initial operating results from the first initial
play

Initial Operating Results from the First Initial Operating Results - PowerPoint PPT Presentation

Electric Utility Environmental Conference Initial Operating Results from the First Initial Operating Results from the First TM Wet FGD 121 TM B&V Installations of CT- -121 Wet FGD B&V Installations of CT Technology in North America


  1. Electric Utility Environmental Conference Initial Operating Results from the First Initial Operating Results from the First TM Wet FGD 121 TM B&V Installations of CT- -121 Wet FGD B&V Installations of CT Technology in North America Technology in North America Dave Harris Vice President, AQCS Technology January 30, 2008

  2. Presentation objectives � Provide description of initial performance of the Killen Unit 2 CT-121 FGD system � Provide updates on recently started CT-121 FGD installations � PowerSouth (formerly Alabama Electric Cooperative) plant Lowman Units 1 and 2 � AEP Cardinal Unit 2 EUEC(8) - 2 01/30/08

  3. 01/30/08 DP&L Killen Station Unit 2 DP&L Killen Station Unit 2 EUEC(8) - 3

  4. DP&L Killen Electric Generation Station Unit 2 � Manchester, Ohio � 635 MW net (2.8 x 10 6 acfm) � Balanced draft � Hot-side ESP / SCR � Existing brick chimney flue (designed for 2 units) � Coal delivered by barge � Bottom ash and fly ash sluiced to ponds EUEC(8) - 4 01/30/08

  5. FGD design parameters � Limestone forced-oxidation FGD producing commercial gypsum (>95% gypsum, <10% H 2 O) � Single module of field-wound FRP (87 ft. – 6 in. diameter) � 97% SO 2 removal � Design coals: Design Typical high Parameter Permit coal high sulfur sulfur HHV, Btu / lb 11,080 11,080 11,649 SO 2 , lb / MBtu 7.22 6.32 2.82 Cl 2 , lb / MBtu 0.036 0.036 0.060 EUEC(8) - 5 01/30/08

  6. CT-121 Jet Bubbling Reactor (JBR) Outlet Plenum Gas Cooler To ME Inlet Plenum Absorber Gas Cooling Bleed Pumps Reaction Tank Pumps EUEC(8) - 6 01/30/08

  7. 01/30/08 Site arrangement EUEC(8) - 7

  8. Planned versus actual unit load during startup � Planned: � Gradually increasing unit generation to 100% over 7 days. Unit load as-dispatched thereafter � Compliant coal (400 ppmvd inlet SO 2 ) � Actual Conditions: � Forced outage at Stuart Station (600 MW) � Rapid increase to 100% over 36 hours � Compliant coal / Nymex coal blend (600 ppm) EUEC(8) - 8 01/30/08

  9. Planned versus actual unit load during startup 700 Actual 600 Load Unit Generation (MW) 500 400 300 200 Planned Load 100 36 Hr 0 5/30 6/1 6/3 6/5 6/7 EUEC(8) - 9 01/30/08

  10. Planned versus actual SO 2 during startup Planned: � Compliant coal ( 1.2 lb / MBtu) – startup + 3 days � Increasing higher inlet SO 2 – 7 days per step: � 100% Nymex coal ( 1.6 lb / MBtu) � 75% Nymex / 25% medium S ( 2.15 lb / MBtu) � 50% Nymex / 50% medium S ( 2.7 lb / MBtu) � 25% Nymex / 75% ,medium s ( 3.25 lb / MBtu) � 100% medium S ( 3.8 lb / MBtu) EUEC(8) - 10 01/30/08

  11. Planned versus actual SO 2 during startup Actual: � Rapidly decreasing blend of compliant coal and Nymex � 100% Nymex within 48 hours (600 ppmvd) � Parametric testing (400 and 600 ppmvd) EUEC(8) - 11 01/30/08

  12. Planned versus actual inlet SO 2 during startup 1,600 1,400 Planned 1,200 SO 2 (ppmvd) 1,000 800 Actual 600 400 200 0 5/28 6/4 6/11 6/18 6/25 7/2 7/9 7/16 7/23 7/30 EUEC(8) - 12 01/30/08

  13. 01/30/08 Performance Results Initial EUEC(8) - 13

  14. Slurry density control 25 Suspected density 20 meter calibration error. Density (wt%) 15 10 5 0 5/30 6/1 6/3 6/5 6/7 6/9 6/11 EUEC(8) - 14 01/30/08

  15. Initial FGD system performance – 1 st two weeks 100 99 SO 2 Removal Efficiency (%) 98 97 96 Guarantee 95 94 Reduced efficiency to 93 reduce gypsum production prior to 92 vacuum filter startup 91 90 5/30 6/1 6/3 6/5 6/7 6/9 6/11 6/13 6/15 EUEC(8) - 15 01/30/08

  16. Initial FGD system performance – parametric testing period June 19 to June 27 Reaction Tank Sparger pH Submergence, in. 5.0 base, ± 4 4.5 base, ± 2.5 4.0 base, ± 2.5, + 4 4.5 base, + 2.5 5.0 base + 2.5 5.0 → 3.8 base 4.3 base EUEC(8) - 16 01/30/08

  17. Initial FGD system performance – parametric testing period 100 99 98 97 SO 2 Removal (%) 96 Guarantee 95 94 93 92 Parametric testing program (SO 2 , pH, submergence) 91 90 5/28 6/4 6/11 6/18 6/25 7/2 7/9 7/16 7/23 7/30 EUEC(8) - 17 01/30/08

  18. Performance following parametric testing 100 99 98 Guarantee SO 2 Removal (%) 97 96 95 94 End of 93 Parametric Testing 92 91 90 7/23 7/30 8/6 8/13 8/20 8/27 9/3 9/10 EUEC(8) - 18 01/30/08

  19. Continuing CT-121 performance � Inlet SO 2 increasing to 1,000 – 1,500 ppmvd range � pH held at constant at ±4.0 to maximize reagent utilization � Sparger submergence held constant � SO 2 removal efficiency varies with inlet SO 2 (ranges 95 to 98%) � SO 2 removal efficiency is higher than predicted EUEC(8) - 19 01/30/08

  20. Killen observations CT-121 FGD system has demonstrated: � Stable chemistry under normal load variations � >97% SO 2 removal efficiency capability � Reaction tank slurry density control within ±1 wt% � pH control within ±0.2 unit � Produces commercial-grade gypsum EUEC(8) - 20 01/30/08

  21. 01/30/08 PowerSouth Lowman Units 1 and 2 PowerSouth Lowman Units 1 and 2 EUEC(8) - 21

  22. PowerSouth Lowman Units 1 and 2 � New FGD (CT-121) on Units 1 and 2 � Combined flow � New chimney � FGD Upgrade on Unit 3 � Utilizing existing Units 2 and 3 FGD � Limestone conversion � DCS controls conversion � SCR on Units 2 and 3 � No bypass � Doubled gypsum production � Environmental bottom line � 6,963 tons NO X removed � 14,102 tons SO 2 removed EUEC(8) - 22 01/30/08

  23. FGD design parameters � Limestone forced-oxidation FGD � Single FGD module serving Units 1 and 2 � Alloy 2205 tank with alloy 255 at the bubbling zone � 68’- 0” diameter � 98% SO 2 removal � Design coal: 2.5% sulfur bituminous EUEC(8) - 23 01/30/08

  24. FGD operation � Initial startup on November 27, 2007 with Unit 2 returning from outage � Full load operation of Unit 2 achieved before a scheduled turbine inspection � System tuning to be completed in late January; meanwhile SO 2 removal and scrubber operation support unit operations EUEC(8) - 24 01/30/08

  25. 01/30/08 AEP Cardinal Unit 2 AEP Cardinal Unit 2 EUEC(8) - 25

  26. AEP Cardinal Units 1, 2, and 3 � New FGD (CT-121) on Units 1, 2, and 3 � Nominal 600 MW units (each) � Common BOP facilities � Limestone / gypsum systems located near JBRs for Units 1 and 2 � Wastewater treatment � AEP performing balance draft conversion and DCS retrofits on Units 1 and 2 EUEC(8) - 26 01/30/08

  27. FGD design parameters � Limestone forced-oxidation FGD � Single FGD module per unit � Alloy 2205 tank with alloy 255 at the bubbling zone � 89’- 0” diameter (Unit 1 or Unit 2) � 95’-0” diameter (Unit 3) � 98% SO 2 removal � Design coal: 7.5 lb / MBtu SO 2 bituminous EUEC(8) - 27 01/30/08

  28. FGD status � Initial Unit 2 startup on December 15, 2007 with unit returning from outage � Tuning and testing of the Unit 2 FGD has not yet occurred � Unit 1 FGD essentially complete; awaiting tie-in outage opportunity � Unit 3 FGD construction continues EUEC(8) - 28 01/30/08

  29. 01/30/08 Discussion Discussion EUEC(8) - 29

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend