Integrated Design Paul Westbrook Sustainable Development Manager, - - PowerPoint PPT Presentation

integrated design
SMART_READER_LITE
LIVE PREVIEW

Integrated Design Paul Westbrook Sustainable Development Manager, - - PowerPoint PPT Presentation

Integrated Design Paul Westbrook Sustainable Development Manager, LEED AP Texas Instruments Facilities, Energy Team Senior Member of the TI Technical Staff Senior Fellow, US State Department Energy and Climate Partnership of the Americas (ECPA)


slide-1
SLIDE 1

Integrated Design

Paul Westbrook

Sustainable Development Manager, LEED AP Texas Instruments Facilities, Energy Team Senior Member of the TI Technical Staff Senior Fellow, US State Department Energy and Climate Partnership of the Americas (ECPA)

slide-2
SLIDE 2

Outline

  • Impact of Buildings
  • Integrated Design Defined
  • Case Study: Residential
  • Case Study: Industrial
  • RFAB Results
slide-3
SLIDE 3

Buildings

  • We spend 90% of our lives in buildings
  • Buildings use 73% of all electricity produced
  • Buildings use 14% of all water consumed
  • Buildings use 40% of all raw materials
  • Buildings produce 38% of all CO2 emissions
slide-4
SLIDE 4

Integrated Design

An iterative, non-linear process

  • 1. Architect draws up design
  • 2. Everyone else makes it work:
  • High cooling load window locations
  • No room for ductwork
  • Excessive materials use / waste
  • Poor daylighting

. . . Over budget, then “value engineering” occurs

Typical Linear Design Process

slide-5
SLIDE 5

Integrated Design

Value Engineering is Neither

  • Amory Lovins, RMI
slide-6
SLIDE 6

Integrated Design

Source: “A Group Effort,” GreenSource Magazine, Nov 2006

This process can reduce capital cost AND operating cost

slide-7
SLIDE 7

Two Words: START EARLY

Diagram by Tetra Tech/KCM

Minimal Cost + Minimal Effort = Maximum Savings

slide-8
SLIDE 8

Case One: Personal Experience

  • In the early 90’s I designed my own passive

solar home

– I was the architect, engineer, finance department, interior designer, . . . . – I hired a small, local builder and obtained their input during the design phase – We asked for input from suppliers during the design

“Quality, Cost, Schedule – Pick Two”

– We took the time to do make sure the quality was there – from the design, through the construction – We managed the budget by estimating and bidding the entire job during the design phase

slide-9
SLIDE 9

Case One: Integrated Design Example

  • These items:

– Proper orientation with respect to the sun path – The best glazing, in the right place, with the correct overhang – High levels of insulation and air tightness – A reflective metal roof

  • Led to:

– Reduced cooling/heating load

  • Which resulted in:

– A smaller air conditioning system

  • Which allowed me to afford:

– A highly efficient ground source heat pump

All those items combine for better comfort at lower cost

Window Quality Window Qty Solar Gain Window Location House Size A/C Size A/C Type A/C Cost Insulation Value House Layout

Optimization Loop

slide-10
SLIDE 10

Case One: Results

  • Energy costs of about 1/3rd of my neighbors
  • Water costs about 1/8th of my neighbors
  • Low maintenance costs
  • Won the 1996 NAHB Energy Value Housing

Award for Innovative Design

  • House was exactly on budget – no late Value

Engineering required

  • The builder and I are still speaking
  • Tour of my house by a TI VP sparked an idea to

do this process on a very large scale . . . .

Westbrook House - www.enerjazz.com/house

slide-11
SLIDE 11

Case Two: Semiconductor Fab

  • 92-acre site
  • 1.1 million square feet
  • 284,000 square feet of cleanroom

space

  • Capacity for about 1,000 employees
slide-12
SLIDE 12

Case Two: The Opportunity

  • Very tight temperature and humidity

requirements . . .

– 70F+/-2 (21C+/-1) and 45% RH +/- 3%

  • Combined with a large amount of exhaust and

subsequent make up air . . .

– 650,000 cfm (307 m3/sec) = 2 Macy’s Kermit balloons per second

  • Combined with the need to recirculate a large

volume of air through the filters for cleanliness . .

– 4,400,000 cfm (2077 m3/sec) = 22 Goodyear blimps a minute

  • Combined with hundreds of process tools with

vacuum pumps and other support equipment . . . Could lead to annual energy consumption of 250,000 mWh

(~15,000 homes worth) and an annual utility bill >$18M.

slide-13
SLIDE 13

Case Two: Strategy

  • Strategy Team - Fabscape

– 4 strategy teams were formed in advance of project – Request made to add a 5th team - sustainability – Generated early white papers on a number of ideas

  • Tour My House

– Invited 3 TI VP’s to tour active/passive solar home

– Low utility bills for “normal” house spurred interest

  • Design Workshop

– Teamed up with Rocky Mountain Institute (RMI)

– Held 3-day design charrette to brainstorm ideas (Dec 2003) – Generated 15 “Big Honkin’ Ideas” to carry forward along with a large list of other good ideas – Made a first pass at LEED score sheet

slide-14
SLIDE 14

Case Two: Project Management

  • Sustainable Development Manager role

assigned

– Chief integrator of ideas and systems – The building was the system to be optimized

  • Project Manager was fully supportive

– Safety, Cost, Schedule, and Sustainability were front page

  • Construction Contractor was the general

contractor with the design firm under them

– Everyone on board from the start

Don’t optimize the parts and pessimize the system

slide-15
SLIDE 15

Cost Reduction – Friend or Foe

  • Challenge:

–Reduce fab capital costs per square foot by 30 percent from the previous fab

  • Response:

– WHAT? – Question everything – Space efficiency – Couldn’t just copy previous design – had to innovate – All of this led to . . . . Engineering!

slide-16
SLIDE 16

Integrated Design

You know you are on the right track

when your solution for one problem accidentally solves several others.

  • Amory Lovins, RMI
slide-17
SLIDE 17

Lighting #1 energy user In office

Integrated Design Example

An example of making the connections

– Light Fixture Selection

Standard cost = $125

  • p cost = $40/yr

Sensor light cost = $375

  • p cost = $25/yr

Simple payback = 16.7 years However, we need 30% fewer sensor light

  • fixtures. Simple payback down to 6.7 years.

Efficient lighting also saves cooling energy. Simple payback down to 6.0 years. Add the contribution from dozens of similar projects (lighting, reflective roof, light shelves, sun shades, quality windows, extra insulation, better vacuum pumps, . . ) Enough cooling load disappears to avoid buying a $1M chiller . . . and the cooling tower, pumps, pipes, and even the space needed to install it. Simple payback is now 0.0 years. The total net capital cost is the same, or even less, and the operating costs are lowered forever.

Typical Texas Office Building Energy Use Lighting 42% Vent / Cooling 24% Office Equipment 18% Heating 6% Water Heating 5% Misc 5%

slide-18
SLIDE 18

Integrated Design Example

But wait, it gets even better . . .

Sensor lights are individually controllable by each employee Natural daylighting has been shown to increase productivity Cost of operation over 30 years for an office building People costs account for 92% of all costs over a 30 year period. If natural daylighting, self-control of lighting, improved indoor air quality, and all the other green building factors improved productivity by just 1% that would save the company >$1M/year for a large office complex. Plus, if people like the building and control over their space it can give companies a recruiting advantage for top talent.

slide-19
SLIDE 19

Categories

  • Lower Capital Cost AND Lower Operating Cost
  • Space efficiency
  • Piping / ductwork efficiency
  • No Net Capital Cost and Lower Operating Cost
  • Site Selection, orientation
  • Cost trades
  • Increase cost of insulation and windows, but reduce

mechanical system size and cost

  • Some Additional Capital Cost with Lower Operating

Cost

  • Projects with ~5 year or better payback
slide-20
SLIDE 20

Steps

  • Complete space layout and furniture selection first
  • Optimize column and wall spacing for furniture system
  • Minimize wasted space
  • Model, model, model
  • Build a working energy model and iterate/optimize the

whole system design

  • Construction contractor on board at the start
  • Real time cost and constructability feedback during the

design

slide-21
SLIDE 21
  • Passive solar orientation with exterior shading
  • Optimized glazing (high VLT, low SHGC, low U value)
  • Reflective roof
  • Natural daylighting with light shelves / light-louvers
  • High-efficiency lighting (motion and daylight sensors)
  • Demand-controlled ventilation
  • Attention to detail on insulation and infiltration

Office Efficiency

slide-22
SLIDE 22

Compost tubes

Pond collects runoff from most of the 92 acres. 2.7 million gallon (10.2 million liters) base + 2 million gallon buffer. The pond meters runoff and settles sediment. Pond water is used for all site irrigation. Windmill drives an air compressor to aerate the pond. < Areas were restored to native prairie grass to minimize irrigation and provide biodiversity.

More Integration

slide-23
SLIDE 23

23

Efficient Lights Exterior Shades Solar Water Heating Native Meadow Restoration Water Turbine Powered Faucet Rain Water Reuse Pond

Sustainability at RFAB

Reflective Roof Day lighting Dark Skies Friendly Lighting Bicycle Parking Efficient cooling system with waste heat recovery

slide-24
SLIDE 24

Boiler

Fab Energy Flow

Recirc Fans Shell Loss

  • air leak
  • thermal

Tool Power Lighting Support Syst Cooling Coil Other Exhaust General Exhaust

Enthalpy Wheel

54 CHW MUA 40 CHW Boiler CDA Make Up Air Run Around

  • 2. Internal Cooling Load
  • 3. Sensible Heat Removal
  • 1. External Load
  • 4. Exhaust and Make Up Air
  • 5. MUA Cooling, Dehumidification, and Heating
  • 6. Energy Efficient – Energy Recovery
slide-25
SLIDE 25

Energy Savings – Facilities Efficiency

Central Utilities Plant – Chiller Plant (25%

  • f fab load)
  • Split plant to match needs to capacity:
  • 40° F (4.4° C) for dehumidification (.44 - .51 kW/ton)
  • 54° F (12.2° C) for all other loads (.32 - .50 kW/ton)
  • Heat recovery on 54° F plant (75% of CHW load)
  • More constant load year-round
  • Minimal energy penalty for free hot water
  • Reduced boilers from six to two (500HP each)
  • Utilize variable primary distribution – only one set
  • f pumps that vary their speed with the demand
  • Redundancy is 1 x 40° F chiller for both 40° F and

54° F (blending for 54° F)

slide-26
SLIDE 26

Energy Savings – Chiller Plant

40° F CHWS 54° F CHWS 70° F (21° C) CHWR

4,560 tons – 40° F (4.4° C) 8,000 tons – 54° F (12.2°C) with heat recovery

1,520T 1,600T 1,600T 1,600T 1,600T 1,600T 1,520T 1,520T

  • Make-up air pre-cool
  • Cleanroom recirculated air
  • PC water
  • Plant vacuum
  • Cooling for DIW
  • Miscellaneous AHU

MUA dehumidification

slide-27
SLIDE 27

Energy Savings – Hot Water

100° F (38° C) HRWS 65° F (18° C) HRWR

54° F heat recovery bundles

HR HR HR HR HR

  • MUA pre-heat/re-heat
  • Raw water heating for DIW

500 HP 500 HP Boiler backup CDA 25 HP 25 HP HDIW heating

140° F HWR 180° F HWS

HDIW boilers Cooling Towers

1 2 3

  • 1. Primary source – waste heat

from air compressors;

  • 2. Secondary source waste heat

from chillers;

  • 3. Coldest days require boilers

to be used.

slide-28
SLIDE 28

RFAB Results

  • We invested less than 1 percent of the project cost

($1.5M/$320M) in LEED-related items:

  • Predominately efficiency improvements that we would have

considered regardless of LEED

  • Overall capital cost was 30 percent less than our previous

fab just 6 miles away

  • In the first year, we saved $1 million in operating costs
  • At full build out, we will save more than $4 million per year:
  • 20 percent energy reduction (>38% for facilities systems)
  • 40 percent water-use reduction
  • 50 percent emissions reduction
  • LEED Gold Certified Office and Fab (first LEED Gold fab in the world)

www.ti.com/rfab

slide-29
SLIDE 29

RFAB Results

  • “RFAB will be at least 20% more energy efficient

than DM6” (Paul Westbrook, April 6, 2005)

26% better Energy/pattern

Results: 26% more efficient than DM6

slide-30
SLIDE 30

Summary

  • Develop the basic project requirements
  • Set the sustainable goals early
  • Organize for success

– Have a broad team on board early – Assign a champion and integrator – Have a design session to exchange ideas, stretch thinking, and make connections

  • Be space efficient
  • Let form follow function
  • Iterate and optimize the design
  • Have the estimator and construction contractor on board

from the start

  • Make sustainability a front page priority
slide-31
SLIDE 31

Don’t Wait . . . Integrate Design = Better Results

Start Finish

slide-32
SLIDE 32

Thank You

TI Corporate Citizenship Report www.ti.com/ccr

Paul Westbrook

p-westbrook@ti.com