Harbour Island Force Main Replacement
South Neighborhood Association October 22, 2018
Design – Build Project
Harbour Island Force Main Replacement Design Build Project South - - PowerPoint PPT Presentation
Harbour Island Force Main Replacement Design Build Project South Neighborhood Association October 22, 2018 Agenda Project Update o Surge Facility Construction Update o Status of Route Study o First Segment of Harbour Island Force
Harbour Island Force Main Replacement
South Neighborhood Association October 22, 2018
Design – Build Project
Harbour Island Force Main along Water Street
roadway
PROS
in City Right-of-Way
Independent of New 54” Force Main CONS
Duration
PROS
in City Right-of-Way
CONS
Needed
Trust Approval Needed
PROS
Independent of New 54” Force Main
Inconvenience CONS
PROS
Independent of New 54” Force Main
Inconvenience CONS
Alternative Total Length (LF) Total Comparative Cost ($)
A 2,995 $825,075 B 1,660 $493,725 C 1,560 $405,825 D 1,600 $409,425
Easement Requirements For Alternative D - SNA
Proposal
permanent easement
easement over the east half of the TECO easement
more than 20’ below the deepest floor beneath the boat slip
Proposal
requirements still to be determined based
investigations
roadway
in the grass
work would be limited to one day
beautification of the area would be completed to the standards of the SNA
Weeks 1 2 3 4 5 6 7 8
Mobilize Onsite Construct New Force Main from Pump Station
Perform Directional Drill Across Channel
Install Pipe Across Channel Make Final Connections Shift Flows to New Line Restoration of Site (Landscaping and Irrigation)
emergency
mid-December 2018
route is selected
Community Task Force Meeting – Mid-November
Public Meeting #3 – Mid/Late November
Project Website: www.hiforcemain.com Project Hotline: (813) 235-4830