I-229 Exit 5 (26 th Street) Crossroad Corridor Study Public Open - - PowerPoint PPT Presentation
I-229 Exit 5 (26 th Street) Crossroad Corridor Study Public Open - - PowerPoint PPT Presentation
I-229 Exit 5 (26 th Street) Crossroad Corridor Study Public Open House #3 Jan 15 th , 2014 5:30 - 7:30 P.M. John Harris School Gym Presentation Agenda 1. Discuss Exit 5 (I 229 & 26 th Street) remaining Options (5a, 7a, 7c) 2. Discuss 26
Presentation Agenda
- 1. Discuss Exit 5 (I‐229 & 26th Street)
remaining Options (5a, 7a, 7c)
- 2. Discuss 26th Street and Southeastern
Avenue remaining Options (A &C)
- 3. Discuss Noise Study Findings
- 4. Discuss Park Access
Evaluation Process for Interchange
1. Developed 21 Concept Options including the “No Build” Option (Sept 2012 to May 2013)
Evaluation Process for Interchange 2. Screening Matrix evaluated each Option under 8 categories
1.Design Standards 2.Driver/Public Perception 3.Construction Impacts (high‐level review) 4.Traffic Operations and Safety 5.Pedestrian Impacts 6.Property Impacts 7.Environmental Impacts 8.Construction Costs
Evaluation Process for Interchange
3.
Developed a Screening Matrix to accurately compare the Options (May 2013 to August 2013)
Evaluation Process for Interchange
- 4. Evaluation process resulted in a small
number of Options for further evaluation (Posted to Website Oct 13)
Interchange Remaining Options OPTION 5a
(Westside Ramps along I‐229)
Benefits
‐Lower construction cost with no ramp in NE quadrant of interchange ‐Will serve forecasted traffic demands ‐Minimal impacts to Rotary Park or BSR floodplain ‐Allows for future expansion if needed, northeast ramp could be added ‐Minimal widening west of Yeager Road
Drawbacks
‐26th Bridge reconstruction is necessary due to proximity of ramps in NW and SW quadrants ‐Additional bridge structure along I‐229 ‐Most expensive of remaining options
Interchange Remaining Options OPTION 7a
(SW Loop w/Yeager Rd)
Benefits
‐Lower construction cost with no north side ramps to construct and reduced bridge reconstruction ‐Will serve forecasted traffic demands ‐Minimal impacts to Rotary Park or BSR floodplain ‐Allows for future expansion if needed, northeast ramp could be added
Drawbacks
‐Loop ramp for SB I229 to 26th Street provides a relatively low design speed (25 mph) ‐Widening of 26th Street and connection of Yeager Road to 26th Street requires property acquisitions
Interchange Remaining Options OPTION 7c
(SW Loop w/o Yeager Rd)
Benefits
‐Lower construction cost with no north side ramps to construct and reduced bridge reconstruction ‐Will serve forecasted traffic demands ‐Minimal impacts to Rotary Park or BSR floodplain ‐Allows for future expansion if needed, northeast ramp could be added ‐Fewer impacts to residential properties than 7a as Yeager Road is eliminated
Drawbacks
‐Loop ramp for SB I229 to 26th Street provides a relatively low design speed (25 mph) ‐Widening of 26th Street requires property acquisition ‐Yeager Road Closure will cause traffic to re‐route to local or nearby streets further deteriorating traffic conditions along Cliff Avenue & 26th Street
Evaluation Process for Intersection
- 1. Developed 7 options including the “No
Build” Option (Sept 2012 to May 2013)
Evaluation Process for Interchange 2. Screening Matrix evaluated each
- ption under 9 categories
1.Design Standards 2.Driver/Public Perception 3.Construction Impacts (high‐level review) 4.Environmental Impacts 5.Pedestrian Impacts 6.BNSF Railroad 7.Traffic Operations and Safety 8.Property Impacts 9.Construction Costs
Evaluation Process for Intersection
3.
Developed a Screening Matrix to accurately compare the options (May 2013 to August 2013)
Evaluation Process for Intersection
- 4. Evaluation process selected a small
number of options for further evaluation (Posted to Website Oct 13)
Intersection Remaining Options
OPTION A (Raised Intersection) Benefits
‐Access to NE quadrant will not change from existing conditions ‐Will serve forecasted traffic demands per City criteria ‐Access to Rotary & Norlin Park is relocated improving safety along 26th Street during peak periods ‐BNSF has noted their preference for this option
Intersection Remaining Options
OPTION A (Raised Intersection) Drawbacks
‐Property acquisition of several parcels is required as access can’t be provided to either the commercial or residential properties in the SE Quadrant ‐Visual Impacts assumed by property owners
Intersection Remaining Options
OPTION C (Raised Intersection shifted west) Benefits
‐Access to NE Quadrant will not change from existing conditions ‐Will serve forecasted traffic demands per City criteria ‐Access to Rotary & Norlin Park is relocated improving safety along 26th Street during peak periods ‐Only 1 residential property would need to be acquired
Intersection Remaining Options
OPTION C (Raised Intersection shifted west) Drawbacks
‐Property acquisition of 1 parcel is required to construct access road to Pioneer Trail ‐Visual Impacts assumed by property
- wners
‐City Maintenance Dept. has difficulty with access roads
Options Evaluation Memo
Click Here to take Survey
- n Screening
Process Click on either the Interchange or Intersection Memo’s to Review
www.26thstreetcorridorstudy.com
Noise Study Process & Findings Step 1 – Conduct Field Monitoring
Noise Study Process & Findings Step 1 – Conduct Field Monitoring
Noise Study Process & Findings Step 2 –Develop Existing Noise Prediction Model
Monitoring Location Monitoring Leq (dBA) Modeled Leq (dBA) Difference 1 66.9 68.3 +1.4 2 64.9 65.4 +0.5 4 59.1 58.4 ‐0.7 5 68.6 68.2 ‐0.4 6 58.9 56.8 ‐2.1 7 68.0 67.4 ‐0.6 8 62.8 61.7 ‐1.1 9 70.1 67.3 ‐2.8
INPUTS
- Existing Traffic Volumes/Speeds
- Existing Geometrics (number of
lanes, proximity to homes, elevation of road to homes, etc..)
- Vehicle Types (cars, trucks, buses,
motorcycles, etc.)
Model validated if “Modeled” values are within +/‐ 3 dBA
- f “Monitored”
Values
Noise Study Process & Findings Step 3 – Develop Year 2035 Noise Prediction Model for Each Option
Noise Study Process & Findings Step 3 – Develop Year 2035 Noise Prediction Model for Each Option INPUTS
- SB off/on ramps added outside
I229 shoulder
- Vertical elevation of ramp added
- Distance to homes and elevation
- f homes
- Vehicle volumes, speeds, & types
- Receptors
Riverdale Subdivision in Option 5a
Noise Study Process & Findings
Step 4 – Compare results to Noise Abatement Criteria Thresholds
Activity Category Activity Leq(h)
1
Evaluation Location Description of Activity Category FHWA SDDOT B2 67 52 66 51 Exterior Interior Residential. C2 67 66 Exterior Active sports areas, amphitheaters, auditoriums, campgrounds, cemeteries, day care centers, hospitals, libraries, medical facilities, parks, picnic areas, places of worship, playgrounds, public meeting rooms, public or nonprofit institutional structures, radio studios, recording studios, recreational areas, Section 4(f) sites, schools, television studios, trails, and trail crossings.
Noise Study Process & Findings
Step 4 – Compare results to Noise Abatement Criteria Thresholds
Riverdale Subdivision in Option 5a
Noise Study Process & Findings
Step 5 – Evaluate Noise Abatement Measures per SDDOT Policy
- 1. Modifying the proposed horizontal and/or vertical alignments of the
roadway Impractical based on options developed
- 2. Traffic management measures (e.g. modify speed limits and restrict truck
traffic) Impractical given the type of road in question
- 3. Construction of noise barriers along or within the ROW
Possible; options include walls, berms, and vegetation. Berms and vegetation would require more space than is available
- 4. Acquisition of property rights for construction of noise barriers
Not necessary because walls from Item 3, above, can be used
- 5. Acquisition of property to serve as a buffer zone
Prohibitively expensive
Noise Study Process & Findings Step 6 – When Impacts are identified, noise abatement will be considered and evaluated for Feasibility per SDDOT policy Feasibility Requirements
- Safety: No site distance issues, no continuous shadow resulting in
icing or snow accumulation on driving lanes, no drainage impacts
- Barrier Height: Safety concerns exist when barriers exceed 20 feet
in height, evaluation will not consider barriers higher than 20’
- Topography: topography shall allow for construction of
abatement measure
- Drainage, Utilities, and Abatement Measure: access to provide
maintenance
Noise Study Process & Findings Step 6 – When Impacts are identified, noise abatement will be considered and evaluated for Acoustic Feasibility per SDDOT policy Acoustic Feasibility
- Abatement Measure: must achieve a 5 dBA reduction for 60%
- f the front‐row receptors directly behind the noise wall
Noise Study Process & Findings Step 6 – When Impacts are identified, noise abatement will be considered and evaluated for Reasonableness per SDDOT policy Reasonableness
- Cost Effectiveness of abatement measure: Cost per benefited
receptors shall be $21,000 or less to be considered reasonable
Noise Study Process & Findings
Step 7 – Complete Noise Abatement Study
(No Noise Barrier – Riverdale Area Option 5a)
Summary
(Option 5a)
- Ramp serves as Wall
- Average Height = 12’
- No actual separate noise wall
Noise Study Process & Findings
Step 7 – Complete Noise Abatement Study
(Noise Barrier B – Riverdale Area Option 7a/7c)
Wall Summary
(Option 7a & 7c)
- Length = 879’
- Average Height = 19’
- Wall Cost = $735,000
Noise Study Process & Findings Step 7 – Complete Noise Abatement Study (Noise Barrier B – Riverdale Area Option 7a/7c) RESULTS
- Not cost effective, 4.5 times
higher than the $21,000 threshold per benefited receptor
- Wall achieved noise reduction
criteria
Noise Study Process & Findings Step 7 – Complete Noise Abatement Study (Noise Barrier C – Yeager Rd Area Option 7a) Wall Summary
(Option 7a)
- Length = 1997’
- Average Height = 14.85’
- Wall Cost = $1.3 Million
Noise Study Process & Findings Step 7 – Complete Noise Abatement Study (Noise Barrier C – Yeager Rd Area Option 7a) RESULTS
- Not cost effective, 2.5 times
higher than the $21,000 threshold per benefited receptor
- Wall achieved noise reduction
criteria
I‐29 Noise Abatement Project Example
I‐29 Noise Abatement Project Example RESULTS
- Cost effective, approx. $17,700
per benefited receptor which is below the $21,000 threshold per benefited receptor (when using $44 per square foot per current policy)
- Wall achieved noise reduction
criteria
Major Factors
- Density of Homes (i.e. smaller lots
than along our corridor)
- 2nd Row of receptors benefited
from noise wall along I‐29 12’‐16’ Height
Park & Trail Access EA Considerations
Section 4(f)
- Addresses Impacts to
Park & Rec Land
Section 6(f)
- Addresses Impacts to
Park & Rec Land/Trail that utilized National Park Service (NPS) Grants Funds
Park & Trail Access
“Existing” Vehicle Access
‐Driveway to Rotary /Norlin Park from 26th Street ‐Gravel driveway to Canoe Launch Area ‐Driveway to Pasley Park
Pedestrian Access
‐Sidewalk connection to Park and Trail on the north side of 26th Street ‐Unsignalized Crossing on Southeastern Avenue to enter park or trail system at Pasley Park entrance ‐Sidewalks only on north side of 26th Street west of Southeastern ‐Sidewalks only on east side of Southeastern Avenue
Park & Trail Access
“Proposed Base” Vehicle Access
‐Paved driveway to Canoe Launch Area ‐Considering driveway off of Pasley Park entrance road to serve Rotary & Norlin Park as bridge over river will provide approximately 18’ of clearance
Pedestrian Access
‐Sidewalks on both sides of 26th Street through corridor with the intersection serving all directions, 10’ wide sidewalk on Bridge west of Southeastern Avenue ‐Sidewalk connection from 26th Street to Pasley Park entrance on west side of Southeastern ‐Considering additional access to Rotary Park from 26th Street
Park & Trail Access
“Additional Access Thoughts” Pedestrian Access
‐Circular Ramp or Straight Ramp from 26th Street down to Park or Trail
Drawbacks
- Most Expensive option to connect
26th Street directly to park/trail (+/‐ 1.3 Million)
Future Trail
Possible Stairs Location
Park & Trail Access
“Additional Access Thoughts” Pedestrian Access
‐Stairs option with ability to walk bike down to park level
Future Trail
Possible Stairs Location
Park & Trail Access
“Additional Access Thoughts” Pedestrian Access
‐Stairs option with ability to walk bike down to park level
Drawbacks
- Least desirable winter
maintenance option
- Not ADA Compliant
Possible Pedestrian Bridge Location
Park & Trail Access
“Additional Access Thoughts” Pedestrian Access across Big Sioux River
‐Pedestrian Bridge from Canoe Launch Parking Area across Big Sioux River to Trail/Parks
Future Trail
Possible Parking
Park & Trail Access
“Additional Access Thoughts”
Pedestrian Access across Big Sioux River
‐Pedestrian Bridge from Canoe Launch Parking Area across Big Sioux River to Trail/Parks
Drawbacks
- Requires another structure
crossing over the Big Sioux River
Room Layout
Next Steps
Take Public Comment regarding options remaining, environmental concerns, and park access options Finalize Environmental Coordination and “Recommend a Preferred Alternative” Complete Environmental Assessment
Before You Leave!!!!!!!
Please Sign In! Share your thoughts?
- Remaining Options
- Environmental
Considerations
I-229 Exit 5 (26th Street) Crossroad Corridor Study
Thank You!!!! Please visit the Website! www.26thstreetcorridorstudy.com
Project Contacts
SDDOT Project Manager Steve Gramm, PE Project Development, Data Analysis Engineer Steve.gramm@state.sd.us Phone: 605‐773‐6641 City of Sioux Falls Project Manager Shannon Ausen, PE Traffic Engineering Division sausen@siouxfalls.org Phone: 605‐367‐8607 CONSULTANT Team Project Manager Jason Kjenstad, PE HDR Engineering, Sioux Falls Jason.Kjenstad@hdrinc.com Phone: 605‐977‐7740