Load Average Actual Load Forecast Error
Slide 29
Dispatch Range MW t t-2.5 t+2.5 t+5 t+7.5 t+10 Minutes Interval 1 Interval 2 Run starts Here for Interval 2 ADS Instruction Sent for Interval 2 Units begin in move to DOT in interval 2 10 minutes A B C D E
Slide 30
Slide 31
Slide 32
Slide 33
Slide 34
Slide 35
Slide 36
Slide 37
* Regulation MW vary by TOD and season
Slide 38
Slide 39
Slide 40
Slide 41
Slide 42
Slide 43
Slide 44
200 400 600 800 1,000 0.01 0.02 0.03 0.04 0.05 0.06 0.07 0.08 0.09 Hours MW
DRAFT RESULTS
Slide 45
500 1,000 1,500 2,000 2,500 0.0 0.6 1.1 1.6 2.2 2.7 3.3 3.8 4.3 4.9 5.4 5.9 6.5 7.0 7.6 8.1 8.6 9.2 9.7 Hours MW
DRAFT RESULTS
Slide 46
Duration Curve of Reg-up Shortfall (MW) 2012 (2006- based) 100 200 300 . 1 . 2 . 3 . 4 . 5 . 6 . 7 . 8 . 9 . 1 . 1 1 . 1 2 . 1 3 Hours MW DRAFT RESULTS
Slide 47
500 1,000 1,500 2,000 2,500 0.0 0.1 0.3 0.4 0.5 0.6 0.7 0.8 1.0 1.1 Hours MW Over-Gen in DA Over-Gen in HA Over-Gen in RTD DRAFT RESULTS
Slide 48
Violation Occurrences from 100-iteration Simulations Service Overgeneration Reg-up shortfall Unserved Energy Date Market DAM HAM RTD DAM HAM RTD DAM HAM RTD February 27, 2012 2006-based April 17, 2012 2006-based 99 49 105 May 7, 2012 2006-based 108 82 8 June 24, 2012 2006-based 1 July 23-24, 2012 2006-based 6 2 5 September 3, 2012 2006-based February 27, 2012 2007-based July 3, 2012 2007-based August 30, 2012 2007-based 5 2 3 2
DRAFT RESULTS
Slide 49
Slide 50
Slide 51
Slide 52
Slide 53
Slide 54
Slide 55
Nuclear 2,522 4,500 4,526 4,500 3,620 4,500 3,468 4,500 Hydro 3,823 3,500 2,707 2,700 1,009 1,000 2,337 2,000 Thermal 3,822 3,100 4,325 4,400 5,573 4,500 5,263 4,000 Qualifying Facilities 3,339 3,000 4,021 4,000 4,238 4,000 3,651 3,500 Geothermal 783 1,200 789 1,200 794 1,200 800 1,200 Imports 5,149 4,000 5,511 4,500 4,744 4,200 4,630 4,000 Total Generation plus Interchange 19,438 19,300 21,879 21,300 19,978 19,400 20,149 19,200 Average Wind - 2006 711 1,043 430 324 Average Load - 2006 20,149 22,922 20,408 20,473 Minimum Load 19,064 20,800 20,837 22,800 19,189 21,000 18,737 20,500 Maximum Renewable that can be Integrated - 2012 1,500 1,500 1,600 1,300
High Hydro --- Average Generation by Technology
Spring Summer Fall Winter 2006 MW 2012 MW 2006 MW 2006 MW 2006 MW 2012 MW 2012 MW 2012 MW
Slide 56
Nuclear 4,279 4,500 4,179 4,500 3,886 4,500 4,196 4,500 Hydro 1,108 1,100 1,392 1,400 879 900 811 800 Thermal 3,107 4,000 4,140 4,400 5,587 4,100 5,667 4,000 Qualifying Facilities 3,744 3,700 4,305 4,200 4,125 4,000 4,402 4,000 Geothermal 801 1,200 827 1,200 816 1,200 798 1,200 Imports 7,023 4,600 6,947 5,400 5,065 4,500 4,598 4,500 Total Generation plus Interchange 20,062 19,100 21,790 21,100 20,358 19,200 20,472 19,000 Average Wind - 2007 823 1,087 308 386 Average Load - 2007 20,885 22,877 20,666 20,858 Minimum Load 19,699 20,800 21,020 22,800 19,630 21,000 19,414 20,500 Maximum Renewable that can be Integrated - 2012 1,700 1,700 1,800 1,500
Low Hydro --- Average Generation by Technology
Spring Summer Fall Winter 2007 MW 2012 MW 2007 MW 2007 MW 2007 MW 2012 MW 2012 MW 2012 MW
Slide 57
Summer 2006 - Minimum 10% of Load
2 4 6 8 10 12 14 16 18 20 22 24 26 100 200 300 400 500 600 700 800 900 1,000 1,100 1,200 1,300 1,400 1,500 1,600 1,700 1,800
Wind Production (MW) # of Occurrences
Slide 58
2 2 , 9 2 3 , 2 2 3 , 5 2 3 , 8 2 4 , 1 2 4 , 4 2 4 , 7 2 5 , 2 5 , 3 2 5 , 6 2 5 , 9 2 6 , 2 2 6 , 5 2,000 2,800 3,600 4,400 5,200 0.5 1 1.5 2 2.5 3
# of Occurrences
Load (MW)
Wind (MW)
Summer 2012 --- Load vs. Wind
Minimum 10% of Load
Slide 59
Summer 2012 --- Load vs. Wind
Minimum 10% of Load
22,000 22,400 22,800 23,200 23,600 24,000 24,400 24,800 25,200 25,600 26,000 26,400 26,800 27,200 300 600 900 1,200 1,500 1,800 2,100 2,400 2,700 3,000 3,300 3,600 3,900 4,200 4,500 4,800
Wind Production (MW) Load (MW)
Slide 60
Estimated Energy Curtailment
Summer 2012 --- High Hydro
10 20 30 40 50 60 70 80 90 100 110 120 100 300 500 700 900 1,100 1,300 1,500 1,700 1,900 2,100 2,300 2,500 2,700 2,900 3,100 3,300 3,500
Curtailment (MW) # of Hours
Min Wind 1,000 MW Min Wind 1,500 MW Min Wind 2,000 MW
Slide 61
Expected Curtailment High Hydro --- 20% RPS
Spring Summer Fall Winter
Maximum Wind (MW) Expected Curtailed (Hrs) Maximum Wind (MW) Expected Curtailed (Hrs) Maximum Wind (MW) Expected Curtailed (Hrs) Maximum Wind (MW)) Expected Curtailed (Hrs)
Total (Hrs) 1,000 130 1,000 112 1,100 57 800 34 333 1,500 91 1,500 73 1,600 25 1,300 12 201 2,000 46 2,000 46 2,100 6 1,800 4 102
Expected Curtailment High Hydro --- 20% RPS
Spring Summer Fall Winter
Maximum Wind (MW) Expected Curtailed (MWh) Maximum Wind (MW) Expected Curtailed (MWh) Maximum Wind (MW) Expected Curtailed (MWh) Maximum Wind (MW) Expected Curtailed (MWh)
Total (MWh) 1,000 116,600 2.74% 1,000 120,000 2.17% 1,100 30,700 0.83% 800 17,700 0.53% 285,000 1,500 60,300 1.42% 1,500 71,400 1.29% 1,600 9,300 0.25% 1,300 5,400 0.16% 146,400 2,000 24,100 0.57% 2,000 41,400 0.75% 2,100 1,600 0.04% 1,800 1,200 0.04% 68,300
Slide 62
Estimated Energy Curtailment
Summer 2012 --- Low Hydro
10 20 30 40 50 60 70 80 90 100 100 300 500 700 900 1,100 1,300 1,500 1,700 1,900 2,100 2,300 2,500 2,700 2,900 3,100 3,300 3,500
Curtailment (MW) # of Hours
Min Wind 1,000 MW Min Wind 1,500 MW Min Wind 2,000 MW
Slide 63
Expected Curtailment Low Hydro --- 20% RPS
Spring Summer Fall Winter
Minimum Wind (MW) Expected Curtailed (Hrs) Minimum Wind (MW) Expected Curtailed (Hrs) Minimum Wind (MW) Expected Curtailed (Hrs) Minimum Wind (MW) Expected Curtailed (Hrs)
Total (Hrs) 1,200 130 1,200 86 1,300 41 1,000 26 283 1,700 64 1,700 54 1,800 16 1,500 10 144 2,200 30 2,200 36 2,300 2 2,000 3 71
Expected Curtailment Low Hydro --- 20% RPS
Spring Summer Fall Winter
Minimum Wind (MW) Expected Curtailed (MWh) Minimum Wind (MW) Expected Curtailed (MWh) Minimum Wind (MW) Expected Curtailed (MWh) Minimum Wind (MW) Expected Curtailed (MWh)
Total (MWh) 1,200 80,300 1.88% 1,200 88,100 1.66% 1,300 19,800 0.54% 1,000 11,500 0.35% 199,700 1,700 35,700 0.84% 1,700 52,000 0.94% 1,800 5,100 0.14% 1,500 3,100 0.09% 95,900 2,200 12,400 0.29% 2,200 28,600 0.52% 2,300 700 0.02 % 2,000 400 0.01 % 42,100
Slide 64
Slide 65
Slide 66
Slide 67
Slide 68
Slide 69
Slide 70
Slide 71
10 20 30 40 50 60 70 80 90 100
20 40 60 80 100 MW # of Occurences Wind Solar
Slide 72
Wind/Solar Hourly Ramps
50 100 150 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 MW/hr W in d S
r
Slide 73
ACE/Regulation/Wind Profile
100 200 300 400 500 600 700 00:00 01:15 02:30 03:45 05:00 06:15 07:30 08:45 10:00 11:15 12:30 13:45 15:00 16:15 17:30 18:45 20:00 21:15 22:30 23:45 ACE/Regulation (MW) 100 200 300 400 500 600 700 800 900 Wind (MW) ACE Regulation Wind
Slide 74
500 550 600 650 700 750 800 850 1 3 5 7 9 1 1 1 3 1 5 1 7 1 9 2 1 2 3
Slide 75
Maximum Upward Ramp 3-Hour 1-Hour 10-min. 5-min 6,255 3,053 826 442 4:20 5:55 5:56 5:59 218 157 54 37 19:41 20:38 22:29 14:37 6,175 3,079 813 440 4:20 5:55 5:56 5:59 Maximum Downward Ramp 3-Hour 1-Hour 10-min. 5-min 5,813 2,224 458 325 20:52 21:58 22:25 3:44 243 162 70 43 16:30 18:34 21:59 14:33 5,933 2,271 495 322 20:52 22:09 22:23 3:44
**** Time indicates the start of respective ramps.
Wind (MW) Load-Wind (MW) Load (MW) Wind (MW) Load-Wind (MW) Load (MW)
Slide 76
Slide 77
Slide 78