I-635 LBJ East Project – Industry Workshop June 15, 2018
I-635 LBJ EAST PROJECT
Industry Workshop June 15, 2018
I-635 LBJ EAST PROJECT Industry Workshop June 15, 2018 June 15, - - PowerPoint PPT Presentation
I-635 LBJ EAST PROJECT Industry Workshop June 15, 2018 June 15, 2018 I-635 LBJ East Project Industry Workshop I-635 LBJ East Project Duane M uane Mil illigan, P igan, P.E .E. Dire Di rector o of f Co Constr truction TxDO xDOT
I-635 LBJ East Project – Industry Workshop June 15, 2018
Industry Workshop June 15, 2018
I-635 LBJ East Project – Industry Workshop June 15, 2018
1
I-635 LBJ East Project – Industry Workshop June 15, 2018
2
I-635 LBJ East Project – Industry Workshop June 15, 2018
3
Project Location Purpose and Need Proposed Project Work Complete/Underway Project Challenges QS Evaluation Delivering QS Submittals 4 5 6-10 10 11 11-12 12 13 13 14 14-17 17 19 19 Responsibilities 20 20 TxDOT Civil Rights Division - DBE Outreach 21 21-25 25 Questions 26 26 Procurement Timeline 18 18
I-635 LBJ East Project – Industry Workshop June 15, 2018
4
I-635 LBJ East Project – Industry Workshop June 15, 2018
5
I-635 LBJ East Project – Industry Workshop June 15, 2018
DART Railroad (Orange/Red Line)
DART (Blue line)
– 3.2 miles – Full reconstruction of the existing eight general purpose lanes to ten general purpose lanes, with auxiliary lane(s) between entrance and exit ramps – Full reconstruction of the existing one concurrent tolled managed lane – Full reconstruction of the discontinuous frontage roads and addition of new frontage roads Skillman/Audelia Interchange
6
I-635 LBJ East Project – Industry Workshop June 15, 2018
7
I-635 LBJ East Project – Industry Workshop June 15, 2018
– KCS Railroad Reconstruction of existing LBJ Overpass Reconstruction of Jupiter Rd. & Kingsley Rd existing at-grade crossings
– 2.6 miles – Full reconstruction of the existing 8 general purpose lanes to 10 general purpose lanes, with auxiliary lanes at entrance and exit ramps – Full reconstruction of the existing 1 concurrent Tolled Managed lane – Full reconstruction of the discontinuous frontage roads and addition of new frontage roads
8
I-635 LBJ East Project – Industry Workshop June 15, 2018
– I-30/I-635 Interchange Reconstruction
I-635 south of the interchange
from west of Gus Thomasson Road to east of N Galloway Avenue
74-02-053:
West o
H 78 ( 78 (Gar arland Road) t to I I-30
– 5.2 miles – Full reconstruction of the existing 8 general purpose lanes to 10 general purpose lanes, with auxiliary lanes at entrance and exit ramps – Full reconstruction of the existing 1 concurrent Tolled Managed lane – Full reconstruction of the discontinuous frontage roads and addition of new frontage roads – KCS Railroad
Overpass
road underpasses
9
I-635 LBJ East Project – Industry Workshop June 15, 2018
10
EXISTING TYPICAL SECTION PROPOSED DESIGN-BUILD
TYPICAL SECTION
Note: Additional capacity shown in purple.
I-635 LBJ East Project – Industry Workshop June 15, 2018
Schemat atic – IH 635 LBJ East Schematic was approved on July 21, 2017 – Skillman/Audelia Interchange Schematic was approved on May 1, 2014 – IH 635 LBJ East Schematic is currently being evaluated to remove the depressed ML design
al Clear aran ance – IH 635 LBJ East Original FONSI was issued on January 30, 2003. A subsequent Environmental Assessment Re- evaluation for the revised schematic was completed and approved on April 24, 2017. – The Categorical Exclusion of the Skillman/Audelia Interchange was separately approved on June 23, 2015.
Acquisition – ROW acquisition for the project is ongoing. Any parcels not acquired by execution of the DB contract will become the responsibility of the DB contractor.
E – up to Level B is complete. Level A at selective locations
lity R Reloc locat ation – Coordination for the project‘s transmission line relocation is currently underway. It is anticipated that all transmission lines would be relocated before construction commences.
lroad ad C Coor
ation – Coordination is underway. Anticipate to obtain a Preliminary Railroad Crossing License and Construction License Agreements based on approved Schematic’s design with both DART and KCS by execution of DB Contract.
11
I-635 LBJ East Project – Industry Workshop June 15, 2018
se W Walls s Const stru ruction
(CSJ 2 2374-01 01-180 180 & & 2374-02 02-14 144) – Vari riou
s location
s from East st o
rams R s Road to I-30 – Let in N November 2 r 2017 – Ant nticipated completion i n in n Ma May 2 y 2019
12
I-635 LBJ East Project – Industry Workshop June 15, 2018
13
I-635 LBJ East Project – Industry Workshop June 15, 2018
14
I-635 LBJ East Project – Industry Workshop June 15, 2018
15
I-635 LBJ East Project – Industry Workshop June 15, 2018
16
I-635 LBJ East Project – Industry Workshop June 15, 2018
17
I-635 LBJ East Project – Industry Workshop June 15, 2018
18
I-635 LBJ East Project – Industry Workshop June 15, 2018
19
I-635 LBJ East Project – Industry Workshop June 15, 2018
20
I-635 LBJ East Project – Industry Workshop June 15, 2018
21
I-635 LBJ East Project – Industry Workshop June 15, 2018
22
I-635 LBJ East Project – Industry Workshop June 15, 2018
23
I-635 LBJ East Project – Industry Workshop June 15, 2018
Ti Title 49: 49: T Tran ansportation Part 2 26: P Particip ipatio ion By Dis Disadv dvantaged d Business Enterpris ises in in De Department of
Tran ansportat ation F Finan ancial al Assistan ance P Program ams 49 C 49 CFR P Par art 26 26 Obje jectiv ives
24
I-635 LBJ East Project – Industry Workshop June 15, 2018
25
I-635 LBJ East Project – Industry Workshop June 15, 2018
26