1
Information for Tenderers FIDIC
Time for Completion
- The Contractor shall commence work on the Contract on a date to
be specified in a written order by the Employer acting through the Engineer, and shall fully complete the work within the time for completion stated in the Form of Tender from and including the date thereof. The specified time for completion shall be considered to include public, official, religious and summer holidays.
- In order to assure the completion of the work within the time
stated in the Contract the Engineer reserves the right to order the Contractor to employ more men or equipment or to expedite the work in any way he may deem necessary.
- The specified date for the Contractor to commence work
shall be no later than Sixty (60) calendar days from the Engineer's order to commence work. In this respect allowance
- f one month was considered necessary for the Contractor to
arrange the supply of the pipes and fittings and of the rest of the materials for the purposes of the contract.
Time for Completion
- The Engineer shall give to the Contractor the order to
commence work not later than 15 days after the date of the execution of the Contract unless the Employer specifically sanctions an extension of such period to 30 days.
Substantial Completion of Parts of the Work
- As soon as, in the opinion of the Engineer, the
Works or self-contained parts of the works, which can be put into operation as agreed by the Engineer, have been substantially completed and have satisfactorily passed any final test that may be prescribed by the Contract, the Engineer shall, as specified in Section 48 of the General Conditions, on receiving a written undertaking by the Contractor to finish any outstanding work during the Period of Defects Liability, issue such Certificate of Completion in respect of the Works, and the Period
- f Defects Liability shall commence from the date
- f such Certificate of Completion.
Period of Defects Liability
- The Period of Defects Liability, as specified in Section
49 of the General Conditions, shall be for a period of 78 weeks from the date of the Certificate of Completion, as specified in Section 48 of the General Conditions.
Progress Claims
- The Contractor shall submit to the Engineer, at the
end of each calendar month, a fully itemized statement showing the estimated value of the permanent work executed up to the end of the
- month. This shall be based on items and prices