Subtitle, date, client name, etc.
Proposed Design and Easement Acquisition
Hampton Avenue Storm Drainage Improvement Project
Christ Church Charlotte November 1, 2018
Hampton Avenue Storm Drainage Improvement Project Christ Church - - PowerPoint PPT Presentation
Proposed Design and Easement Acquisition Hampton Avenue Storm Drainage Improvement Project Christ Church Charlotte November 1, 2018 Subtitle, date, client name, etc. Introduction of Staff Charlotte-Mecklenburg Storm Water Services Dane
Subtitle, date, client name, etc.
Christ Church Charlotte November 1, 2018
Subtitle, date, client name, etc.
Charlotte-Mecklenburg Storm Water Services
Danée McGee - Project Manager Phone - 704-336-4102 E-mail - dmcgee@charlottenc.gov Doug Lozner - Watershed Area Manager Phone - 704-432-0964 E-mail - dlozner@charlottenc.gov
WK Dickson – Engineering Consultant
David Perry - Project Manager
City of Charlotte Real Estate Services
Kimberly Calhoun - Sr. Project Manager Phone - 704-353-0470 E-mail - Kimberly.calhoun@charlottenc.gov Randy Hosch - TELICS, Acquisition Agent Phone - 704-881-1724 E-mail - rhosch@telics.com
Subtitle, date, client name, etc.
presentation
sessions
Subtitle, date, client name, etc.
Subtitle, date, client name, etc.
current status
property impacts
Subtitle, date, client name, etc.
Planning June 2010 - February 2013 (Complete) Design Started Rehabilitation Approach October 2017
Easement Acquisition Typically 9 to 12 months, overlaps design Permitting Typically 3 to 9 months, overlaps design Bid Typically 7 to 8 months Construction Approximately 12 months
Subtitle, date, client name, etc.
The Design phase generally consists of the following:
– Preliminary Design – Permitting – Easement Acquisition – Final Design
Subtitle, date, client name, etc.
Preliminary Design
– Drainage system layout and location – Additional field survey – Utility coordination and design – Geotechnical investigations – Traffic control plans – Erosion control plans – Public meeting
Subtitle, date, client name, etc.
David Perry, PE WK Dickson
Subtitle, date, client name, etc.
Subtitle, date, client name, etc. Sinkhole at Hampton Avenue and Malvern Drive Pipe condition is typical along Hampton Ave
Subtitle, date, client name, etc. Existing pipe location at 2226 Beverly Drive
Subtitle, date, client name, etc.
Filling Existing 36” RCP located by home foundation Add new 18” RCP and inlets Replace pipe and add new inlets Adding a new 48” RCP Location of existing sinkhole
Breakout table #1
Subtitle, date, client name, etc.
Rehabilitate existing 48-inch diameter reinforced concrete pipe Rehabilitate existing dual 48-inch diameter corrugated metal pipe Adding new access structures to existing system FEMA Floodplain from Briar Creek
Breakout table #2
Subtitle, date, client name, etc.
– Cured-in-Place Pipe lining – Minimize impacts to neighborhood – Construct five new junction boxes over existing pipe for access – Increases pipe capacity slightly due to smoother interior
– Take existing pipe out of service adjacent to foundation of 2226 Beverly Drive – Add system capacity with larger pipe in street
Subtitle, date, client name, etc.
– Intercepts flows from church property – Reduces stormwater in street
– Curb re-aligned in corner to accommodate accessible ramp – New inlets added to accommodate new curbline – Pipe to existing inlet replaced
Subtitle, date, client name, etc.
City Arborist Recommendations
to root rot)
will do this work separately from the stormwater project
replaced
this time
Two trees with root rot to be removed at: 3021 and 2758 Hampton Avenue
Subtitle, date, client name, etc.
– Plan for temporary relocation
– Irrigation – Fencing – Ornamentals – Temporary pet fencing – Outbuilding / shed
– What it is and why we would do it
Current project impacts due to the rehabilitation approach are limited to restoring grass or concrete disturbed by adjacent construction
Subtitle, date, client name, etc.
– Continued traffic flow with single lane and flaggers
– Phased closures with marked detours – CMS (school buses), Police, Fire and Medic will be aware – In areas of closures driveways may not be accessible for some properties during portions of construction – On-street parking may be necessary – Closures will be as short as possible – Sidewalks will generally be accessible
Significantly decreased by rehabilitation approach
Subtitle, date, client name, etc.
Example Detour Plan
Work Area
Subtitle, date, client name, etc.
100-Yr Future Floodplain Extents within Project Area
Peak flow from Hampton Ave.
prior to the peak flow from Briar Creek
Subtitle, date, client name, etc.
Army Corps of Engineers)
staff, and this review is already complete.
are very limited
Resources/Erosion Control)
Subtitle, date, client name, etc.
for a specific purpose.
from property owners to come onto their property and repair drainage problems and perform on-going maintenance.
property, but it does create some limitations on the use of the area.
Subtitle, date, client name, etc.
Storm Drainage Easement (SDE) Grants access to a specific portion of the property for the purpose
Temporary Construction Easement (TCE) Are not permanent easements. They give us the right to access your property to construct this project only. Sidewalk and Utility Easement (SUE) Grants access to a specific portion of the property for the purpose
Permanent Utility Easement (PUE) Grants access to a specific portion of the property for the purpose
Subtitle, date, client name, etc.
Final Design
Bid Phase
Subtitle, date, client name, etc.
construction and are the point of contact for the public regarding the project
Subtitle, date, client name, etc.
https://charlottenc.gov/StormWater/Projects/Pages/H amptonAvenue.aspx
Subtitle, date, client name, etc.
you if we need an easement for construction and/or maintenance purposes
service card
specific questions you may have regarding impacts to your property or general information about this project