HALL MIDDLE SCHOOL F I E L D R E P L A C E M E N T P R O J E C T - - PowerPoint PPT Presentation

hall middle school
SMART_READER_LITE
LIVE PREVIEW

HALL MIDDLE SCHOOL F I E L D R E P L A C E M E N T P R O J E C T - - PowerPoint PPT Presentation

HALL MIDDLE SCHOOL F I E L D R E P L A C E M E N T P R O J E C T FIELD USE Joint Use Agreement with Larkspur Parks and Recreation and Larkspur-Corte Madera School District School Use during the School Day Sports Leagues use


slide-1
SLIDE 1

F I E L D R E P L A C E M E N T P R O J E C T

HALL MIDDLE SCHOOL

slide-2
SLIDE 2

FIELD USE

  • Joint Use Agreement with Larkspur Parks and

Recreation and Larkspur-Corte Madera School District

  • School Use during the School Day
  • Sports Leagues use afternoons, evenings, and

weekends

  • Field Scheduling and Maintenance through Parks

and Recreation

slide-3
SLIDE 3

YEAR-ROUND USE

  • Current Field is artificial turf, allowing all-year use
  • Youth and Adult Leagues
  • Soccer, Lacrosse, Rugby, Baseball
  • Available for other community uses when not

booked

slide-4
SLIDE 4

FIELD SPECS

  • Artificial Turf, Crumb Rubber, installed 2004
  • Drainage system installed to prevent standing water
  • Soils prepared for artificial turf
  • Life of artificial turf 12-14 years
  • Maintenance has included “brushing” crumb

rubber

slide-5
SLIDE 5

MILLER CREEK MIDDLE SCHOOL NEW TURF FIELD

slide-6
SLIDE 6

FIELD REPLACEMENT PROCESS

  • Consulting for Field Replacement – Carducci and

Associates

  • Site Assessments
  • DSA Preview
  • Public Meetings
slide-7
SLIDE 7

FIELD REPLACEMENT TIMELINE

DRAFT Hall Middle School – Field Replacement Timeline

  • Nov 15-30
  • Prepare Access Compliance Plan
  • Nov 18 - LCMSD Board Meeting/Summary Budget and

Schedule

  • Nov 23 - Public Outreach for Community Input
  • Dec-March - City/District Committee meet to discuss options
  • Dec 1
  • Submit ADA Plan to DSA
  • Jan-Feb
  • Ongoing Board Agenda and Public Input
  • Jan 4-Feb15
  • Develop Plans and Specs
  • Feb 9-March 30
  • DSA Backcheck/Approval ADA Plan
  • Feb 24 - LCMSD Approval/District to Public Bid Process
  • Feb 26-May 6 - Bid process
  • April 20 - LCMSD Board approval award contract
  • April 22-May 19 - Submittals and Review
  • May 20-July 14 - Procurement
  • June 17-Aug 17 - Construction (mobilization/demolition/repair/install)