Giant Mine Interim Underground Stabilization Plan– 2013
Work Plan Review – Aug 23, 2013
MV2007L8-0031
Giant Mine Interim Underground Stabilization Plan 2013 Mitigation - - PowerPoint PPT Presentation
MV2007L8-0031 Work Plan Review Aug 23, 2013 Giant Mine Interim Underground Stabilization Plan 2013 Mitigation Sequence Strategy A phased mitigation sequence that addresses previously identified geotechnical hazard priority but also
MV2007L8-0031
A phased mitigation sequence that addresses previously identified
1.
2.
This area provides a good area for commissioning of paste
3.
December 16, 2013 2
December 16, 2013 3
1.
2.
3.
4.
5.
6.
7.
December 16, 2013 4
December 16, 2013 5
Mini Stockpiles Truck Wash
Surface boreholes required for:
December 16, 2013 6
C&M contractor currently only maintains minimal underground
A process to assess hazards for re-entry into old mining areas,
December 16, 2013 7
Underground drilling into voids that cannot be intersected reasonably
December 16, 2013 8
In some cases drilling boreholes from surface directly into the targeted
Voids under arsenic stopes. Voids under Baker Creek (e.g. 1-18 stope Upper) Etc. Vertical boreholes will be drilled to safely accessible underground
December 16, 2013 9
Once ground support is up-to-date, fill fences can be installed. Barricades do not need to be completely tight to the back and ~ 90-95%
December 16, 2013 10
Borehole emplaced barricades do not need to be completely tight to the
Low slump paste
Similar to those attempted for FOS with concrete, but using cemented
Expanding foam barricades.
December 16, 2013 11
Produce Paste and Place It Underground Monitor Filling Success Using Camera’s and Cavity Surveys in
Show Video
December 16, 2013 12
December 16, 2013 13
We need to test
Paste Mixes Drift Barricades
December 16, 2013 14