11111@
~
r5
st.peters
burg
www.stpete.org
PASADENA 36-INCH FORCE MAIN REPLACEMENT PROJECT PHASE III - - PowerPoint PPT Presentation
~ PASADENA 36-INCH FORCE MAIN REPLACEMENT PROJECT PHASE III ENGINEERING AND CAPITAL IMPROVEMENTS DEPARTMENT SEPTEMBER 2020 11111@ r5 st.peters burg www.stpete.org BACKGROUND The original Pasadena Transmission Force Main was
11111@
~
r5
burg
www.stpete.org
c
~'11111111
st.petersburg
www.stpete.org
wastewater flow to the Northwest Water Reclamation Facility.
following communities:
defunct Interpace Pipeline Corporation which was fabricated with tensioning wire that was susceptible to accelerated corrosion failure.
systematically replaced. Phases I and II of the Transmission Force Main replacement are complete and in service. This Project represents Phase III.
c
~'\WIii
re
st.petersburg
w w w . s t p e t e .
g
TIit Jungle tlb\.
'
l,.n11r• hi and C••t
P a r . H U H I s l a n d al'OIN~t~O 1'N0 (:~I(. 1M l l A e , . . a , e . aS~l""'8ff
(:l'l'Yd81 Pefet.eevRO"
:
! n n , A
!
~"
O N
·
!
I
NWMRF I I
I I
iq,111a.C..u•.-w•Y
1 1 1 ■ 1 z: C,01..._i ;
~:>.
= ;
~Otl,(;'l",V % 1stft P1 Ntttll fat+ 1 1 1 1 . , A . , , _ N
uu,Av•N
l,UtaAv•H
>
~P A S A D E N A 3 6 " F O R C E MA I N R E P L A C E M E N T · P H A S E I l l P r
e c t N
1 8 5 ~ 1 1 1
"
; ;
ti
~~ 211hAv9ff;
t , :
V: ;
n r
ltiU AYeH HanplgnDrN ltthAv•N 2 ttt,Asw•N"
fi
,ltt1AoN. 1
OailJnWllt...... 51rq.
: : r : 4 l t w. . . .
.
;; ?
"'
;;
B1111i119IDIIA"• 2nd Awastewater from the City’s Lift Station 61 Pasadena Master to the Northwest Water Reclamation Facility.
5,300 feet of 36-inch diameter ductile iron pipe between Lift Station 61 and 72nd Street N at 8th Avenue.
approximately 12 months.
c
~'11111111
st.petersburg
www.stpete.org
inconvenience and cost, maximize safety, and preserve residential roadways and tree canopies.
the existing defective pipe with new durable materials.
the replacement because of its rigidity, durability and expected service life.
avoided by utilizing trenchless methods such as jack and augering technology.
multiple Transmission Force Main pipe routes.
c
~'11111111
st.petersburg
www.stpete.org
lllllrt
s
.pete
www.stpete.org
c
~'11111111
st.petersburg
www.stpete.org
aware of:
Due to the location of the new Force Main pipe and the existing underground facilities, it will be necessary to temporarily close traffic lanes and detour traffic. The contractor will be required to maintain access for residences, businesses, St. Petersburg College, bus routes, emergency vehicles, mail delivery, solid waste collection, etc. throughout construction. Additionally, the Force Main pipe construction will be staged and limited to smaller portions of the overall project, and road restoration and opening will be performed as these stages of the pipe installation are completed.
The nature of construction will result in additional noise related to the construction activities. However, the contractor will be required to comply with the City noise control ordinance. The contractor will be required to use pumps with sound barriers suitable for residential areas to minimize noise during non-construction periods.
Dust and debris can be expected as related to the construction activities. However, the contractor will be required to apply water to dust producing areas and replace road pavement and grass as soon as practical. The contractor will be required to remove all extraneous construction debris on a daily basis.
c
~'\WIii
re
st.petersburg
www.stpete.org