Harrisburg Overpass Construction Update December 1, 2015 All Utility Work East of Union Pacific Railroad Total % Completed Installed 2095 LF Utilities Completed 3,800 LF 55% Utilities Remaining to be Relocated East of Union Pacific


slide-1
SLIDE 1

Harrisburg Overpass Construction Update

December 1, 2015

slide-2
SLIDE 2

Utilities Completed 3,800 LF % Completed Installed Total 55% 2095 LF

All Utility Work East of Union Pacific Railroad

slide-3
SLIDE 3

Utilities Remaining to be Relocated East of Union Pacific Railroad

slide-4
SLIDE 4

Concrete Paving East of Union Pacific Railroad

slide-5
SLIDE 5

Current Sidewalk Detour Plan

5

slide-6
SLIDE 6

All Utility Work West of Union Pacific Railroad

Utilities Completed 4,150 LF % Completed Installed Total 73% 3,210 LF

slide-7
SLIDE 7

Utilities Remaining to be Relocated West of Union Pacific Railroad

slide-8
SLIDE 8

Concrete Paving West of Union Pacific Railroad

slide-9
SLIDE 9

Progress and Planned Activities

  • Pavement Operations are beginning in the Northeast Quadrant
  • McCarthy will maintain driveways by adding crushed stone as required
  • Relocated Street Lighting during construction to be maintained and illuminate along new

roadway

  • METRO/McCarthy are working to adjust schedule activities to keep the project on schedule
  • Select construction activities will be built concurrently with major bridge activities during the third phase of

construction

  • McCarthy will be working extended hours to expedite completion of roadway pavement
  • The placing, finishing, curing, and saw cutting new pavement requires extended work hours
  • Utility crews started 12 hour days instead of 10 hours
  • To make up time due to rain, McCarthy chose to work on one Sunday in November
  • McCarthy plans to work extra shifts during the drilling of the 6 major bridge bents in Phase II
  • f the project
  • Weather permitting, this work will begin in January 2016

9

slide-10
SLIDE 10

30 Day Look Ahead

10

West of UPRR  Complete 24” Storm east of Caylor  Water line and Sanitary Sewer Service Taps  Rough grade, lime stabilize subgrade, fine grade, erect forms, place steel reinforcement, place concrete, cure, and saw cut for new roadway, intersection and driveway pavement  Install curbs and sidewalks  Install underground conduit for bridge lighting  Install temporary asphalt transitions from existing roadway to new concrete pavement East of UPRR  Complete all storm sewer lines  Complete 8” waterlines  Complete Sanitary sewer lines  Wet connects for water services  Clear and grub right of way for new roadway pavement  Rough grade, lime stabilize subgrade, fine grade, erect forms, place steel reinforcement, place concrete, cure, and saw cut for new roadway, intersection and driveway pavement  Traffic control switch from south to north side of Harrisburg to complete utility work in southeast quadrant

slide-11
SLIDE 11

Marketing Update for East End Businesses

  • Collaborated with the EEMD, the EECOC, Business Owners, and Residential

Stakeholders

  • Final Product is the East End Calendar of Events scheduled to start on

Wednesday, December 2

  • We have produced 5,000 flyers ( English/Spanish)
  • Posters printed and distributed
  • Banners – facilities will install
  • Radio Buys with Univision ( Estereo Latino)
  • Print ads with two week run of the front cover and two page spread due December 2

– (Que Onda)

  • Foam Arrows for business visibility
  • Individual Store flyers
  • Direct Mail/Door hangers

11

slide-12
SLIDE 12

Radio Spots

12