how to get more from foundation fieldbus
play

How to Get More From FOUNDATION fieldbus Beyond wiring savings By - PowerPoint PPT Presentation

How to Get More From FOUNDATION fieldbus Beyond wiring savings By Alex To - TURCK BANNER Singapore Topics Covered Background Training Design Procurement Integration Configuration Factory Acceptance Test (FAT)


  1. How to Get More From FOUNDATION fieldbus Beyond wiring savings By Alex To - TURCK BANNER Singapore

  2. Topics Covered  Background  Training  Design  Procurement  Integration  Configuration  Factory Acceptance Test (FAT)  Installation  Commissioning  Change Work Practices  Network Maintenance  System Management  Design  Procurement  Integration  Configuration  FAT  Installation  Commissioning  Operation

  3. Background Do more

  4. You Can Do More  Plants are achieving wiring, I/O card, and marshalling savings: o Multiple devices on the same pair of wires o Multiple I/O per device on the same pair of wires o Innovative multi-channel devices o ~100 I/O signals per fieldbus H1 card o Virtual Marshalling™ for easy I/O signal changes  Do more: o Simplified loop check o Tighter control o Instrument diagnostic alarm management o Intelligent discrete devices o Add instruments for equipment condition and performance monitoring; on premise or IIoT

  5. Fieldbus Training Competency is a critical success factor

  6. FF Training Helps  FF capabilities still not fully utilized o Learn more to get more out fieldbus  FF has evolved over the years o Learn more to do fieldbus the easier way  Use consultants, EPC contractors, and subcontractors trained on FF  Train plant I&C personnel on FF to ensure continuity  Get trained on FF NE107 IIoT Control-in-the-Field Loop Check Intelligent on-off devices

  7. FF Design Better and simpler

  8. Fieldbus Design the Easy Way  Count devices, not I/O signals  One worst case ‘Typical’ power calculation o Voltage drop  One worst case ‘Typical’ loading calculation o Scan time

  9. FOUNDATION Fieldbus for IIoT - Build on the Fieldbus You’ve Got  Add instruments for equipment condition and performance monitoring o On premise or IIoT  Fieldbuses usually not fully populated  Add sensors for condition monitoring and energy management Control System Condition Monitoring System & Energy Management System etc. Process Control & Monitoring Condition Monitoring & Energy Management etc.

  10. FF Configuration Engineer to avoid alarm flooding

  11. Same as for Avoid Alarm Flooding: HART Instrument Diagnostic Alarm Management  If the instrument diagnostic alarm management system is not configured there will be a flood of nuisance alarms o System will not be used  ISA108 guidance being developed  Interim guide: o http://www.eddl.org/DeviceManagement/Pages/DeviceDiagnostics.as px  Specify a control system supporting diagnostics alarm management o Filtering based on criticality o Routing to the right person

  12. Same as for HART Instrument Diagnostic Alarm Routing Instrument Tech Operator • Failure • Failure • Maintenance Required • Function Check • Out of Specification Nuisance Alarms Devices

  13. Same as for HART Instrument Diagnostics Alarm Rationalization  Categorize severity of diagnostics: o NAMUR NE107  Identify criticality to the process for each device tag  Configure system and devices

  14. Factory Acceptance Test (FAT) Test to make sure instrument diagnostics alarm management will work as intended

  15. Same as for HART FAT Interoperability / Integration Test  Connect one of each device type  Open each device type in the IDM software o Verifies the DD file for each type and version of the device has been loaded o Verifies the device displays correctly  Download a device configuration o Verify the download is error free

  16. FF Installation Wiring

  17. Same as for Good Digital Communication Installation HART Practices  Don’t ground shield at device, insulate shield  Maintain shield through junction boxes  Route signal cables in separate tray from power cables  Don’t loop cable too tight Don’t spend too much  Ground device housing and junction boxes  Don’t coil signal cables and power cables together the first 3…  Don’t damage shield and conductor insulation  Don’t strip off more jacket than necessary  Ground overall shield for multi-pair cable  Ground the cable armor

  18. Same as for Other Good Installation Practices 4-20 mA  Do not pull cable with too much force  Make sure cable glands are tight  Seal unused conduit entries Don’t spend too much  Use correct size ferrule/fork and tool  Do not cram wires in device terminal compartment the first 3…  Do not over/under-tighten screws  Make sure covers are tight  Do not tighten cable-tie too much  Label wires  Observe polarity

  19. FF Commissioning Digital loop check

  20. 5-Point Loop Check is Not Required on Fieldbus Projects  No 4-20 mA ranging  No 4-20 mA signal distortion  No traditional five-point loop tests  Instead a simple plausibility check DIGITAL • No range mismatch • Not limited • No biased • No non-linearity • No current calibration mismatch

  21. Change Work Practices Getting into the habit of using the IDM software as part of the daily routine

  22. Same as for HART Instrument Technician Culture Change  Review instrument diagnostic alarms o Instrument technicians must review the instrument diagnostic alarm summary and log every day  Spend time on devices which need attention  Check the software first o When operations say a device is not working, instrument technicians must check the software first , before going to the field to take a look  Avoid unnecessary field visits  Rewriting Standard Operating Procedures (SOPs) o Rewrite work procedures to include IDM software  Inspection, replacement, calibration and other tasks

  23. Network Maintenance Maintain installation in good condition to ensure the communication continues to work error free

  24. Same as for HART Monitor Network Health  Periodically check communication Packet Error Rate (PER) to detect deteriorating communication before alarms appear  Built-in control system communication diagnostics

  25. System Management Keep systems up to date with new device types and versions

  26. Same as for HART Keep System Up to Date  Load the DD files for new device types and versions on the control system and IDM software

  27. Same as for HART DD File Management  DD files are easy to download from the Internet  Load DD files for all devices, even if they are currently not in use o You don’t have to figure which you need now and which you don’t o You never know when new devices will be installed o The system is ready for all kinds of devices  Some systems have DD wizard that automatically distributes the DD to all computers in the system  Some hosts offer update services which loads DD files onto the system automatically as they become available

  28. Conclusion

  29. Get More from Fieldbus  Simplified loop check  Tighter control  Instrument diagnostic alarm management  Intelligent discrete devices  Add instruments for equipment condition and performance monitoring; on premise or IIoT

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend