Hampton Avenue Storm Drainage Improvement Project Christ Church - - PowerPoint PPT Presentation

hampton avenue storm drainage improvement project christ
SMART_READER_LITE
LIVE PREVIEW

Hampton Avenue Storm Drainage Improvement Project Christ Church - - PowerPoint PPT Presentation

Proposed Design and Easement Acquisition Hampton Avenue Storm Drainage Improvement Project Christ Church Charlotte November 1, 2018 Subtitle, date, client name, etc. Introduction of Staff Charlotte-Mecklenburg Storm Water Services Dane


slide-1
SLIDE 1

Subtitle, date, client name, etc.

Proposed Design and Easement Acquisition

Hampton Avenue Storm Drainage Improvement Project

Christ Church Charlotte November 1, 2018

slide-2
SLIDE 2

Subtitle, date, client name, etc.

Introduction of Staff

Charlotte-Mecklenburg Storm Water Services

Danée McGee - Project Manager Phone - 704-336-4102 E-mail - dmcgee@charlottenc.gov Doug Lozner - Watershed Area Manager Phone - 704-432-0964 E-mail - dlozner@charlottenc.gov

WK Dickson – Engineering Consultant

David Perry - Project Manager

City of Charlotte Real Estate Services

Kimberly Calhoun - Sr. Project Manager Phone - 704-353-0470 E-mail - Kimberly.calhoun@charlottenc.gov Randy Hosch - TELICS, Acquisition Agent Phone - 704-881-1724 E-mail - rhosch@telics.com

slide-3
SLIDE 3

Subtitle, date, client name, etc.

Reminders

  • Sign-In
  • Agenda
  • Customer Service Comment Cards
  • General question and answer period after

presentation

  • Property specific questions in small group break-out

sessions

slide-4
SLIDE 4

Subtitle, date, client name, etc.

Storm Water Services

  • Administrative Team
  • GIS
  • Financial Management
  • Water Quality Team
  • Public Education
  • Stream Restoration
  • Monitoring
  • Stormwater Control Measures
  • Construction
  • On-Call Contracts
  • Inspection Services
  • Planning Team
  • Asset Management
  • Service Request Evaluation
  • Design Management Team
  • Point Repair Projects
  • Engineering Team
  • Capital Improvement Projects
slide-5
SLIDE 5

Subtitle, date, client name, etc.

Agenda

  • Project Phases: Summary of project progress and

current status

  • Design Phase: Present the designed improvements
  • Permitting: Discussion of process
  • Real Estate: Discuss the easement acquisition process
  • Respond to general questions and concerns
  • Provide owners property-specific information on

property impacts

slide-6
SLIDE 6

Subtitle, date, client name, etc.

Project Phases

Planning June 2010 - February 2013 (Complete) Design Started Rehabilitation Approach October 2017

Easement Acquisition Typically 9 to 12 months, overlaps design Permitting Typically 3 to 9 months, overlaps design Bid Typically 7 to 8 months Construction Approximately 12 months

slide-7
SLIDE 7

Subtitle, date, client name, etc.

Design Phase

The Design phase generally consists of the following:

– Preliminary Design – Permitting – Easement Acquisition – Final Design

slide-8
SLIDE 8

Subtitle, date, client name, etc.

Design Phase

(Completed Tasks)

Preliminary Design

– Drainage system layout and location – Additional field survey – Utility coordination and design – Geotechnical investigations – Traffic control plans – Erosion control plans – Public meeting

slide-9
SLIDE 9

Subtitle, date, client name, etc.

Hampton Avenue Storm Drainage Improvements

David Perry, PE WK Dickson

slide-10
SLIDE 10

Subtitle, date, client name, etc.

Reasons for Project

  • Pipe sinkhole issues
  • Aging infrastructure
  • High on City priority ranking
slide-11
SLIDE 11

Subtitle, date, client name, etc. Sinkhole at Hampton Avenue and Malvern Drive Pipe condition is typical along Hampton Ave

slide-12
SLIDE 12

Subtitle, date, client name, etc. Existing pipe location at 2226 Beverly Drive

slide-13
SLIDE 13

Subtitle, date, client name, etc.

Upper Section

Filling Existing 36” RCP located by home foundation Add new 18” RCP and inlets Replace pipe and add new inlets Adding a new 48” RCP Location of existing sinkhole

Breakout table #1

slide-14
SLIDE 14

Subtitle, date, client name, etc.

Lower Section

Rehabilitate existing 48-inch diameter reinforced concrete pipe Rehabilitate existing dual 48-inch diameter corrugated metal pipe Adding new access structures to existing system FEMA Floodplain from Briar Creek

Breakout table #2

slide-15
SLIDE 15

Subtitle, date, client name, etc.

Elements of the Project

  • Existing Pipe Rehabilitation

– Cured-in-Place Pipe lining – Minimize impacts to neighborhood – Construct five new junction boxes over existing pipe for access – Increases pipe capacity slightly due to smoother interior

  • Pipe Relocation

– Take existing pipe out of service adjacent to foundation of 2226 Beverly Drive – Add system capacity with larger pipe in street

slide-16
SLIDE 16

Subtitle, date, client name, etc.

Elements of the Project

  • New Pipe Construction at Church Driveway

– Intercepts flows from church property – Reduces stormwater in street

  • New Curb and Pipe Construction at Malvern Road

– Curb re-aligned in corner to accommodate accessible ramp – New inlets added to accommodate new curbline – Pipe to existing inlet replaced

slide-17
SLIDE 17

Subtitle, date, client name, etc.

Tree Evaluations

City Arborist Recommendations

  • Tree pruning of branches
  • ver roadways
  • Diseased tree removal (due

to root rot)

  • Landscape Management

will do this work separately from the stormwater project

  • Removed trees will not be

replaced

  • No schedule for this work at

this time

Two trees with root rot to be removed at: 3021 and 2758 Hampton Avenue

slide-18
SLIDE 18

Subtitle, date, client name, etc.

Typical Site Impacts

  • HVAC Relocation

– Plan for temporary relocation

  • Landscaping / Hardscaping

– Irrigation – Fencing – Ornamentals – Temporary pet fencing – Outbuilding / shed

  • Foundation Protection

– What it is and why we would do it

Current project impacts due to the rehabilitation approach are limited to restoring grass or concrete disturbed by adjacent construction

slide-19
SLIDE 19

Subtitle, date, client name, etc.

Traffic Impacts

  • Lane Closures

– Continued traffic flow with single lane and flaggers

  • Road Closures

– Phased closures with marked detours – CMS (school buses), Police, Fire and Medic will be aware – In areas of closures driveways may not be accessible for some properties during portions of construction – On-street parking may be necessary – Closures will be as short as possible – Sidewalks will generally be accessible

Significantly decreased by rehabilitation approach

slide-20
SLIDE 20

Subtitle, date, client name, etc.

Traffic Impacts

Example Detour Plan

Work Area

slide-21
SLIDE 21

Subtitle, date, client name, etc.

FEMA Floodplain Impacts

100-Yr Future Floodplain Extents within Project Area

Peak flow from Hampton Ave.

  • ccurs approximately seven hours

prior to the peak flow from Briar Creek

slide-22
SLIDE 22

Subtitle, date, client name, etc.

Next Step - Complete Design Phase

Permitting

  • 401/404 permit (NC Dept. of Environmental Quality /

Army Corps of Engineers)

  • A Regional Permit is reviewed and issued by City

staff, and this review is already complete.

  • The channel and wetland impacts from this project

are very limited

  • DEMLR (NC Dept. of Energy, Mineral and Land

Resources/Erosion Control)

slide-23
SLIDE 23

Subtitle, date, client name, etc.

Next Step - Complete Design Phase

Easement Acquisition

  • An easement is a right to use land owned by another party

for a specific purpose.

  • Easements provide Storm Water Services with permission

from property owners to come onto their property and repair drainage problems and perform on-going maintenance.

  • Granting an easement does not reduce the size of your

property, but it does create some limitations on the use of the area.

slide-24
SLIDE 24

Subtitle, date, client name, etc.

Storm Drainage Easement (SDE) Grants access to a specific portion of the property for the purpose

  • f repairing and maintaining a storm drainage system.

Temporary Construction Easement (TCE) Are not permanent easements. They give us the right to access your property to construct this project only. Sidewalk and Utility Easement (SUE) Grants access to a specific portion of the property for the purpose

  • f construction and use of sidewalk.

Permanent Utility Easement (PUE) Grants access to a specific portion of the property for the purpose

  • f construction and use of above- or below-ground utilities.

Next Step - Complete Design Phase

slide-25
SLIDE 25

Subtitle, date, client name, etc.

Next Step - Complete Design Phase

Final Design

  • All permits have been obtained
  • All easements have been acquired
  • Construction plans are completed

Bid Phase

  • Bid advertisement
  • Bid opening – Lowest Qualified Bidder
  • Recommendation for approval and City Council award
  • Pre-construction meeting
slide-26
SLIDE 26

Subtitle, date, client name, etc.

  • Notification to residents
  • Utility relocations happen prior to construction
  • Contractor is given a Notice to Proceed
  • Emails or mailers with progress updates
  • Final walk through with contractor
  • Accept project
  • Start warranty phase (1 year)
  • City Inspectors will be on site daily during

construction and are the point of contact for the public regarding the project

Construction

slide-27
SLIDE 27

Subtitle, date, client name, etc.

  • Project Webpage:

https://charlottenc.gov/StormWater/Projects/Pages/H amptonAvenue.aspx

  • QR Code:

Project Information

slide-28
SLIDE 28

Subtitle, date, client name, etc.

What Happens Now?

  • A representative (Randy Hosch) from Telics will contact

you if we need an easement for construction and/or maintenance purposes

We will NOT have another public meeting prior to bid and construction

  • Please remember to sign-in and fill out a customer

service card

  • The City and our consultants will stay here to answer any

specific questions you may have regarding impacts to your property or general information about this project

Thank you for coming to the meeting!