ICONE-22 July 7, 2014 Prague, Czech Republic Slide 1 SPEAKERS Dr. - - PowerPoint PPT Presentation

icone 22 july 7 2014 prague czech republic
SMART_READER_LITE
LIVE PREVIEW

ICONE-22 July 7, 2014 Prague, Czech Republic Slide 1 SPEAKERS Dr. - - PowerPoint PPT Presentation

Forthcoming Seismic PRA for US Operating Plants Following Fukushima Event ICONE-22 July 7, 2014 Prague, Czech Republic Slide 1 SPEAKERS Dr. Sanj Malushte smalusht@bechtel.com Dr. Annie Kammerer amkammer@bechtel.com Dr.


slide-1
SLIDE 1

Forthcoming Seismic PRA for US Operating Plants Following Fukushima Event

ICONE-22 July 7, 2014 Prague, Czech Republic

Slide 1

slide-2
SLIDE 2

SPEAKERS § Dr. Sanj Malushte smalusht@bechtel.com § Dr. Annie Kammerer amkammer@bechtel.com § Dr. Farhang Ostadan fostadan@bechtel.com

Slide 2

slide-3
SLIDE 3

Contents

  • 1. Introduction
  • 2. Near-Term Task Force (NTTF) Recommendations
  • 3. Recommendation 2.1: Seismic (R2.1)
  • 4. Additional R2.1-Related Activities
  • 5. Ground Motion Response Spectrum (GMRS) Development
  • 6. Validation of Existing Structural/SSI Models

10 Minute Break (10:50 - 11:00)

Slide 3

slide-4
SLIDE 4
  • 7. Seismic Fragility Evaluations
  • 8. Advanced Structural Analysis Approaches
  • 9. Plant Response Models
  • 10. Seismic Risk Calculations and Deaggregation
  • 11. Time Line and Current Status
  • 12. Questions (12:10 - 12:30)

Slide 4

Contents

slide-5
SLIDE 5

Fukushima Near Term Task Force (NTTF) Recommendations

Near-Term Task Force (NTTF) Recommendations

Slide 5

slide-6
SLIDE 6

NTTF Recommendations § In July 2011, NRC’s Near Term Task Force (NTTF) provided a report

(http://pbadupws.nrc.gov/docs/ML1118/ML111861807.pdf) containing 12

  • verarching recommendations addressing principles of defense-in-

depth, protection, mitigation and emergency preparedness (encl./SECY 11-0093)

§ SECY 11-0124 (http://pbadupws.nrc.gov/docs/ML1124/ML11245A127.pdf)

contains NRC’s assessment of the NTTF recommendations that can and, in NRC’s judgment, should be initiated, in part or in whole, without delay

§ SECY 11-0137 (http://pbadupws.nrc.gov/docs/ML1126/ML11269A204.pdf)

contains NRC’s prioritization of the NTTF recommendations, including: recommended regulatory actions, implementation challenges, technical and regulatory bases, additional recommendations, schedule and milestones

slide-7
SLIDE 7

Focus Areas of NTTF Recommendations

§ Regulatory framework (1 recommendation) § Defense-in-depth philosophy (total 10 recommendations) § Protection from natural phenomena (2 recommendations) § Mitigation for long-term station blackout (5 recommendations) § Emergency preparedness (3 recommendations) § NRC programs (1 recommendation) § Many of the 12 NTTF recommendations were further divided into

more detailed actions. In all, a total of 35 actions were identified

slide-8
SLIDE 8

Broad Description of NTTF Recommendations

§ Recommendation 1: Enhance NRC framework for regulating beyond

design basis (BDB) events and severe accidents

§ Recommendation 2: Update seismic and flooding analysis to protect

plants from BDB events*

§ Recommendation 3 (Long Term Evaluation Topic): Evaluate potential

enhancements to prevent or mitigate seismically induced fires and internal floods

§ Recommendation 4: Strengthen coping mechanisms for prolonged

station blackout (SBO) events

§ Recommendation 5: Require reliable hardened vent designs in BWRs

with Mark I and Mark II containments * Items marked in red are the focus of this presentation

slide-9
SLIDE 9

Broad Description of NTTF Recommendations

§ Recommendation 6: Identify insights about hydrogen control and

mitigation inside containment or in other buildings

§ Recommendation 7: Enhance spent fuel pool instrumentation and

makeup capability

§ Recommendation 8: Strengthen and integrate onsite emergency

response capabilities (EOPs, SAMGs, and EDMGs)

§ Recommendation 9: Require that facility emergency plans (EP)

address prolonged SBO and multi-unit events

slide-10
SLIDE 10

Broad Description of NTTF Recommendations

§ Recommendation 10: Additional EP topics related to multi-unit events

and prolonged SBO (Protective equipment for emergency responders, decisionmaker qualifications, command and control, and Emergency Response Data System (ERDs))

§ Recommendation 11: Additional emergency preparedness issues

(offsite emergency response, EP decisionmaking, radiation monitoring, public education on radiation safety and use of potassium iodide)

§ Recommendation 12: Strengthen regulatory oversight of licensee safety

performance (ROP) by focusing more attention on defense-in-depth requirements

slide-11
SLIDE 11

Prioritization of NTTF Recommendations

§ SECY 11-0137 provided detailed prioritization order for all NTTF

actions by organizing them into three tiers

§ Tier 1: Recommendations are those which the staff determined

should be started without unnecessary delay and for which sufficient resource flexibility, including availability of critical skill sets, exists

§ Tier 1 includes eight actions, the seven identified in SECY

11-0124 plus one additional item (7.1 SFP Instrumentation)

§ Tier 1 actions are: 2.1, 2.3, 4.1, 4.2, 5.1, 7.1, 8, and 9.3

slide-12
SLIDE 12

§ Tier 2: The second tier consists of those recommendations which

could not be initiated in the near term due to factors that include the need for further technical assessment and alignment, dependence on Tier 1 issues, or availability of critical skill sets

§ Tier 2 recommendations do not require long-term study and can

be initiated when sufficient technical information and applicable resources become available

§ Tier 2 Actions are: 7.2, 7.3, 7.4, 7.5, 9.3

Prioritization of NTTF Recommendations

slide-13
SLIDE 13

§ Tier 3: Recommendations that require further NRC study to

support a regulatory action, have an associated shorter-term action that needs to be completed to inform the longer-term action, are dependent on the availability of critical skill sets, or are dependent on the resolution of Recommendation 1

§ Once the staff has completed its evaluation of the resource

impacts of the Tier 1 and Tier 2 recommendations, it will be able to more accurately address the Tier 3 recommendations

§ Tier 3 Actions: 2.2, 3, 5.2, 6, 9.1, 9.2, 10, 11, 12.1, 12.2

Prioritization of NTTF Recommendations

slide-14
SLIDE 14

Fukushima Near Term Task Force (NTTF) Recommendations

Recommendation 2.1

u

NRC 50.54f Request for Information letter

u

Screening

u

Individual Plant Examination for External Events (IPEEE)

u

Phase 2 Risk-Informed Upgrade Decisions

u

EPRI and Industry Response

Slide 14

slide-15
SLIDE 15

NTTF Recommendations NTTF Recommendations

Slide 15

slide-16
SLIDE 16

R2.1: Seismic Hazard and Risk Reevaluation NRC 50.54(f) Request for Information Letter

§ In August 2010, the NRC issued a report on Generic Issue 199 (GI-199), which demonstrated that the ground motions calculated using current techniques exceeded the ground motions used in design for a significant number of US plants (the report also noted that plants are designed with significant seismic margin) [ Fukushima accident occurs ] § On August 23, 2011, the North Anna Power Station was shut down by beyond-design-basis ground motions from the Mineral VA earthquake § On December 23, 2011, the Consolidated Appropriations Act, Public Law 112-074, was Signed into law. Section 402 of the law also requires a reevaluation of licensees' design basis for external hazards, and expands the scope to include other external events.

Slide 16

slide-17
SLIDE 17

R2.1: Seismic Hazard and Risk Reevaluation NRC 50.54(f) Request for Information Letter

§ Issued March 12, 2012 § Addressed recommendations 2.1:seismic in Enclosure 1: seismic hazard and risk reevaluation § Requested specific deliverables and process

u Hazard evaluation information u Risk evaluation information (if necessary) u Spent fuel pool analysis

Slide 17

slide-18
SLIDE 18

R2.1: Seismic Hazard and Risk Reevaluation Seismic Guidance Development

Slide 18

EPRI 1025286 Seismic Walkdown Guidance EPRI 1025287 Screening, Prioritization and Implementation (SPID) NRC Seismic Margin Assessment Guidance JLC-ISG-2012-04

slide-19
SLIDE 19

R2.1: Seismic Hazard and Risk Reevaluation NRC 50.54(f) Request for Information Letter

§ Phase 1 includes hazard and risk reevaluation § Hazard evaluation information

u Hazard curves, ground motion response spectra (GMRS),

SSE used in design, and comparison of the GMRS and SSE

u GMRS is a probabilistically-based, risk-targeted ground

motion used in current plant design (see Regulatory Guide 1.208 and ASCE 43-05). Basis of the site-specific SSE.

u Any additional insights (such as from walkdowns) gained,

actions planned or taken, selected risk evaluation method (SMA or SPRA), as necessary

Slide 19

slide-20
SLIDE 20

R2.1: Seismic Hazard and Risk Reevaluation NRC 50.54(f) Request for Information Letter

§ Any additional insights (such as from walkdowns) gained, actions planned or taken, selected risk evaluation method (SMA or SPRA), as necessary

Slide 20

Expedited Seismic Evaluation Process

  • Short term actions to demonstrate ability of plants to

address seismic hazard while longer-term actions are

  • ngoing
  • EPRI 1025286 Report provides guidance
slide-21
SLIDE 21

Screening Approach R2.1: Seismic Hazard and Risk Reevaluation

Slide 21

EPRI SPID 1025287 Figure 1.1

slide-22
SLIDE 22

R2.1: Seismic Hazard and Risk Reevaluation Screening Approach

Slide 22

Seismic hazard analysis performed, GMRS developed and compared with SSE No exceedance Only low frequency exceedance in low hazard area

  • Analyze low-

frequency sensitive components Exceedance in 1 to 10 Hz range

  • SPRA with some

exceptions High frequency exceedance (with or without 1 to 10 Hz exceedance)

  • Addressed through

EPRI testing program

Exceptions include: GMRS<1.3 x SSE at all points (SMA allowed) Very narrow band frequency exceedance Spectrum from demonstrated IPEEE HCLPF >GMRS and adequate quality demonstrated

slide-23
SLIDE 23

Screening exceptions

Slide 23

Only low frequency exceedance Only high frequency exceedance From EPRI 1025287 (SPID)

slide-24
SLIDE 24

Screening exceptions

Slide 24

Narrow band exceedance 1-10Hz

From EPRI 1025287 (SPID)

slide-25
SLIDE 25

R2.1: Seismic Hazard and Risk Reevaluation Individual Plant Examination for External Events

§ 50.54(f) program in late 90s to evaluate beyond design basis earthquake (DBE) loads in response to maturing of the PRA methodologies and increased awareness of potential for beyond DBE

  • loads. (Generic Letter 88-20, Supplement no. 4, 1991).

§ Procedures detailed in NUREG-1407 (1991). Results and insights detailed in NUREG-1742 (2002) § Approach was generally qualitative with emphasis on developing risk

  • insights. About 1/3 of plants performed SPRA and 2/3 performed SMA.

A generic Review Level Earthquake ground motion spectrum was used § The NRC allows for R2.1 screening based on demonstrated IPEEE plant HCLPF values and a demonstration by licensees that analyses are still valid and are sufficient to meet the objectives of the March 2012 50.54(f) letter. (See the EPRI SPID for details)

Slide 25

slide-26
SLIDE 26

R2.1: Seismic Hazard and Risk Reevaluation Individual Plant Examination for External Events

§ Three levels of review based on plant setting: full scope, focused scope and reduced scope. For R2.1 screening, focused scope submittals needs to be augmented with site geotechnical hazard study. Reduced scope studies cannot be used for screening § Key elements of NRC review are:

u Prerequisites: Commitments made were met (as detailed in R2.3 Seismic

Walkdown report), modifications or changes credited in IPEEE analysis are in place, deficincies or weaknesses in plant SER were properly justified to assure conclusions remain valid, and a review major plant modifications to identify potential for new issues

u R2.1 submittals showing adequacy: structural models, ISRS scaling,

seismic equipment list, component screening, walkdowns, fragility evaluations, systems model and containment performance analysis

Slide 26

slide-27
SLIDE 27

IPEEE comparison

Slide 27

From EPRI 1025287 (SPID)

slide-28
SLIDE 28

HCLPF Description High confidence of low probability of failure

This is intended to be a value of ground motion at which the potential of failure is exceedingly small High confidence – typically the 95% confidence band Low probability – typically the 1% or 5% value (depending on usage) Failure is the inability to perform the intended safety function

Slide 28

95%

confidence

Peak Ground Acceleration (g) Probability of Failure

slide-29
SLIDE 29

R2.1: Seismic Hazard and Risk Reevaluation NRC 50.54(f) Request for Information Letter

§ Risk evaluation information requested (for SPRA)

u List of risk-significant contributors u Summary of methodologies used to estimate SCDF or LERF

  • Fragilities (methods, parameters, values, and dominant failures modes)
  • Findings from walkdowns and list of corrective actions
  • Process used for model development
  • Assumptions about containment

u Description of process used to ensure technical adequacy,

including information on peer reviews

u Identified vulnerabilities and actions planned or taken

Slide 29

slide-30
SLIDE 30

Phase 2 Actions and Activities R2.1: Seismic Hazard and Risk Reevaluation

Slide 30

EPRI SPID 1025287 Figure 1.1

§ Phase 2 actions/activities will be determined by the NRC based on the risk analysis results provided by the licensees

slide-31
SLIDE 31

R2.1: Seismic Hazard and Risk Reevaluation Role of the Electric Power Research Institute (EPRI)

§ Co-sponsored studies to develop new seismic source characterization and ground motion characterization models with NRC, DOE, and USGS § Developed key guidance documents for walkdowns and hazard/risk reevaluation with NRC and NEI staff § Developed of new interim ground motion prediction equations (attenuation relationships) § Developed and implemented high-frequency testing program to address issues of (GMRS to SSE) exceedances >10Hz § Developed concept, guidance and technical basis for the Expedited Seismic Evaluation Process § Managed industry-wide seismic hazard reevaluation activities

Slide 31

slide-32
SLIDE 32

Current and Upcoming Efforts

Additional R2.1 Related Activities

u

FLEX/ESEP Work

u

High Frequency Issues

u

Spent Fuel Pool Evaluations

Slide 32

slide-33
SLIDE 33

What is ESEP? § “Expedited Seismic Evaluation Process (ESEP)” augments 2.1: Seismic implementation

§ ESEP identifies the“Expedited Seismic Equipment List (ESEL)”, and determins the need for seismic evaluation and upgrade (if any) of the ESEL equipment prior to the full implementation of R2.1. § ESEL includes permanent plant equipment connected with the FLEX equipment to help deliver extended core cooling capability after a beyond-design-basis event § By focusing on seismic margin of permanent plant equipment necessary to cope with loss of AC Power and/or loss of UHS, ESEP increases confidence in coping capability, and thus helps address public/NRC safety concerns while risk reevaluation is underway § EPRI Report 3002000704 (2013)

Slide 33

slide-34
SLIDE 34

Typical ESEL Items for ESEP Work

Slide 34

slide-35
SLIDE 35

Typical ESEL Items for ESEP Work

Slide 35

slide-36
SLIDE 36

ESEP Activities Flowchart

Slide 36

slide-37
SLIDE 37

Seismic High Frequency Issue

§ SMA and SPRA activities for R2.1 focus on 1-10 Hz range § For rock NPP sites located in the CEUS, the peak of site-specific ground motion is typically in the 20-40 Hz range § Component proof testing is being implemented to verify adequacy of potentially HF-sensitive bi-state devices such as relays, contactors, switches, potentiometers and similar devices whose output signal or settings could be changed due to HF motion § A two-phase test program has been conducted to determine the seismic fragility spectra for hundreds of bi-state devices § Phase 1 of the test program developed the test protocol to be used for Phase 2 to determine the high-frequency vulnerability of a broad set of control devices used in NPPs - 11 sample devices were tested in Phase 1, and 154 more were tested in Phase 2 § EPRI Report 3002000706 provides more information

Slide 37

slide-38
SLIDE 38

Phase 1 High Frequency Test Program § A variety of high-frequency input motions were applied to determine the most appropriate for the Phase 2 effort (because high-frequency seismic behavior of contact type devices had not been studied before)

Ø Sine sweep motions over the range 16-64 Hz Ø Random multi-frequency (wide band) motions Ø Filtered random multi-frequency (narrow band) motions

§ Filtered multi-frequency narrow-band inputs resulted in fragility

values that were 2-3 times the fragilities obtained using the wide- band multi-frequency inputs. This suggests that the clipping factors used for low frequency fragility are valid for high-frequency fragility.

Slide 38

slide-39
SLIDE 39

Phase 1 Input Motions

Slide 39

Wide Band Random Multi-Frequency Filtered Random Multi-Frequency Normalized Spectra for Sine Beat and Pure Sine

slide-40
SLIDE 40

Phase 2 High Frequency Test Program

Slide 40

The following groups of devices were tested in Phase 2 (in all 154 items):

  • 1. Control relays
  • 2. Protective relays
  • 3. Contactors and motor starters
  • 4. Molded case circuit breakers
  • 5. Control switches
  • 6. Process switches
  • 7. Transmitters
  • 8. Low voltage and medium voltage circuit breakers
  • 9. Others –panel mounted potentiometer, proximity switch
slide-41
SLIDE 41

Phase 2 High Frequency Test Program § Control Switches and Transmitters were tested to table limits (20g, 14g) without chatter or output discontinuity - conclude that these devices are not high frequency sensitive § Energized control relays were tested to table limits (20g) without chatter – conclude that energized control relays are not high frequency sensitive § The remaining components types and de-energized control relays can have chatter or functional fragility limits at varying lower levels but all appear to have capacity greater than that obtained for low frequency testing (still being verified by EPRI) – conclude that there is no unique high frequency sensitivity and that, device capacity is manufacturer and model specific

Slide 41

slide-42
SLIDE 42

Spent Fuel Pool (SFP) Evaluations

§ Not necessary to perform structural integrity evaluation provided that the checklist in NUREG-1738 is followed to show that SFP has a high seismic HCLPF value § Necessary to evaluate failures that could lead to uncovering of fuel: Ø Failure of a connection penetrating the SFP structure below the top of stored fuel (e.g., drain line, cooling water line, etc) Ø Failure of a connection penetrating the SFP structure above the fuel such that significant inventory can be drained off in the absence of makeup due to evaporation and boil-off Ø Extensive sloshing causing loss of significant inventory and fuel uncovering Ø Potential for siphoning inventory due to seismic failure of cooling system discharge line (or its connections) Ø Tearing of steel liner due to seismic movement of fuel assemblies Ø Failures that could lead to draining if in refueling configuration

Slide 42

slide-43
SLIDE 43

GMRS Development

GMRS Development

u

Probabilistic Seismic Hazard Analysis (PSHA)

u

New CEUS Models

u

GMRS Development

Slide 43

slide-44
SLIDE 44

Slide 44

Probabilistic Seismic Hazard Assessment

Seismic Source Characterization: SSC Model Ground Motion Characterization: GMC Model Base figure from Reiter (1990) Earthquake Recurrence Source Geometry

slide-45
SLIDE 45

§ PSHA approaches detailed in NRC Regulatory

Guide 1.208 and in NUREG/CR-6372 (1989) and NUREG 2117. The NUREGs for the SSHAC guidelines)

§ A new SSHAC level 3 seismic source model for

the CEUS was published jointly by the NRC (NUREG 2115), EPRI and DOE in January 2012.

§ Coupled with existing ground motion

characterization models (the most recent was published by EPRI in 2012), this formed the basis

  • f hazard reanalysis for plants in the CEUS.

§ Western plants are performing site-specific

SSHAC Level 3 studies. Western plants have additional time to develop and submit their GMRS.

Slide 45

Probabilistic Seismic Hazard Assessment

PUBLISHED January 2012

slide-46
SLIDE 46

Slide 46

Uncertainty Definitions

Uncertainty

Aleatory

Integration over distribution of expected parameter values

Epistemic

logic tree of technically defensible interpretations

slide-47
SLIDE 47

Slide 47

Uncertainty Definitions

Uncertainty

Aleatory Epistemic

Acceleration (g) Annual Prob of Exceedance

Aleatory variability principally gives the curve its shape. Epistemic uncertainty leads to uncertainty bands

85% Median 15%

slide-48
SLIDE 48

§ Development of best estimate

dynamic soil properties is based on available data

§ Both epistemic and aleatory

uncertainties must be recognized

§ 60 randomized profiles are used to

capture uncertainties

§ Soil property, layer thickness and

depth to base rock variation must be considered

§ Advantage of co-located plant sites § Given the rock input motion, soil

amplification analysis is the most important step in GMRS calculation

Slide 48

GMRS – Soil Amplification

slide-49
SLIDE 49

§ RCTS (Resonant Column Torsional

Shear) is most commonly used in US

§ Limited test data are obtained and

  • ften merged with standard

nonlinear soil curves

§ Variation of soil nonlinear curves

may be obtained from published data

  • r soil nonlinear models using the

range of index soil properties

§ Nonlinear soil property and its

variation must be simulated

§ Use of kappa in included for deep

layers

Slide 49

GMRS – Nonlinear Soil Models

slide-50
SLIDE 50

§ Hard rock input motion are de-

aggregated to HF and LF spectra

§ RVT method is commonly used

to get spectral amplification avoiding time history

§ Four Soil amplification methods

(NUREG/CR 6728); mostly methods 2 and 3 are used

§ The choice between method 2

and 3 is a function of variability in the amplification functions

§ GMRS is obtained from UHS

applying the design factors

Slide 50

1.0E-03 1.0E-02 1.0E-01 1.0E+00 1.0E+01 1.0E+02 0.1 1 10 100 5% Damping Spectral Acceleration Frequency [Hz] Input Rock HF 1E-3 LF 1E-3 HF 1E-4 LF 1E-4 HF 1E-5 LF 1E-5 HF 1E-6 LF 1E-6 HF 1E-7 LF 1E-7 HF 1E-8 LF 1E-8 0.0 0.5 1.0 1.5 2.0 2.5 3.0 3.5 4.0 4.5 0.1 1 10 100 AR S Amplificat ion Frequency [Hz] BBM Low PI - Ground Surface HF 1E-3 LF 1E-3 HF 1E-4 LF 1E-4 HF 1E-5 LF 1E-5 HF 1E-6 LF 1E-6 HF 1E-7 LF 1E-7 HF 1E-8 LF 1E-8

GMRS – Soil Amplification Analyses

slide-51
SLIDE 51

§ SSEs for operating plants were typically based on standard shape spectra scaled to selected PGAs § GMRS is a performance based design spectra that includes site specific amplification effects § The frequency content between SSE and GMRS ground motions are quite different § Nearly 70% of the plants screened into further evaluation

Slide 51

Typical Soil Site GMRS/SSE Comparison

slide-52
SLIDE 52

Validation of Existing Structural/SSI Models

Validation of Existing Structural/SSI Models

Slide 52

slide-53
SLIDE 53

As per SPID Section 6.3, most existing models are stick models and can be used if they meet the following criteria:

§ Represent overall building response in H and V directions § Significant coupling between H and V must be captured § Total mass and center of mass must be preserved § Models must capture structural frequencies up to 20 Hz to

ensure ISRS is adequate up to 10 Hz

§ Torsional eccentricity must be included

Slide 53

Validation of Existing Structural/SSI Models

slide-54
SLIDE 54

Validation of Existing Structural/SSI Models

§ Most existing plants used Lumped-Mass-Stick-Models (LMSMs)

for their design basis seismic analysis

§ Also, some designs were based on fixed base analysis (i.e., no

SSI) , or simple SSI analysis using equivalent soil springs and dashpots

§ Task 2.1: Seismic requires validation of existing SSI and

structural modeling approaches for ensuring development of accurate ISRS up to 10 Hz frequency

§ SPID Section 6.3 provides guidelines for verifying the accuracy of

existing structural/SSI models

§ Fixed base analysis is considered appropriate if the structure is

supported on layers with shear wave velocity in excess of 5,000 ft/sec (about 1,500 m/s)

Slide 54

slide-55
SLIDE 55

Break

10 Minute Break (10:50 - 11:00)

Slide 55

slide-56
SLIDE 56

SPRA and Fragility

Fragility Methods for Components

u

Overview of SPRA

u

Fragility methods for systems and components

u

Fragility screening

Slide 56

slide-57
SLIDE 57

Overview of Seismic PRA

Slide 57

SPRA

Seismic Load Capacity

Seismic Motion Parameter Conditional Prob. of Failure

i

Systems Analysis

Event trees, Fault trees, Containment Analysis

Seismic Motion Parameter Frequency of Exceedance

Pi

slide-58
SLIDE 58

Fragility Development Approaches

§ Objective of a Seismic Fragility Evaluation is estimation of the

conditional probability of failure of important structures and equipment whose failure may lead to unacceptable damage to the plant (e.g., core damage).

§ Failure is defined as the inability to perform intended safety

function.

§ Plant walkdown is an important activity in conducting the

  • evaluation. Actual conditions and failure modes need to be

assessed.

§ Two Key methods are currently used

Ø Conservative-Deterministic-Failure-Margin (CDFM) Hybrid method Ø Separation of variables

Slide 58

slide-59
SLIDE 59

Separation of variables method

§ Am is the median capacity § βR is the random variability § Βu is the modeling uncertainty

Slide 59

Fragility Development

EPRI 1002988 (2002), 1019200 (2009)

slide-60
SLIDE 60

Separation of variables method

Slide 60

Fragility Development

C

Mean Curve Development

slide-61
SLIDE 61

CDFM Hybrid method

§ Can be used for first pass through SPRA. Components that are found to be

potentially important to risk must be analyzed using the separation of variables method

§ CDFM method determines HCLPF, which is combined with an assumed β

(fragility logarithmic standard deviation) to develop the fragility curve

§ β ranges from 0.3 to 0.6

Slide 61

Fragility Development

EPRI NP-6041-SL, Rev. 1 (1991)

slide-62
SLIDE 62

Fragility Screening Approaches

Slide 62

From NRC ISG SMA Guidance JLC-ISG-2012-04 and EPRI SPID

slide-63
SLIDE 63

Fragility Screening Approaches

§ The R2.1 reevaluations focus on both core damage frequency

(CDF) and large early release frequency (LERF), therefore both are considered in the component screening analysis

§ The components identified as “high capacity” SSCs should be

assigned capacities equal to the screening level and retained in the system model (can use tables in EPRI NP-6041- SL Rev.1, other recent refs.)

§ As discussed in the EPRI SPID, The screening level may be set as

either:

§ A screening level consistent with a HCLPF capacity that is 2.5 times the review level ground motion, or § A screening level equivalent to the HCLPF that leads to a frequency of failure

  • n the order of 5x10-7/yr using a mean point estimate.

Slide 63

slide-64
SLIDE 64

Fragility Screening Approaches

§ Once the SPRA/SMA analysis has been performed, a check must

be conducted to assure that none of the following conditions exist:

Ø A “high seismic capacity” SSC (which has been assigned a conservative HCLPF equal to the screening level) is identified as a dominant contributor to HCLPF of core damage Ø A “high seismic capacity” SSC is identified as a dominant contributor to HCLPF of large early release

§ Setting the screening level well above the review ground motion

level, and the requirement to review the results, are intended to avoid the “surrogate element” issue that arose in IPEEE

Slide 64

slide-65
SLIDE 65

Structural Analysis

Advanced Structural Analysis Models

Slide 65

slide-66
SLIDE 66

SSI with RVT

§ Seismic demand must be

  • btained from SSI analysis to

develop the fragility curves

§ Now for SSI analysis, time

history can be avoid and RVT can be used to get all responses

§ This is most ideal for both

deterministic and probabilistic SSI analysis

§ Most ideal for scenario EQs

Slide 66

Advanced Structural Analysis Approaches

slide-67
SLIDE 67

Incoherency Effects

§ The hard rock incoherency approach is

approved by US NRC (see NRC Interim Staff Guidance COL-DC-ISG-1 ML081400293)

§ The implementation of the model in the SSI

computer programs have also been approved

§ The new ASCE 4-2014 has long section on

use of incoherency

§ The model is most effective for stiff and rock

sites with large mat foundation

§ Per NUREG-0800 the reduction in ISRS in high

frequency is capped at 30% unless it can be justified

Slide 67

Advanced Structural Analysis Approaches

slide-68
SLIDE 68

Soil-Structure Interface Modeling for Extreme Loading

§ The structure may slide under

extreme loading with small amount

  • f slippage

§ The slippage reduces the seismic

load and drift significantly

§ The slippage is likely to occur well

before the structure reaches nonlinear state

§ This is an area that could be

beneficial under appropriate conditions and needs to be pursued and developed more pro-actively

Slide 68

Advanced Structural Analysis Approaches

slide-69
SLIDE 69

SPRA and Systems Modeling

Systems and Plant Response Modeling

Slide 69

slide-70
SLIDE 70

Systems modeling and Accident Sequence Identification

§ To develop a Seismic PRA models, one begins with an

internal events systems model and adds enhancements:

Ø Additional earthquake-induced initiating events Ø Updated SSC fragilities that account for both seismic fragility and random failures Ø Increased likelihood of correlated and increased dependencies between components Ø Loss of offsite power is assume for all accident sequences

§ Event trees address system success or failure and fault

trees feed individual components into systems analysis

Slide 70

slide-71
SLIDE 71

Systems Modeling and Accident Sequence Identification

Slide 71

success failure

slide-72
SLIDE 72

SPRA Components

Slide 72

Event tree System fault trees Hazard input Initiating event development for external events Fragility Accident Sequences

slide-73
SLIDE 73

Additional Important Considerations

§ Containment response

§ Seismic-induced failures are different from those assumed in internal PRA and must be assessed separately § Sequences must be binned by plant damage state § The containment event tree should be reviewed for consistency with seismic core damage sequence types

§ Site Hazard Evaluations

§ Increasingly considered in the input to the SPRA § Can be implemented as the initiating event analysis is conducted

§ Human Factors

Slide 73

slide-74
SLIDE 74

SPRA

Seismic Risk Calculation and Deaggregation of Results

Slide 74

slide-75
SLIDE 75

Seismic Risk Evaluation and Deaggregation of Results

§ Using the Boolean-algebra based systems model supported by

fault trees and assigned fragilities, and the hazard curve as input, the risk is evaluated by analyzing each of the accident sequences and summing the results.

§ The results can be deaggregated and reviewed such that the

contributions (importance) of individual or grouped accident sequences and individual components are assessed.

§ Sequences are calculated directly § Components are assessed through Fussell-Vesely Importance,

Risk Reduction Ratio, and Risk Increase Ratio, and Uncertainty Importance.

Slide 75

slide-76
SLIDE 76

Seismic Risk Evaluation and Deaggregation of Results

§ Outcomes can be used and reviewed in several ways

Ø Overall plant risk is calculated as CDF and LERF, which can be compared with overall risk tolerances. Ø Key risk contributors (SSCs) can be identified. This allows for an understanding of where risk comes from and how risk can be reduced most effectively. Ø A review can be made to assure that no single SSC dominates

  • risk. Supports the “redundancy” requirement of defense-in-

depth.

Slide 76

slide-77
SLIDE 77

Time Line and Summary

Time Line and Current Status

Slide 77

slide-78
SLIDE 78

R2.1: Seismic Timeline

Slide 78

http://pbadupws.nrc.gov/docs/ML1308/ML13085A008.pdf

slide-79
SLIDE 79

Current Status

§ All CEUS operating plants submitted a GMRS report in March 2014 § Based on the GMRS results, 18 sites screened out for further evaluation, the rest

are screened in or considered as conditional in subject to further evolution

§ The sites that are screened in or are conditionally screened in are divided into 3

risk evaluation prioritization groups (1 to 3)

§ All plants that screen in must submit a plan for expedited approach by 12/31/2014 § Deadline for seismic risk evaluation for CEUS plants:

  • Group 1

June 30, 2017

  • Group 2

December, 2019

  • Group 3

December 2020

§ NRC issued their draft version of GMRS for each site in early May 2014, currently

utilities are reconciling the differences among the two sets of GMRS

§ The schedule for 3 WUS plant sites is 1-2 years behind the CEUS sites

Slide 79

slide-80
SLIDE 80

Question and Answer

Questions?

Slide 80