How to Get More From FOUNDATION fieldbus Beyond wiring savings By - - PowerPoint PPT Presentation

how to get more from foundation fieldbus
SMART_READER_LITE
LIVE PREVIEW

How to Get More From FOUNDATION fieldbus Beyond wiring savings By - - PowerPoint PPT Presentation

How to Get More From FOUNDATION fieldbus Beyond wiring savings By Alex To - TURCK BANNER Singapore Topics Covered Background Training Design Procurement Integration Configuration Factory Acceptance Test (FAT)


slide-1
SLIDE 1

How to Get More From FOUNDATION fieldbus

Beyond wiring savings By Alex To - TURCK BANNER Singapore

slide-2
SLIDE 2

Topics Covered

 Background  Training  Design  Procurement  Integration  Configuration  Factory Acceptance Test (FAT)  Installation  Commissioning  Change Work Practices  Network Maintenance  System Management

Design Procurement Integration Configuration FAT Installation Commissioning Operation

slide-3
SLIDE 3

Background

Do more

slide-4
SLIDE 4

You Can Do More

 Plants are achieving wiring, I/O card, and marshalling savings:

  • Multiple devices on the same pair of wires
  • Multiple I/O per device on the same pair of wires
  • Innovative multi-channel devices
  • ~100 I/O signals per fieldbus H1 card
  • Virtual Marshalling™ for easy I/O signal changes

 Do more:

  • Simplified loop check
  • Tighter control
  • Instrument diagnostic alarm management
  • Intelligent discrete devices
  • Add instruments for equipment condition and performance

monitoring; on premise or IIoT

slide-5
SLIDE 5

Fieldbus Training

Competency is a critical success factor

slide-6
SLIDE 6

FF Training Helps

 FF capabilities still not fully utilized

  • Learn more to get more out fieldbus

 FF has evolved over the years

  • Learn more to do fieldbus the easier way

 Use consultants, EPC contractors, and subcontractors trained on FF  Train plant I&C personnel on FF to ensure continuity  Get trained on FF

Loop Check Control-in-the-Field NE107 Intelligent on-off devices IIoT

slide-7
SLIDE 7

FF Design

Better and simpler

slide-8
SLIDE 8

Fieldbus Design the Easy Way

 Count devices, not I/O signals  One worst case ‘Typical’ power calculation

  • Voltage drop

 One worst case ‘Typical’ loading calculation

  • Scan time
slide-9
SLIDE 9

FOUNDATION Fieldbus for IIoT

  • Build on the Fieldbus You’ve Got

 Add instruments for equipment condition and performance monitoring

  • On premise or IIoT

 Fieldbuses usually not fully populated  Add sensors for condition monitoring and energy management

Process Control & Monitoring Condition Monitoring & Energy Management etc. Control System Condition Monitoring System & Energy Management System etc.

slide-10
SLIDE 10

FF Configuration

Engineer to avoid alarm flooding

slide-11
SLIDE 11

Avoid Alarm Flooding: Instrument Diagnostic Alarm Management

 If the instrument diagnostic alarm management system is not configured there will be a flood of nuisance alarms

  • System will not be used

 ISA108 guidance being developed  Interim guide:

  • http://www.eddl.org/DeviceManagement/Pages/DeviceDiagnostics.as

px

 Specify a control system supporting diagnostics alarm management

  • Filtering based on criticality
  • Routing to the right person

Same as for HART

slide-12
SLIDE 12

Instrument Diagnostic Alarm Routing

Operator Instrument Tech

  • Failure
  • Function Check
  • Failure
  • Maintenance Required
  • Out of Specification

Devices Nuisance Alarms Same as for HART

slide-13
SLIDE 13

Instrument Diagnostics Alarm Rationalization

 Categorize severity of diagnostics:

  • NAMUR NE107

 Identify criticality to the process for each device tag  Configure system and devices

Same as for HART

slide-14
SLIDE 14

Factory Acceptance Test (FAT)

Test to make sure instrument diagnostics alarm management will work as intended

slide-15
SLIDE 15

FAT Interoperability / Integration Test

 Connect one of each device type  Open each device type in the IDM software

  • Verifies the DD file for each type and version of the

device has been loaded

  • Verifies the device displays correctly

 Download a device configuration

  • Verify the download is error free

Same as for HART

slide-16
SLIDE 16

FF Installation

Wiring

slide-17
SLIDE 17

Good Digital Communication Installation Practices

 Don’t ground shield at device, insulate shield  Maintain shield through junction boxes  Route signal cables in separate tray from power cables  Don’t loop cable too tight  Ground device housing and junction boxes  Don’t coil signal cables and power cables together  Don’t damage shield and conductor insulation  Don’t strip off more jacket than necessary  Ground overall shield for multi-pair cable  Ground the cable armor

Don’t spend too much the first 3… Same as for HART

slide-18
SLIDE 18

Other Good Installation Practices

 Do not pull cable with too much force  Make sure cable glands are tight  Seal unused conduit entries  Use correct size ferrule/fork and tool  Do not cram wires in device terminal compartment  Do not over/under-tighten screws  Make sure covers are tight  Do not tighten cable-tie too much  Label wires  Observe polarity

Don’t spend too much the first 3… Same as for 4-20 mA

slide-19
SLIDE 19

FF Commissioning

Digital loop check

slide-20
SLIDE 20

5-Point Loop Check is Not Required on Fieldbus Projects

 No 4-20 mA ranging  No 4-20 mA signal distortion  No traditional five-point loop tests  Instead a simple plausibility check

DIGITAL

  • No range mismatch
  • Not limited
  • No biased
  • No non-linearity
  • No current calibration

mismatch

slide-21
SLIDE 21

Change Work Practices

Getting into the habit of using the IDM software as part of the daily routine

slide-22
SLIDE 22

Instrument Technician Culture Change

 Review instrument diagnostic alarms

  • Instrument technicians must review the instrument

diagnostic alarm summary and log every day

  • Spend time on devices which need attention

 Check the software first

  • When operations say a device is not working,

instrument technicians must check the software first, before going to the field to take a look

  • Avoid unnecessary field visits

 Rewriting Standard Operating Procedures (SOPs)

  • Rewrite work procedures to include IDM software
  • Inspection, replacement, calibration and other tasks

Same as for HART

slide-23
SLIDE 23

Network Maintenance

Maintain installation in good condition to ensure the communication continues to work error free

slide-24
SLIDE 24

Monitor Network Health

 Periodically check communication Packet Error Rate (PER) to detect deteriorating communication before alarms appear  Built-in control system communication diagnostics

Same as for HART

slide-25
SLIDE 25

System Management

Keep systems up to date with new device types and versions

slide-26
SLIDE 26

Keep System Up to Date

 Load the DD files for new device types and versions on the control system and IDM software

Same as for HART

slide-27
SLIDE 27

DD File Management

 DD files are easy to download from the Internet  Load DD files for all devices, even if they are currently not in use

  • You don’t have to figure which you need now and

which you don’t

  • You never know when new devices will be installed
  • The system is ready for all kinds of devices

 Some systems have DD wizard that automatically distributes the DD to all computers in the system  Some hosts offer update services which loads DD files

  • nto the system automatically as they become available

Same as for HART

slide-28
SLIDE 28

Conclusion

slide-29
SLIDE 29

Get More from Fieldbus

 Simplified loop check  Tighter control  Instrument diagnostic alarm management  Intelligent discrete devices  Add instruments for equipment condition and performance monitoring; on premise or IIoT