I-440 Reconstruction From I-40 to I-24 What is Design Build? A - - PowerPoint PPT Presentation
I-440 Reconstruction From I-40 to I-24 What is Design Build? A - - PowerPoint PPT Presentation
I-440 Reconstruction From I-40 to I-24 What is Design Build? A project delivery method that combines all or some portions of the design and construction phases of a project into a single contract. TDOT clearly defines the
What is Design Build?
- A project delivery method that
combines all or some portions of the design and construction phases of a project into a single contract.
- TDOT clearly defines the
standards, scope, and specifications for a project, and the Design-Builder works to satisfy those requirements.
2
20 October 2017
Why Design-Build?
- Shortened completion time by
- verlapping design and
construction
- Construction can begin before
all design details are final.
- Reduced claims due to design
errors/ omissions because construction happens under same contract.
- Shortened project delivery
time which can reduce user costs.
- Single contact point for
quality, cost and schedule from design through construction.
3
I-440 Project Overview - Location Map
4
Begin Project End Project
I-440 Project Overview
- Constructed in the early 80s
- 7.8 miles+/-
- I-440 serves as an urban interstate
facility linking I-40 in the west to I- 24/I-40 in the east. This facility also serves as a connection to I-65, which connects to Nashville to the north and to Brentwood/Franklin/Huntsville to the south.
- The existing concrete pavement on
I-440 is in substandard condition.
- The crash rates on I-440 are
approximately 1.8 times higher than the statewide average for urban interstate facilities.
5
I-440 ADT
6
- Highest between Hillsboro
Road & I‐65
- 115,740 (2021)
- 138,400 (2041)
- 7% Trucks
- Lowest between Murphy
Road and West End
- 85,890 (2021)
- 104,360 (2041)
- 2021 – 102,968
(Along the corridor)
- 2041 – 123,688
(Along the corridor)
- 2016 – 94,801
(Along the corridor)
AADT
Existing Typical Section
7
- Travel Lanes (TL)
- 2 Lanes in each direction
- 8‐foot inside shoulders with 2‐foot curb
- 13‐foot grass median
- Total Median Width – 46 feet (TL to TL)
- 12‐foot outside shoulders
I-440 Proposed Improvements
8
- Widening to the inside to provide a minimum of
six (6) travel lanes (3 in each direction) throughout the corridor
- Widening ends west of Nolensville Road
- 12‐foot Travel Way
- 11‐foot +/‐ shoulder
- Removing and replacing the existing
pavement
- Eastbound Reconstruction ends west of
Nolensville Road
Other Improvements
- Other Improvements
– New Noise walls – Repair/Replace Noise walls – Signing – ITS – Rockfall Mitigation
- PROP. 51” MEDIAN BARRIER
BEGIN I‐440 WIDENING
Charlotte Ave.
I-440 Slide 1
10
NEW PAVEMENT REPLACE NEW SHOULDER REPLACE MEDIAN PAVING WIDENING RAMP REPAIR/REPLACE LEGENDS
- PROP. 51” MEDIAN BARRIER
- PROP. NOISE BARRIER
I-440 Slide 2
11
NEW PAVEMENT REPLACE NEW SHOULDER REPLACE MEDIAN PAVING WIDENING RAMP REPAIR/REPLACE LEGENDS
I-440 Slide 2
12
STA 1081+60 STA 1086+60 Barrier near ROW Barrier near ROW
- PROP. 51” MEDIAN BARRIER
- PROP. NOISE BARRIER
I-440 Slide 3
13
NEW PAVEMENT REPLACE NEW SHOULDER REPLACE MEDIAN PAVING WIDENING RAMP REPAIR/REPLACE LEGENDS
I-440 Slide 3
14
STA 1105+07 STA 1110+40 Existing Barrier Barrier Replacement Barrier Replacement at Existing Location
- PROP. 51” MEDIAN BARRIER
Belmont Blvd.
I-440 Slide 4
15
NEW PAVEMENT REPLACE NEW SHOULDER REPLACE MEDIAN PAVING WIDENING RAMP REPAIR/REPLACE LEGENDS
- PROP. 51” MEDIAN BARRIER
- PROP. NOISE BARRIER
Lealand Ln.
I-440 Slide 5
16
NEW PAVEMENT REPLACE NEW SHOULDER REPLACE MEDIAN PAVING WIDENING RAMP REPAIR/REPLACE LEGENDS BRIDGE WIDENING
I-440 Slide 5
17
STA 1203+60 Existing Barrier Barrier Replacement at Existing Location (12’ Height) Existing Barrier Barrier Replacement at Existing Location (12’ Height) STA 1217+60
- PROP. 51” MEDIAN BARRIER
U.S. 31
I-440 Slide 6
18
NEW PAVEMENT REPLACE NEW SHOULDER REPLACE MEDIAN PAVING WIDENING RAMP REPAIR/REPLACE LEGENDS BRIDGE WIDENING
I-440 Slide 7
19
- PROP. 51” MEDIAN BARRIER
END I‐440 WIDENING
NEW PAVEMENT REPLACE NEW SHOULDER REPLACE MEDIAN PAVING WIDENING RAMP REPAIR/REPLACE LEGENDS
- PROP. 51” MEDIAN BARRIER
- PROP. NOISE BARRIER
I-440 Slide 8
20
NEW PAVEMENT REPLACE NEW SHOULDER REPLACE MEDIAN PAVING WIDENING RAMP REPAIR/REPLACE LEGENDS
I-440 Slide 8
21
Replace Existing Barrier New Barrier
- n Berm
Existing Barrier STA 1371+96 STA 1382+84
Maintenance of Traffic / Staging
22
Full Depth Build Inside 1st Phase Full Depth Build Outside 2nd Phase Build Outside 2nd Phase
Aggressive Schedule
23
JUNE ‘17 Request for Owners Representative June 16, 2017 AUGUST ‘17 Final Selection for Owners Representative August 2, 2017 Release Request for Qualifications for I-440 August 18, 2017 OCTOBER ‘17 Statement of Qualifications Due October 13, 2017 Anticipated Completion of NEPA October 30, 2017 NOVEMBER ‘17 Short-Listed Design Builders November 10, 2017 DECEMBER ‘17 Complete Request for Proposal/Preliminary Plans December 7, 2017 Issue Request for Proposal to Short-listed Design-Builders December 15, 2017 MARCH ‘18 Technical Proposals Due March 9, 2018 APRIL ‘18 Price Proposals Due April 27, 2018 MAY ‘18 Award of DB Contract May 4, 2018
Community Outreach
- Noise Wall Meeting
- As –Needed Community Outreach
- Maintenance Agreement for Landscaping
Q & A
25