HVS Consortium Single Phase Far Detector: ITF & installation requirements
SURF, October 30th, 2018
- V. Guarino
- F. Pietropaolo
- B. Yu
HVS Consortium Single Phase Far Detector: ITF & installation - - PowerPoint PPT Presentation
HVS Consortium Single Phase Far Detector: ITF & installation requirements SURF, October 30th, 2018 V. Guarino F. Pietropaolo B. Yu DUNE SP HV System ~7 m From ProtoDUNE to DUNE Far detector 6m CPA panels FC End walls
10/30/18 ITF and Installation Workshop 2
From ProtoDUNE to DUNE Far detector
FC End walls
6m ~7 m
CPA panels FC top/bottom modules
12m
use of bent profiles)
10/30/18 ITF and Installation Workshop 3
(Docdb 6260)
Voltage New Power Supply 1 day Current
filters induced instabilities:
nominal voltage at 180 kV randomly affected by two kind of instabilities.
acquisition
least one GP
charge on GP’s
US-BL) & Beam Plug Termination
UP-US-BL & BPT
10/30/18 ITF and Installation Workshop 4
10/30/18 ITF and Installation Workshop 5
the FRP I-beam to the GP I-beam
the high field region
underway
beam (reduce plastic in high field region)
10/30/18 ITF and Installation Workshop 6
10/30/18 ITF and Installation Workshop 7
scheme, no repackaging into underground crates foreseen
FC modules for visual/electrical inspection
10/30/18 ITF and Installation Workshop 8
underground activities
10/30/18 ITF and Installation Workshop 9
10/30/18 ITF and Installation Workshop 10
10/30/18 ITF and Installation Workshop 11
installation
cables
10/30/18 ITF and Installation Workshop 12
10/30/18 ITF and Installation Workshop 13
Boxed CPA lowered into SAS and moved to Assy Fixture in CR Boxed CPA in position. 1/3 panel being raised from crate CPA panels placed into fixture
10/30/18 ITF and Installation Workshop 14
Assembled CPA panel placed onto TCO Beam
10/30/18 ITF and Installation Workshop 15
Top FC Panels installed as the CP array hangs under the TCO beam Crated FC Panels and GP assembly lowered into SAS and moved into Clean Room GP assembly remounted on FC panels
hanging from the TCO beam
its final place using a fixture
the same manner as ProtoDune SP
be deployed simultaneously
10/30/18 ITF and Installation Workshop 16
10/30/18 ITF and Installation Workshop 17
10/30/18 ITF and Installation Workshop 18
inspection
the top and bottom FC are deployed, 2 CPA and 2 x 4 FC modules a week need to go underground
upstream after full top/bottom deployment
10/30/18 ITF and Installation Workshop 19