Installation of Additional Low Voltage Power at UXC55 Cameron Bravo Eve Emmanuelidu Monday, August 19, 13 Assembled and installed brackets to hold the additional junction boxes for ME4/2 chambers at X2 and X4 Monday, August 19, 13 Installed


slide-1
SLIDE 1

Installation of Additional Low Voltage Power at UXC55 Cameron Bravo Eve Emmanuelidu

Monday, August 19, 13

slide-2
SLIDE 2

Assembled and installed brackets to hold the additional junction boxes for ME4/2 chambers at X2 and X4

Monday, August 19, 13

slide-3
SLIDE 3

Installed rails and heat exchangers for the new MARATONs (PSUs) for ME1/1 and ME4/2 chambers Removed cable distributors that need to be modified for the addition of another MARATON

Monday, August 19, 13

slide-4
SLIDE 4

Removed 4 junction boxes from YE1+X2 Near side

Monday, August 19, 13

slide-5
SLIDE 5

Monday, August 19, 13

slide-6
SLIDE 6

Installed the junction boxes at X4+ Near and X2+ Far Sides