hrtac regional financial plan
play

HRTAC Regional Financial Plan Recap and Work Order Scenarios January - PowerPoint PPT Presentation

HRTAC Regional Financial Plan Recap and Work Order Scenarios January 19, 2016 Post Presenta*on Version with correc*on to Slide 8. Recap: Initial Project Financing Scenario Description In November 2015, PFM


  1. HRTAC Regional Financial Plan Recap and Work Order Scenarios January 19, 2016 Post ¡Presenta*on ¡Version ¡with ¡correc*on ¡to ¡Slide ¡8. ¡

  2. Recap: Initial Project Financing Scenario Description • In November 2015, PFM prepared and presented six HRTAC project financing scenarios Toll Patriots Crossing Only assumed $2.00 fixed toll rate 1. HOT Network 2. HOT on existing I-64 HOV lanes, High Rise Bridge, HRBT, MMBT, and Rt. 460/58 Connector; $2 fixed toll rate all lanes on Patriots Crossing Toll All Lanes – Option A 3. $1 on High Rise Bridge, Patriots Crossing, HRBT and MMBT; HOT on Rt. 460/58 Connector Toll All Lanes – Option B 4. $2 on High Rise Bridge, Patriots Crossing, HRBT and MMBT; HOT on Rt. 460/58 Connector Toll All Lanes – Option C 5. Same as Scenario 3 except peak & off-peak congestion pricing at $1.5 & $1 on HRBT Toll All Lanes – Option D 6. Same as Scenario 4 except peak & off-peak congestion pricing at $3 & $2 on HRBT * All stated toll rates are in 2015 dollars; toll rates are inflated by 2.5% annually 2

  3. Recap: Initial Project Financing Scenario Results • Scenario 1-6 are not financially feasible with the key assumptions below: – Total toll revenues through 2070 range from $0.5 billion to $5.9 billion among the six scenarios in 2016 dollars (discounted @ 5.0%) – HRTF revenues through 2070 are $10.7 billion in 2016 dollars (discounted @ 2.5%) – $2 billion HRTPO/VDOT funds in 2016 dollars (discounted @ 2.5%) – Toll projects completed by FY 2037 – Capital costs are $14.5 billion (HOT tolling option) and $13.0 billion (Toll all lane option) in 2014/2015 dollars Scenario 1 Scenario 2 Scenario 3 Scenarnio 4 Scenario 5 Scenario 6 Toll Patriots Toll All Lanes Toll All Lanes Toll All Lanes Toll All Lanes HOT Network $ millions Crossing Only Option A Option B Option C Option D Future Value of Additional Grants Needed* 7,799 9,005 4,528 2,045 3,551 642 Additional Tax Revenue Needed** 229 265 133 60 104 19 Note: *FV of grants net of residual revenues through 2040 **Additional HRTF revenue in 2016 needed; annual revenues thereafter are based on the new assumed 2016 revenue and grow at the growth rates as the current estimates. • PFM also prepared Scenario 6B that assumed delaying Patriots Crossing construction after MMBT could be completed. Scenario 6B is feasible. 3

  4. Review of Assumptions: Project Schedule Updates • VDOT indicated that the I-64 Widening Segment 3 and Ft. Eustis Blvd Interchange projects would start construction in 2018 and 2021, respectively, regardless funding availability • In addition, I-64 Widening Segment 2 and I-64/I-264 Interchange projects completion dates are slightly delayed • Updated assumed fiscally unconstrained schedules are as follows: PE Construction Construction PE Construction Start Date Start Finish Duration Duration I-64 Widening - Segment 1 7/1/2014 1/1/2015 1/1/2018 6 mns 36 mns I-64 Widening - Segment 2 2/1/2015 7/1/2016 6/1/2019 18 mns 36 mns I-64 Widening - Segment 3 7/1/2016 7/1/2018 12/1/2021 24 mns 41 mns Ft. Eustis Blvd Interchange 1/1/2019 3/1/2021 12/1/2023 26 mns 33 mns I-64/I-264 Interchange - Phase 1 4/1/2015 11/1/2016 7/1/2019 19 mns 32 mns I-64/I-264 Interchange - Phase 2 1/1/2016 1/1/2017 12/1/2021 12 mns 59 mns High Rise Bridge 1/1/2015 1/1/2017 1/1/2022 24 mns 60 mns Patriots Crossing 11/1/2017 1/1/2020 1/1/2025 26 mns 60 mns HRBT 5/1/2023 1/1/2025 1/1/2030 20 mns 60 mns MMBT 11/1/2027 1/1/2030 1/1/2035 26 mns 60 mns Route 460/58/13 Connector 1/1/2033 1/1/2035 1/1/2038 24 mns 36 mns 4

  5. Review of Assumptions: Studied Scope vs. SEIS Scope • VDOT and FHWA have initiated work on a Supplemental Environmental Impact Statement (SEIS) to reevaluate the Hampton Roads Crossing Study. • In November 2015, VDOT and FHWA presented four alternatives to HRTPO ‒ The regional system scope assumed in PFM’s November analysis is mostly aligned with the HRCS SEIS Alternative D Alt. ¡A ¡ Alt. ¡B ¡ Alt. ¡C ¡ Alt. ¡D ¡ � Alt. B and C � I-664 � I-64/HRBT � I-64 improvements b/w � I-664/I-564 Connectors � I-564 I-664 & I-564 � I-564 � I-564 Connector � HRBT � Route 164 Connector � Route 164 Connector � Route 164 5

  6. Review of Assumptions: HOT Network • VDOT retained qualified engineering and traffic consultants the study Hampton Roads projects who in 2014 produced reports regarding a High Occupancy Toll network. • PFM used these reports as a primary basis for our financing analyses to the extent possible: – Engineers were asked and provided project costs based upon all general purpose lanes, which eliminated significant costs related to HOT direct connectors – Traffic consultant provided toll revenue estimates for tolling all lanes of the major water crossings • Based on this data, PFM determined that HOT revenues did not cover HOT incremental costs • It may be possible to add HOT lanes to some of the projects without direct connectors at major interchanges, and PFM has been asked to study this: – Engineers suggest an operational study to evaluate the safety & operation at each access point. – General purpose lanes cost estimates eliminated DCs but did NOT identify any corresponding slip ramps or pavement/bridge widenings that would be required for access/egress if HOT without DCs – The direct connectors provide a ‘cleaner’ system in terms of operational effectiveness and in terms of controlling leakage (toll evasion) – The HOT revenue forecast depends how the areas without direct connectors would function operationally with weaving and merging, etc. – If a HOT network with Patriot’s Crossing tolling is the chosen alternative, then additional detailed traffic & revenue study is needed 6

  7. Review of Assumptions: HRTF Revenue Forecast Update • Virginia Department of Taxation prepared HRTF revenue estimates from FY 2016 to FY 2022 in December 2015 ‒ Fuel tax revenues are revised down and sales tax revenues are revised up. ‒ Combined HRTF revenues are close to the previous estimates. • HRTF estimates from FY 2023 to FY 2045 revenues are extrapolated based on growth rates assumed previously. Estimates thereafter assume the same growth rate as in FY 2045 • Fuel tax revenues growth rates vary from 0.0% to 1.7%; sale tax revenues growth rate is approximately 3.3% 7

  8. Work Order 2 Additional Funding Scenarios • The previous Scenario 1&2 are not feasible. The additional scenarios are to explore two options to close the funding gap: – Increase HRTF revenues o Set a fuel tax floor price of $3.22* (FY 2016 projected price is $1.98) o Raise tax rates: currently 0.7% sales tax and 2.1% fuels tax** – Delay project schedules until sufficient funds are accumulated • Scenario 1: Toll Patriots Crossing Only ($2 Fixed Toll) – 1A - $3.22 Floor Fuels Price – 1B - $3.22 Floor Fuels Price & Increase Fuels Tax Rate As Needed – 1C - $3.22 Floor Fuels Price & Increase Fuels Tax & Sales Rates As Needed – 1D - $3.22 Floor Fuels Price & Increase Sales Tax by 1.0% • Scenario 2: $3.22 Floor Fuels Price; $2 Fixed Toll on Patriots Crossing and HOT Tolling on High Rise Bridge, HRBT, MMBT & Rt. 460/58 Connector – 2A - Eliminate Direct Connectors – 2B - Eliminate Direct Connectors and Add I-64 HOV/HOT Project (no direct connectors) *Weighted average figure established based on market prices on 2/20/2013 (76% gasoline and 24% diesel) ** Transposed numbers noted and corrected in FSAC meeting by PFM. This version denotes that correction. 8

  9. Work Order 2 Financing Variations For each of the previously outlined additional scenarios, the following three financing variations have been evaluated: • I. HRTF debt issuance allowed and $2 billion PV VDOT/HRTPO funds in total • II. HRTF debt issuance allowed and $500 million PV VDOT/HRTPO funds in total ‒ VDOT may not pay pre-construction costs • III. HRTF debt NOT allowed (pay-go funds only) and $2 billion PV VDOT/HRTPO funds in total For the previous Scenario 4 as well as the above scenarios, as applicable, assume no capacity or other improvements to HRBT during the planning & financing horizon and no tolling of HRBT of any type • Scope and cost correspond to Hampton Roads Crossing Study SEIS Alternative C 9

  10. Scenarios 1A – 1D Results: Tax Revenue Comparison • The ¡Sales ¡Tax ¡is ¡projected ¡to ¡grow ¡more ¡rapidly ¡than ¡the ¡fuel ¡tax, ¡so ¡a ¡lower ¡star*ng ¡dollar ¡ amount ¡is ¡needed ¡if ¡increasing ¡the ¡Sales ¡Tax ¡ • Scenarios ¡1B, ¡1C, ¡and ¡1D ¡all ¡fully ¡fund ¡all ¡projects ¡by ¡2040 ¡if ¡bond ¡issuance ¡is ¡allowed, ¡even ¡if ¡ lower ¡HRTPO/VDOT ¡funding ¡is ¡assumed ¡ • However, ¡without ¡bond ¡issuance ¡significantly ¡higher ¡tax ¡rates ¡are ¡needed ¡and/or ¡some ¡ projects ¡will ¡be ¡pushed ¡past ¡2040 ¡ $1,350M $1,150M $950M Current Estimate Scenario 1A_I $750M Scenario 1B_1 Scenario 1C_1 $550M Scenario 1D_1 $350M $150M 10

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend