Inspectability of Piping at the Valdez Marine Terminal By Tom - - PowerPoint PPT Presentation
Inspectability of Piping at the Valdez Marine Terminal By Tom - - PowerPoint PPT Presentation
Inspectability of Piping at the Valdez Marine Terminal By Tom Kuckertz & Anna Carey TOEM Commi8ee DifficulttoInspect Pipes at VMT Corrosion on uninspectable pipes Regulatory requirements for InspecDon Alyeskas
Difficult‐to‐Inspect Pipes at VMT
- Corrosion on “uninspectable” pipes
- Regulatory requirements for InspecDon
- Alyeska’s “smart” pigging acDviDes
- Survey of state‐of‐the‐art pigging technologies
- PWSRCAC’s inspectability of the VMT project
- Alyeska’s in‐line‐inspecDon (ILI) project
- Concluding remarks
- QuesDons and answers
PWSRCAC September 2013 Board MeeDng
Efforts to Address Corrosion on “Uninspectable” Pipes
- “Uninspectable” aka “difficult‐to inspect”
– buried or insulated
- Dr. Rust (2012)
- Alyeska
– Berth 4 (2012 and extensive in 2013)
PWSRCAC September 2013 Board MeeDng
An example of corrosion at a girth weld
- n the riser pipes at Berth 4 (2012)
PWSRCAC September 2013 Board MeeDng
Repairs using welded sleeves are
- ccasionally necessary (2012)
PWSRCAC September 2013 Board MeeDng
In 2012 Alyeska embarked on a program to inspect over‐ water girth welds for Berths 4 and 5 (inspecIon in progress: August 2013)
PWSRCAC September 2013 Board MeeDng
Typical state of a girth weld as insulaDon was removed
PWSRCAC September 2013 Board MeeDng
Typical repair, cleaning, & recoaIng of girth weld
PWSRCAC September 2013 Board MeeDng
PWSRCAC became aware of differing requirements for inspecIon based upon regulatory cognizance
- DOT –PHMSA – Pipeline up to Tanks 1 and 3
– 1 year over water, 3 years over land or buried
- BLM & ADEC – Pipeline and VMT shared
– In accordance with Grant and Lease and Alaska AACs
- Other Regulators (State and Federal)
PWSRCAC September 2013 Board MeeDng
Ordinary instrumented “Smart” pigs are used for pipe inspecIon
- MagneDc flux used to measure wall thickness
– ResoluDon about 1 in2
- Propelled by fluid being transported
- Limited to use in straight, constant‐diameter
secDons of pipe or secDons with only large radii bends
- Typically not usable in buried and insulated
piping at the VMT
PWSRCAC September 2013 Board MeeDng
Every three years Alyeska runs a “smart” (instrumented) pig through the Pipeline
PWSRCAC September 2013 Board MeeDng
The end of the line for the “smart” pig is at the pig trap in Alyeska’s East Metering Facility
PWSRCAC September 2013 Board MeeDng
Scraper (“dumb”) pigs are run through the Pipeline every 10 days
PWSRCAC September 2013 Board MeeDng
Neither “smart” nor “dumb” pigs are run at the VMT beyond the East Metering pig trap
PWSRCAC September 2013 Board MeeDng
Development of Improved InspecDon Technologies
- MagneDc flux and/or ultrasound for wall
thickness measurements
– Precision less than 1 in2
- Agile –
– small radii bends OK – VariaDon in diameter OK (pass through smaller valves)
- Can propel itself with power umbilical
- Can exit at entry locaDon
- Applicable to VMT?
PWSRCAC September 2013 Board MeeDng
Many vendors claim the capability to inspect heretofore uninspectable pipes.
PWSRCAC September 2013 Board MeeDng
Newer pigs can inspect smaller diameter pipes
PWSRCAC September 2013 Board MeeDng
Pipes with a diameter of 1 foot or less can be inspected using some
- f the newer
pigs
PWSRCAC September 2013 Board MeeDng
The newer pigs are very
- agile. This pig
can navigate back to back small radii bends
PWSRCAC September 2013 Board MeeDng
Some inspecDon technologies are roboDc and work from the outside of the pipe
PWSRCAC September 2013 Board MeeDng
Some internal inspecDon technologies are roboDc and can propel themselves both forward and backwards
PWSRCAC September 2013 Board MeeDng
PWSRCAC’s Inspectability
- f Piping at the VMT Project
- Survey of newer inspecDon technologies with respect
to supporDng inspecDon needs of VMT
- Expert to compare new technologies with needs of
VMT
– RFP developed and ready for issuance – PotenDal vendors idenDfied
- Assess extent of Alyeska’s exploraDon of in‐line‐
inspecDon technologies
- Staff trained on modern pigging technologies
- Pending confirmaDon of Alyeska support
- Pending decision on expert vs. observaDon of Alyeska
in‐line‐inspecDon project
PWSRCAC September 2013 Board MeeDng
Alyeska’s In‐Line‐InspecDon (ILI) Project
- Early in development of concept
- TesDng of concept
– B‐Header at Ballast Water Treatment Facility
- Empty pipe – no fluid
- Tethered pig
– Powered by umbilical – Can exit at entrance locaDon (back‐out)
– Specifics unknown
- Can stakeholders observe?
PWSRCAC September 2013 Board MeeDng
The are some limitaDons on what pigs can do
PWSRCAC September 2013 Board MeeDng
QuesDons & Answers
PWSRCAC September 2013 Board MeeDng
End
PWSRCAC September 2013 Board MeeDng